PRINCE2 Glossary Flashcards

1
Q

Define accept (risk response)

A

A risk response to a threat where a conscious and deliberate decision is taken to retain the threat, having discerned that it is more economical to do so than to attempt a risk response action. The threat should continue to be monitored to ensure that it remains tolerable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Define acceptance

A

The formal act of acknowledging that the project has met agreed acceptance criteria and thereby met the requirements of its stakeholders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Define acceptance criteria

A

A prioritised list of criteria that the project product must meet before the customer will accept it, i.e. measurable definitions of the attributes required for the set of products to be acceptable to key stakeholders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Define activity

A

A process, function or task that occurs over time, has recognisable results and is managed. It is usually defined as part of a process or plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Define agile methods

A

Principally, software development methods that apply the project approach of using short time-boxed iterations where products are incrementally developed. PRINCE is compatible with agile principles.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Define approval

A

The formal confirmation that a product is complete and meets its requirements (less any concessions) as defined by its Product Description.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Define approver

A

The person or group (e.g. a Project Board) who is identified as qualified and authorised to approve a (management or specialist) product as being complete and fit for purpose.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Define assumption

A

A statement that is taken as being true for the purposes of planning, but which could change later. An assumption is made where some facts are not yet known or decided, and is usually reserved for matters of such significance that, if they change or turn out not to be true, there will need to be considerable replanning.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Define assurance

A

All the systematic actions necessary to provide confidence that the target (system, process, organisation, programme, project, outcome, benefit, capability, product output, deliverable) is appropriate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Define authority

A

The right to allocate resources and make decisions (applies to projects, stage, and team levels)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Define authorisation

A

The point at which an authority is granted

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Define avoid (risk response)

A

A risk response to a threat where the threat either can no longer have an impact or can no longer happen.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Define baseline

A

Reference levels against which an entity is monitored and controlled.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Define baseline management product

A

A type of management product that defines aspects of the project and, once approved, is subject to change control.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Define benefit

A

The measurable improvement resulting from an outcome perceived as an advantage by one or more stakeholders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Define benefits review plan

A

A plan that defines how and when a measurement of the achievement of the project’s benefits can be made. If the project is being managed withi a programme, this information may be created and maintained at the programme level.

17
Q

Define benefits tolerance

A

The permissible deviation in the expected benefit that is allowed before the deviation needs to be escalated to the next level of management. Benefits tolerance is documented in the Business See also ‘tolerance’.

18
Q

Define business case

A

The justification for an organisational activity (project), which typically contains costs, benefits, risks and timescales, and against which continuing viability is tested.

19
Q

Define centre of excellence

A

A corporate coordinating function for portfolios, programmes and projects providing standards, consistency of methods and processes, knowledge management, assurance and training

20
Q

Define change authority

A

A person or group to which the Project Board may delegate responsibility for the consideration of requests for change or offspecifications. The Change Authority may be given a change budget and can approve changes within that budget.

21
Q

Define change budget

A

The money allocated to the Change Authority available to be spent on authorised requests for change.

22
Q

Define change control

A

The procedure that ensures that all changes that may affect the project’s agreed objectives are identified, assessed and either approved, rejected or deferred.

23
Q

Define checkpoint

A

A team-level, time-driven review of progress.