Processes Key Inputs/Tools/Outputs Flashcards
Develop Project Charter
Business Docs, agreements / /project charter, assumptions log
Develop project management plan
outputs from other process / / PM Plan
direct and manage project work
PM Plan, approved change requests / / deliverables, work performance data, issue log
Manage Project Knowledge
Deliverables / knowledge management, information management / lessons learned register
Monitor and Control Project Work
PM plan, wpi / / wpr
perform integrated change control
change requests / / approved change requests, project documents updates (change log)
Close Project or Phase
accepted deliverables / / final report, final product or service or transition, project document updates (llr)
plan scope management
pm plan / / scope management plan, requirements management plan
collect requirements
PM plan (scope, requirements, stakeholder engagement plan) / data representation, data gathering, decision making / requirements documentation, requirements traceability matrix
Define Scope
project docs (requirements docs) / data analysis (alternative analysis) , product analysis (value analysis) / project scope statement
create wbs
pm plan (scope mp) / decomposition / scope baseline
validate scope
verified deliverables / inspection / accepted deliverables
control scope
wpd / data analytics / wpi
plan schedule management
/ / schedule management plan (PM plan)
Define Activities
PM Plan (schedule mp, scope baseline) / decomposition, rolling wave planning / activity list, activity attributes
Sequence Activities
activity list, milestone list / precedence diagramming method, dependency determination and integration, leads and lags / project schedule network diagram
Estimate Activity Duration
Project docs (resource calendar, activity list, resource requirements) / analogous estimating, parametric estimating, three point estimating / duration estimates
develop schedule
project documents ( activity list, duration estimates, project schedule network diagram) / cpm, resource optimization (resource leveling, smoothing), agile release planning, leads and lags, schedule compression / schedule baseline (pm plan), project schedule
control schedule
/ data analysis (iteration burndown chart) / wpi, schedule forecasting, change requests