Procurement Flashcards

1
Q

What is the apportionment of risk under Traditional procurement

A

Client - quality of the design
Contractor - time and quality of the build

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the apportionment of risk under D&B procurement

A

Client - Management of the contractor and design team
Contractor - Time, Quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the apportionment of risk under Management Contracting procurement

A

Client - Design, Cost
Contractor - Time, Subcontractor performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the apportionment of risk under Construction Management procurement

A

Client - Design, Cost, Time, subcontractor performance
Contractor - Nothing (just manages)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly