PRINCE2 Glossary Terms (Managing Successful Projects with PRINCE2 (Textbook 2017 EDITION)) Flashcards
Complete glossary of terms for PRINCE2 (2017 Edition)
Accept (risk response)
A risk response that means that the organization takes the chance that the risk will occur, with full impact on objectives if it does.
Acceptance
The formal act of acknowledging that the project has met agreed acceptance criteria and thereby met the requirements of its stakeholders.
Acceptance criteria
A prioritized list of criteria that the project product must meet before the customer will accept it (i.e., measurable definitions of the attributes required for the set of products to be acceptable to key stakeholders).
Activity
A process, function or task that occurs over time, has recognizable results and is managed. It is usually defined as part of a process or plan.
Agile and agile methods
A broad term for a collection of behaviours, frameworks, concepts and techniques that go together to enable teams and individuals to work in an agile way that is typified by collaboration, prioritization, iterative and incremental delivery, and timeboxing. There are several specific methods (or frameworks) that are classed as agile, such as Scrum and Kanban. PRINCE2 is completely compatible with working in an agile way.
Approval
The formal confirmation that a product is complete and meets its requirements (less any concessions) as defined by its product description.
Approver
The person or group (e.g., a project board) who is identified as qualified and authorized to approve a (management or specialist) product as being complete and fit for purpose.
Asset
An item, thing or entity that has potential or actual value to an organization [ISO 55000:2014].
Assumption
A statement that is taken as being true for the purposes of planning, but which could change later. An assumption is made where some facts are not yet known or decided, and is usually reserved for matters of such significance that, if they change or turn out not to be true, there will need to be considerable replanning.
Assurance
All the systematic actions necessary to provide confidence that the target (e.g., system, process, organization, programme, project, outcome, benefit, capability, product output or deliverable) is appropriate. Appropriateness might be defined subjectively or objectively in different circumstances. The implication is that assurance will have a level of independence from that which is being assured. See also project assurance; quality assurance.
Authority
The right to allocate resources and make decisions (applies to project, management stage and team levels).
Authorization
The point at which an authority is granted.
Avoid (risk response)
A risk response to a threat where the threat either can no longer have an impact or can no longer happen.
Backlog
A list of new features for a product. The list may be made up of user stories which are structured in a way that describes who wants the feature and why.
Baseline
Reference levels against which an entity is monitored and controlled.
Baseline management product
A type of management product that defines aspects of the project and, when approved, is subject to change control.
Benefit
The measurable improvement resulting from an outcome perceived as an advantage by one or more stakeholders.
Benefits management approach
An approach that defines the benefits management actions and benefits reviews that will be put in place to ensure that the project’s outcomes are achieved and to confirm that the project’s benefits are realized.
Benefits tolerance
The permissible deviation in the expected benefit that is allowed before the deviation needs to be escalated to the next level of management. Benefits tolerance is documented in the business case. See also tolerance.
Burn chart
A technique for showing progress (e.g., such as with a timebox), where work that is completed and work still to do are shown with one or more lines that are updated regularly or daily.
Business case
The justification for an organizational activity (project), which typically contains timescales, costs, benefits and risks, and against which continuing viability is tested.
Centre of excellence
A corporate coordinating function for portfolios, programmes and projects providing standards, consistency of methods and processes, knowledge management, assurance and training.
Change authority
A person or group to which the project board may delegate responsibility for the consideration of requests for change or off-specifications. The change authority may be given a change budget and can approve changes within that budget.
Change budget
The money allocated to the change authority available to be spent on authorized requests for change.
Change control approach
A description of how and by whom the project’s products will be controlled and protected.
Checkpoint
A team-level, time-driven review of progress.
Checkpoint report
A progress report of the information gathered at a checkpoint, which is given by a team to the project manager and which provides reporting data as defined in the work package.
Closure recommendation
A recommendation prepared by the project manager for the project board to send as a project closure notification when the board is satisfied that the project can be closed.
Communication management approach
A description of the means and frequency of communication between the project and its stakeholders.
Concession
An off-specification that is accepted by the project board without corrective action.
