Process Name, Process Group, Main Outputs Flashcards

1
Q

Develop Project Charter

A

Initiating; Project Charter, Assumption Log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Develop Project Management Plan

A

Planning; Project Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Direct and Manage Project Work

A

Executing; Deliverables, Work Performance Data, Issue Log, Change Request

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Manage Project Knowledge

A

Executing; Lessons Learned Register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Monitor and Control Project Work

A

Monitoring and Controlling; Work Performance Reports, Change Requests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Perform Integrated Change Control

A

Monitoring and Controlling; Approved Change Request

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Close Project or Phase

A

Closing; Final Product, Service, or Result, Transition and Final Report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Plan Scope Management

A

Planning; Scope Management Plan, Requirement Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Collect Requirements

A

Planning; Requirement Documentation, Requirement Traceability Matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Define Scope

A

Planning; Project Scope Statement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Create WBS

A

Planning; Scope Baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Validate Scope

A

Monitoring and Controlling; Accepted Deliverables, Work Performance Information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Control Scope

A

Monitoring and Controlling; Change Request, Work Performance Information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Plan Schedule Management

A

Planning; Schedule Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Define Activities

A

Planning; Activity List, Activity Attributes, milestone List

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Sequence Activities

A

Planning; Project Schedule Network Diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Estimate Activity Durations

A

Planning; Activity Duration Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Develop Schedule

A

Planning; Schedule Baseline, Project Schedule, Schedule Data, Project Calendars

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Control Schedule

A

Monitoring and Controlling; Work Performance Inforemation, Change Request

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Plan Cost Management

A

Planning; Cost Management Plan

21
Q

Estimate Costs

A

Planning; Cost Estimates, Basis of the Estimates

22
Q

Determine Budget

A

Planning; Cost Baseline, Project Funding Requirements

23
Q

Control Costs

A

Monitoring and Controlling; Work Performance Information, Change Requests, Cost Forecasts

24
Q

Plan Quality Management

A

Planning; Quality Management Plan, Quality Metrics

25
Q

Manage Quality

A

Executing; Quality Reports, Test and Evaluation Documents

26
Q

Control Quality

A

Monitoring and Controlling; Quality Control Measurements, Verified Deliverables, Work Performance Information

27
Q

Plan Resource Management

A

Planning; Resource Management Plan, Team Charter

28
Q

Estimate Activity Resources

A

Planning; Resource Requirements, Resource Breakdown Structure, Basis of Estimates

29
Q

Acquire Resources

A

Executing; Physical Resource Assignments, Project Team Assignments, Resource Calendar

30
Q

Develop Team

A

Executing; Team Performance Assessments, Change Requests

31
Q

Manage Team

A

Executing; Change Requests

32
Q

Control Resources

A

Monitoring and Controlling; Work Performance Information, Change Requests

33
Q

Plan Communications Management

A

Planning; Communications Management Plan

34
Q

Manage Communications

A

Executing; Project Communications

35
Q

Monitor Communications

A

Monitoring and Controlling; Work Performance Information, Change Request

36
Q

Plan Risk Management

A

Planning; Risk Management Plan

37
Q

Identify Risks

A

Planning; Risk Register, Risk Report

38
Q

Perform Qualitative Risk Analysis

A

Planning; Project Documents Updates

39
Q

Perform Quantitative Risk Analysis

A

Planning; Project Documents Updates

40
Q

Plan Risk Responses

A

Planning; Change Request, Project Documents Updates, Project Mangement Plan Updates

41
Q

Implement Risk Responses

A

Executing; Change Requests

42
Q

Monitor Risks

A

Monitoring and Controlling; Work Performance Information, Change Requests

43
Q

Plan Procurement Management

A

Planning; Procurement Management Plan

44
Q

Conduct Procurements

A

Executing; Project Documents, Acquire Resources

45
Q

Control Procurements

A

Monitoring and Controlling; Closed Procurements, Work Performance Information, Change Requests

46
Q

Identify Stakeholders

A

Initiating; Stakeholder Register

47
Q

Plan Stakeholder Engagement

A

Planning; Stakeholder Engagement Plan

48
Q

Manage Stakeholder Engagement

A

Executing; Change Request

49
Q

Monitor Stakeholder Engagement

A

Monitoring and Controlling; Work Performance Information, Change Request