What is a project

A

A temporary organisation that is created for the purpose of delivering one or more business products according to an agreed business case

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Describe the characteristics of a project

A

Change - the means by which we introduce change
Temporary - in nature. Once completed, business as (new) usual resumes
Cross-function - different people with different skills working together
Unique - no two projects are the same, different organisational factors, different culture, different teams.
Uncertainty - threats and opportunities are rife in projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the characteristics of a project?

A
Change
Temporary
Cross-functional
Unique
Uncertainty
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the 6 aspects of project performance?

A
Time
Cost
Quality
Scope
Risk 
Benefits
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Describe the 6 aspects of project performance

A

Time - the duration of the project
Cost - budget allocated
Quality - a measure of what must be delivered to be considered fit for purpose
Scope - a definition of what is included within the project and is subject to change control
Risk - an understanding of the uncertainty that affects the project
Benefits - a prediction of value to gained from the change

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a project managers job?

A

Plan -> Delegate -> Monitor -> Control -> Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the four elements of Prince2

A

Processes
Themes
Principles
Project Environment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are Prince2 Principles

A

7 principles guiding obligation and good practice to determine whether the project is genuinely being managed using Prince2 methodology.
If all 7 are not used then it is not a Prince2 Project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are Prince2 Themes

A

The themes describe aspects of project management that must be addressed continually and in parallel during the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are Prince2 processes

A

describing the progression through the project lifecycle from start to finish. Each process has a chehcklist of recommended activities, products and realted responsibilities to complete to ensure success.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the Prince2 project environment

A

Organisations often what a consistant approach to managing projects and tailor PRINCE2 to create their own project management method, which is embedded into the organisations way of working.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What characteristics of project work distinguish it from business as usual

A
Change 
Temporary
Cross functional
Unique
Uncertainty
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the six variables associated with every projects

A
Cost
Time
Quality
Scope
Risk
Benefits
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What aspect of project performance must be managed in order to support effective decision making

A

Risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Is you manage what well, you manage a project well

A

Risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What characteristic distinguishes a project from a programme

A

It delivers products

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Which of the following elements provide the sets of activities required to direct, manage and deliver a project

A

Pocesses

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What are the PRINCE2 principles

A
Manage b y exception
Roles and responsibilities
Tailoring
Learn from experience
continued business justification
Manage by stage
Focus on products
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is manage by exception

A

Principle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What is roles and responsibilities

A

Principle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is tailoring

A

Principle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is learn from experience

A

Principle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is continued business justification

A

Principle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What is manage by stage

A

Principle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
What is focus on products
Principles
26
Which principle does the following statement describe: “Set tolerances for the six aspects of performance and put controls in place for project assurance to monitor”
Manage by exception
27
Which principle does the following statement describe: | “Two out of three accountabilities of the primary stakeholders are not good enough”
Roles and responsibilies
28
Which principle does the following statement describe: “Depends on the risk”
Tailoring
29
Which principle does the following statement describe: | “Writing reports to provoke change and creating a log during starting up a project”
Learn from experience
30
Which principle does the following statement describe: “This always moves from outline to detailed and is then updated”
Continued business justification
31
Which principle does the following statement describe: “Have at least two, so we can plan a little before, doing a little at a Time.”
Manage by stage
32
Which principle does the following statement describe: Quality outputs and deliverables that will be fit for purpose
Focus on products
33
How is the ‘focus on products’ principle applied?
By using a set of product descriptions
34
Which is a benefit of applying the manage by exception principle
The project management team will understand the tolerances permitted
35
Why must the defined roles and responsibilities principle be applied
It answers the question “what is expected of me”
36
What are tolerances
Defined ideals of what can be completed by an individual - if these tolerances are breached then an exception needs to be raised to the higher level of project team
37
What are the seven themes of PRINCE2
``` Business case Organisation Quality Plans Risk Change Progress ```
38
Which theme covers the why?
Business case
39
What is a business case
The theme addresses how the idea for a project is developed into viable invest proposition for the organisation and how project management maintains the focus on the organisations objectives throughout the project, ensuring there is a continued business justification for the investment by the organisation.
40
The theme addresses how the idea for a project is developed into viable invest proposition for the organisation and how project management maintains the focus on the organisations objectives throughout the project, ensuring there is a continued business justification for the investment by the organisation. WHICH THEME IS THIS
Business case
41
Which theme adresses the who?
Organisation
42
What is included in the organisation theme?
The roles and responsibilities of the project management team required to manage the project
43
The roles and responsibilities of the project management team required to manage the project DESCRIBES WHICH THEME
Organisation
44
Which theme defines the what
Quality
45
What is the quality theme
This theme explains how the outline is developed so that all participants understand the quality attributes of the products delivered
46
This theme explains how the outline is developed so that all participants understand the quality attributes of the products delivered WHICH THEME IS THIS
Quality
47
Which theme address the how, when and how much
Plans
48
What is the plan theme
This theme describes the steps required to develop plans, they are matched to the needs of the personnel at the various levels of the organisation and focus on the communication and control throughout the project
49
This theme describes the steps required to develop plans, they are matched to the needs of the personnel at the various levels of the organisation and focus on the communication and control throughout the project WHICH THEME
Plans
50
Which theme Describes the “what if”
Risk
51
What is a risk (theme)
Usually entailed more than stable operation and addresses how a project manager manages uncertainty
52
What is the change theme
This theme describes how project management assesses and acts upon issues which have a potential impact on any of the baseline aspects of the project
53
This theme describes how project management assesses and acts upon issues which have a potential impact on any of the baseline aspects of the project Which theme
Change
54
Which theme addresses the question “what is the impact”
Change
55
Which theme addresses the questions: Where are we now Where are we going Should we carry on
Progress
56
What defines the progress theme
This theme addresses the ongoing viability of the plans, explains the decision making process for approval plans, the monitoring of actual performance and the escalation prices if evens do not go according to plan.
57
This theme addresses the ongoing viability of the plans, explains the decision making process for approval plans, the monitoring of actual performance and the escalation prices if evens do not go according to plan. Defines what theme
Progress
58
Which theme is this? Estimating when something needs to be done, how long it ill take and if it is achievable
Plan
59
Which theme is this? Explain how to document something that might have an effect on your project objectives
Risk
60
What is the following theme To define what will make a product fit for purpose
Quality
61
What is the following theme To show that there is continued business justification
Business case
62
What is the following theme Defining a role description for the people within the team
Organisation
63
What is the following theme What reports are needed to monitor the work to control any unacceptable deviations
Progress
64
What is the following theme To access how something that has happened will affect the project
Change