Configuration item
An entity that is subject to change control. The entity may be a component of a product, a product or a set of products in a release.
Configuration item record
A record that describes the status, version and variant of a configuration item, and any details of important relationships between them.
Configuration management
Technical and administrative activities concerned with the controlled change of a product.
Configuration management system
The set of processes, tools and databases that are used to manage configuration data. Typically, a project will use the configuration management system of either the customer or supplier organization.
Constraints
The restrictions or limitations by which the project is bound.
Contingent plan
A plan intended for use only if required (e.g., if a risk response is not successful). Often called a fallback plan.
Corporate, programme management or customer standards
These are overarching standards to which the project must adhere. They will influence the four project approaches (communication management, change control, quality management and risk management) and the project controls.
Corrective action
A set of actions to resolve a threat to a plan’s tolerances or a defect in a product.
Cost tolerance
The permissible deviation in a plan’s cost that is allowed before it needs to be escalated to the next level of management. Cost tolerance is documented in the respective plan. See also tolerance.
Customer
The person or group who commissioned the work and will benefit from the end results.
Customer’s quality expectations
A statement about the quality expected from the project product, captured in the project product description.
Daily log
A log used to record problems/concerns that can be handled by the project manager informally.
Deliverable
See output.
Delivery approach
The specialist approach used to create the products.
Delivery step
A step within the delivery approach.
Dependency (plan)
A dependency means that one activity is dependent on another. There are at least two types of dependency relevant to a project: internal and external. An internal dependency is one between two project activities. In these circumstances the project team has control over the dependency. An external dependency is one between a project activity and a non-project activity, where non-project activities are undertaken by people who are not part of the project team. In these circumstances the project team does not have complete control over the dependency.
Dis-benefit
A measurable decline resulting from an outcome perceived as negative by one or more stakeholders, which reduces one or more organizational objective(s).
Embedding (PRINCE2)
The act of making something an integral part of a bigger whole. Embedding is what an organization needs to do to adopt PRINCE2 as its corporate project management method and encourage its widespread use.
End project report
A report given by the project manager to the project board, confirming the handover of all products. It provides an updated business case and an assessment of how well the project has done against the original PID.
End stage assessment
The review by the project board and project manager of the end stage report to decide whether to approve the next stage plan. Depending on the size and criticality of the project, the review may be formal or informal. The authority to proceed should be documented as a formal record.
End stage report
A report given by the project manager to the project board at the end of each management stage of the project. This provides information about the project’s performance during the management stage and the project status at the management stage end.
Enhance (risk response)
A risk response to an opportunity where proactive actions are taken to enhance both the probability of the event occurring and the impact of the event should it occur.
Epic
A high-level definition of a requirement that has not been sufficiently refined or understood yet. Eventually, an epic will be refined and broken down into several user stories or requirements.
Event-driven control
A control that takes place when a specific event occurs. This could be, for example, the end of a management stage, the completion of the PID, or the creation of an exception report. It could also include organizational events that may affect the project, such as the end of the financial year.
Exception
A situation where it can be forecast that there will be a deviation beyond the tolerance levels agreed between the project manager and the project board (or between the project board and corporate, programme management or the customer).
Exception assessment
A review by the project board to approve or reject an exception plan.
Exception plan
A plan that often follows an exception report. For a stage plan exception, it covers the period from the present to the end of the current management stage. If the exception were at project level, the project plan would be replaced.
Exception report
A description of the exception situation, its impact, options, recommendation, and impact of the recommendation. This report is prepared by the project manager for the project board.
Executive
The individual with overall responsibility for ensuring that a project meets its objectives and delivers the projected benefits. This individual should ensure that the project maintains its business focus, that it has clear authority, and that the work, including risks, is actively managed. The executive is the chair of the project board. He or she represents the customer and is responsible for the business case.
Exploit (risk response)
A risk response to an opportunity. It means seizing the opportunity to ensure that it will happen and that the impact will be realized.
Follow-on action recommendations
Recommended actions related to unfinished work, ongoing issues and risks, and any other activities needed to take a product to the next phase of its life. These are summarized and included in the end stage report (for phased handover) and end project report.
