Procurement Flashcards

1
Q
  1. Pre-Qualification Questionnaire
A
  • Assess potential bidders (H&S, QA, experience, resources, financial security)
  • Reduce list of suppliers (saves time)
  • Questions such as cash-flow, financial stability
  • Use of Yes/No questions - quicker for both parties
  • Can sometimes use pre-determined suppliers (accredited)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. Tendering/Bidding
A
  • Structured, fair and objective
  • Pre-agreed evaluation criteria (weighting)
  • ITT issued, detailed document, follows procurement rules
  • Bidders can ask questions but answers must be shared with all
  • Clear pricing model so that they can easily be assessed against one another
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. Evaluating
A
  • Deadline for bids, and clear/transparent process to avoid accusations of bias
  • Price broken down into different elements (installation, parts, commissioning etc)
  • Delivery - overall delivery maybe key criteria, schedule and milestones
  • Capability and capacity
  • Quality processes - accreditation e.g. ISO 9000
  • Suppliers can be asked to present solutions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. Negotiations and Contract Award
A
  • Contractor invited for review and clarification

- Contract awarded - debrief of unsuccessful bidders, and feedback