Process Management Process Groups (Page 61) Flashcards

1
Q

What are the 5 Process Groups?

A
  1. INITIATING Process Group
  2. PLANNING Process Group
  3. EXECUTING Process Group
  4. MONITORING and CONTROLLING Process Group
  5. CLOSING Process Group
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the 10 Knowledge Areas?

A

4) Project INTEGRATION Management
5) Project SCOPE Management
6) Project TIME Management
7) Project COST Management
8) Project QUALITY Management
9) Project HUMAN RESOURCES Management
10) Project COMMUNICATIONS Management
11) Project RISK Management
12) Project PROCUREMENT Management
13) Project STAKEHOLDER Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

INITIATING Process Group x Project INTEGRATION Management

A

INITIATE x INTEGRATION

4.1 - Develop Project Charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

INITIATING Process Group x Project STAKEHOLDER Management

A

INITIATE x STAKEHOLDER

13.1 - Identify Stakeholders

(Think “IStakeholder)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

PLANNING Process Group x Project INTEGRATION Management

A

PLANNING x INTEGRATION

4.2 - Develop Project Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

PLANNING Process Group x Project SCOPE Management

A

PLANNING x SCOPE

  1. 1 - Plan Scope Management
  2. 2 - Collect Requirements
  3. 3 - Define Scope
  4. 4 - Create WBS
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

PLANNING Process Group x Project TIME Management

A

PLANNING x SCOPE

  1. 1 - Plan Schedule Management
  2. 2 - Define Activities
  3. 3 - Sequence Activities
  4. 4 - Estimate Activity Resources
  5. 5 - Estimate Activity Durations
  6. 6 - Develop Schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

PLANNING Process Group x Project COST Management

A

PLANNING x COST

  1. 1 - Plan Cost Management
  2. 2 - Estimate Costs
  3. 3 - Determine Budget
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

PLANNING Process Group x Project QUALITY Management

A

PLANNING x QUALITY

8.1 - Plan Quality Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

PLANNING Process Group x Project HUMAN RESOURCE Management

A

PLANNING x HUMAN RESOURCE

9.1 - Plan Human Resource Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

PLANNING Process Group x Project COMMUNICATIONS Management

A

PLANNING x COMMUNICATIONS

10.1 - Plan Communications Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

PLANNING Process Group x Project RISK Management

A

PLANNING x RISK

  1. 1 - Plan Risk Management
  2. 2 - Identify Risks
  3. 3 - Perform Qualitative Risk Analysis
  4. 4 - Perform Quantitative Risk Analysis
  5. 5 - Plan Risk Responses
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

PLANNING Process Group x Project PROCUREMENT Management

A

PLANNING x PROCUREMENT

12.1 - Plan Procurement Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

PLANNING Process Group x Project STAKEHOLDER Management

A

PLANNING x STAKEHOLDER

13.2 - Plan Stakeholder Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

EXECUTING Process Group x Project INTEGRATION Management

A

EXECUTING x INTEGRATION

4.3 - Direct and Manage Project Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

EXECUTING Process Group x Project QUALITY Management

A

EXECUTING x QUALITY

8.2 - Perform Quality Assurance

17
Q

EXECUTING Process Group x Project HUMAN RESOURCE Management

A

EXECUTING x HUMAN RESOURCE

  1. 2 - Acquire Project Team
  2. 3 - Develop Project Team
  3. 4 - Manage Project Team
18
Q

EXECUTING Process Group x Project COMMUNICATIONS Management

A

EXECUTING x COMMUNICATIONS

10.2 - Manage Communications

19
Q

EXECUTING Process Group x Project PROCUREMENT Management

A

EXECUTING x PROCUREMENT

12.2 - Conduct Procurements

20
Q

EXECUTING Process Group x Project STAKEHOLDER Management

A

EXECUTING x STAKEHOLDER

13.3 Manage Stakeholder Engagement

21
Q

MONITORING and CONTROLLING Process Group x Project INTEGRATION Management

A

MONITORING and CONTROLLING x INTEGRATION

  1. 4 - Monitor and Control Project Work
  2. 5 - Perform Integrated Change Control
22
Q

MONITORING and CONTROLLING Process Group x Project SCOPE Management

A

MONITORING and CONTROLLING x SCOPE

  1. 5 - Validate Scope
  2. 6 - Control Scope
23
Q

MONITORING and CONTROLLING Process Group x Project TIME Management

A

MONITORING and CONTROLLING x TIME

6.7 - Control Schedule

24
Q

MONITORING and CONTROLLING Process Group x Project COST Management

A

MONITORING and CONTROLLING x COST

7.4 - Control Costs

25
Q

MONITORING and CONTROLLING Process Group x Project QUALITY Management

A

MONITORING and CONTROLLING x QUALITY

8.3 - Control Quality

26
Q

MONITORING and CONTROLLING Process Group x Project COMMUNICATIONS Management

A

MONITORING and CONTROLLING x COMMUNICATIONS

10.3 - Control Communications

27
Q

MONITORING and CONTROLLING Process Group x Project RISK Management

A

MONITORING and CONTROLLING x RISK

11.6 - Control Risks

28
Q

MONITORING and CONTROLLING Process Group x Project PROCUREMENT Management

A

MONITORING and CONTROLLING x PROCUREMENT

12.3 - Control Procurements

29
Q

MONITORING and CONTROLLING Process Group x Project STAKEHOLDER Management

A

MONITORING and CONTROLLING x STAKEHOLDER

13.3 - Manage Stakeholder Engagement

30
Q

CLOSING Process Group x Project INTEGRATION Management

A

CLOSING x INTEGRATION

4.6 - Close Project or Phase

31
Q

CLOSING Process Group x Project PROCUREMENT Management

A

CLOSING x PROCUREMENT

12.4 - Close Procurement