Governance (corporate)
The ongoing activity of maintaining a sound system of internal control by which the directors and officers of an organization ensure that effective management systems, including financial monitoring and control systems, have been put in place to protect assets, earning capacity and the reputation of the organization.
Governance (project)
Those areas of corporate governance that are specifically related to project activities. Effective governance of project management ensures that an organization’s project portfolio is aligned with the organization’s objectives, is delivered efficiently and is sustainable.
Handover
The transfer of ownership of a set of products to the respective user(s). The set of products is known as a release. There may be more than one handover in the life of a project (phased delivery). The final handover takes place in the closing a project process.
Highlight report
A time-driven report from the project manager to the project board on management stage progress.
Host site
A location where project work is being undertaken (e.g., an office or construction site).
Impact (of risk)
The result of a particular threat or opportunity actually occurring, or the anticipation of such a result.
Information radiator
A general term used to describe the use of walls or boards containing information that can be readily accessed by people working on the project. It can contain any information, although it would typically show such things as work to do and how work is progressing.
Inherent risk
The exposure arising from a specific risk before any action has been taken to manage it.
Initiation stage
The period from when the project board authorizes initiation to when it authorizes the project (or decides not to go ahead with it). The detailed planning and establishment of the project management infrastructure is covered by the initiating a project process.
Issue
A relevant event that has happened, was not planned, and requires management action. It can be any concern, query, request for change, suggestion or off-specification raised during a project. Project issues can be about anything to do with the project.
Issue register
A register used to capture and maintain information on all of the issues that are being managed formally. The issue register should be monitored by the project manager on a regular basis.
Issue report
A report containing the description, impact assessment, and recommendations for a request for change, off-specification, or a problem/concern. It is created only for those issues that need to be handled formally.
Key performance indicator (KPI)
A measure of performance that is used to help an organization define and evaluate how successful it is in making progress towards its organizational objectives.
Lessons log
An informal repository for lessons that apply to this project or future projects.
Log
An informal repository managed by the project manager that does not require any agreement by the project board on its format and composition. PRINCE2 has two logs: the daily log and the lessons log.
Management product
A product that will be required as part of managing the project, and establishing and maintaining quality (e.g., highlight report, end stage report). The management products are constant, whatever the type of project, and can be used as described, or with any relevant modifications, for all projects. There are three types of management product: baselines, records, and reports.
Management stage
The section of a project that the project manager is managing on behalf of the project board at any one time, at the end of which the project board will wish to review progress to date, the state of the project plan, the business case and risks, and the next stage plan, in order to decide whether to continue with the project.
Maturity
A measure of the reliability, efficiency, and effectiveness of a process, function, organization, etc. The most mature processes and functions are formally aligned with business objectives and strategy, and are supported by a framework for continual improvement.
Maturity model
A method of assessing organizational capability in a given area of skill.
Milestone
A significant event in a plan’s schedule, such as completion of key work packages, a development step, or a management stage.
Off-specification
Something that should be provided by the project, but currently is not (or is forecast not to be). It might be a missing product or a product not meeting its specifications. It is one type of issue.
Operational and maintenance acceptance
A specific type of acceptance by the person or group who will support the product after it has been handed over into the operational environment.
Outcome
The result of change, normally affecting real-world behaviour and/or circumstances. Outcomes are desired when a change is conceived. They are achieved as a result of the activities undertaken to effect the change.
Output
A specialist product that is handed over to a user (or users). Note that management products are not outputs but are created solely for the purpose of managing the project.
Performance targets
A plan’s goals for time, cost, quality, scope, benefits, and risk.
Plan
A detailed proposal for doing or achieving something which specifies the what, when, how, and by whom it will be achieved. In PRINCE2 there are only the following types of plan: project plan, stage plan, team plan, and exception plan.
Planned closure
The PRINCE2 activity to close a project.
Planning horizon
The period of time for which it is possible to plan accurately.
Portfolio
The totality of an organization’s investment (or segment thereof) in the changes required to achieve its strategic objectives.