1
Q

What are the 5 Process Groups?

A
Initiating
Planning
Executing
Monitoring and Controlling
Closing
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the 10 Knowledge Areas?

A

Integration, Scope, Time, Cost
Quality, Human Resources, Communications
Risk, Procurement, Stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the Project Integration Management Processes and what Process groups are each in?

A

Integration Management has 6 Processes in 5 Process Groups:
Develop Charter (Initiating), Develop Project Management Plan (Planning), Work and Manage Project (Executing)
Monitor and Control Project (Monitoring and Controlling) Perform Integrated Change Control (Monitoring and Controlling), Close Project or Phase (Closing)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the Project Scope Management Processes and what Process groups are each in?

A

Scope Management has 6 processes in 2 Process Groups:
Develop Scope Management Plan (Planning)
Collect Requirements (Planning)
Define Scope (Planning)
Create WBS (Planning)
Validate Scope (Monitoring and Controlling)
Control Scope (Monitoring and Controlling)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the Project Time Management Processes and what Process groups are each in?

A

Time Management has 7 processes in 2 Process Groups:
Develop Time Management Plan (Planning), Define Activities (Planning)
Sequence Activities(Planning), Estimate Activity Resources (Planning)
Estimate Activity Durations (Planning), Develop Schedule (Planning)
Control Schedule (Monitoring and Controlling)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the Project Cost Management Processes and what Process groups are each in?

A

Cost Management has 4 processes in 2 Process Groups:
Develop Cost Management Plan (Planning)
Estimate Costs (Planning)
Develop Budget (Planning)
Control Costs (Monitoring and Controlling)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the Project Quality Management Processes and what Process groups are each in?

A

Quality Management has 3 processes in 3 Process Groups:
Develop Quality Management Plan (Planning)
Perform Quality Assurance (Executing)
Control Quality (Monitoring and Controlling)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the Project Human Resources Management Processes and what Process groups are each in?

A
Human Resources Management has 4 processes in 2 Process Groups:
Develop Human Resources Plan (Planning)
Acuire Team (Executing)
Develop Team (Executing)
Manage Team (Executing)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the Project Communications Management Processes and what Process groups are each in?

A

Communications Management has 3 processes in 3 Process Groups:
Develop Communication Management Plan (Planning)
Manage Communications (Executing)
Control Communications (Monitoring and Controlling)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the Project Risk Management Processes and what Process groups are each in?

A

Risk Management has 6 processes in 2 Process Groups:
Develop Risk Management Plan (Planning), Identify Risks (Planning)
Perform Qualitative Risk Analysis (Planning),Perform Quantitative Risk Analysis (Planning),Plan Risk Response (Planning)
Control Risk (Monitoring and Controlling)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the Project Procurement Management Processes and what Process groups are each in?

A

Project Procurement Management has 4 processes in 4 Process Groups:
Develop Procurement Plan (Planning)
Conduct Procurements (Executing)
Control Procurements (Monitoring and Controlling)
Close Procurements (Closing)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the Project Stakeholder Management Processes and what Process groups are each in?

A

Stakeholder Management has 4 processes in 4 Processes Groups:
Identify Stakeholders (Initiating)
Develop Stakeholder Management Plan (Planning)
Manage Stakeholder Engagement (Executing)
Control Stakeholder Engagement (Monitoring and Controlling)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the only two processes in the Initiating Process Group and what 2 Knowledge areas are they in?

A
Develop Project Charter (Project Integration Management)
Identify Stakeholders ( Project Stakeholder Management)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the only two processes in the Closing Process Group and what 2 Knowledge areas are they in?

A
Close Project or Phase (Project Integration Management)
Close Procurements (Project Procurement Management)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the only Knowledge area that does not have a process in the Monitoring and Controlling Process Group?

A
Project Management Human Resources.
It has 4 Processes none of which are in the Monitoring and Controlling Group:
Develop Human Resources Plan (Planning)
Acuire Team (Executing)
Develop Team (Executing)
Manage Team (Executing)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How man processes are there within the Knowledge Groups?

A

There are 47 total processes

17
Q

How many processes are there in the Initiating Process Group?

A

The Initiating Process Group has 2 processes
Develop Project Charter (Project Integration Management)
Identify Stakeholders ( Project Stakeholder Management)

18
Q

What Process Group has the most processes and how many are there?

A

The Planning Process Group has the most processes with 24 in total

19
Q

How many processes are in the Executing Process Group?

A

The Executing Process Group has 7 Processes
Direct and Manage Work (Integration)
Perform Quality Assurance (Quality)
Acquire Team, Develop Team, Manage Team (HR)
Manage Communications (Comm.)
Conduct Procurements (Procurements)
Manage Stakeholder Engagement (Stakeholder)

20
Q

How many processes are in the Monitoring and Controlling Process Group?

A

There are 11 processes in the Monitoring and Controlling Process Group.

*Only one of these processes does not have the word Control in it’s name, Validate Scope from the Project Scope Management Knowledge Area