What should be implemented using a risk budget? 1. A request for change 2. A contingent plan 3. Actions to avoid a risk from occurring 4. Responses to dis-benefits A. 1 and 2 B. 2 and 3 C. 3 and 4 D. 1 and 4
B
What is a risk?
A. A certain event occurring in the future that will have a negative impact on the project’s objectives
B. An event that has already occurred that the project manager must deal with immediately
C. An uncertain event that, if it occurs, will have an effect on the achievement of objectives
D. An uncertain event that, if it occurs, will be automatically escalated to the project board
C
What is a risk actionee responsible for?
A. Identifying risks to the project that might occur in their department
B. Owning and authorizing the use of the risk budget to fund risk responses
C. Managing, monitoring and controlling of all aspects of an assigned risk
D. Carrying out a risk response action to respond to a particular risk
D
Which activity is part of the recommended risk management procedure?
A. Allocating a budget to investigate issues
B. Reviewing risk management practices to ensure that they are performing effectively
C. Sending information to stakeholders about risks to the projects
D. Resolving conflicts between the project and the programme board
C
Which is a minimum requirement when applying the ‘risk’ theme?
A. To identify and ring-fence an explicit risk budget within the project’s budget
B. To describe the probability impact grid in the risk management approach
C. To appoint project assurance to maintain the risk register during initiation
D. To assess if risks might have a material impact on business justification
D
Which is a purpose of the ‘quality’ theme?
A. To check that the project is viable and achievable
B. To ensure that the project outputs are agreed
C. To ensure that formal issues are recorded
D. To enable the project to be managed according to plan
B
Which project management team role can be combined with business assurance? A. Project support B. Senior supplier C. Executive D. Project manager
C
Which role can act as the change authority? A. Project assurance B. Team manager C. Project support D. Team member
A
Which role is responsible for ensuring that the project management team works well with all the functional units involved in the project? A. Project board B. Project manager C. Team manager D. Project assurance
A
Identify the missing words in the following sentence. If approved, an exception plan will replace the [ ? ] and show the actions required to recover from the effect of a tolerance deviation. A. benefits management approach B. project brief C. stage plan D. team plan
C
Which level of management sets the project level tolerances?
A. Project board
B. Team manager
C. Corporate, programme management or the customer
D. Project manager
C
Identify the missing words in the following sentence. The first step of [ ? ] is writing the project product description.
A. PRINCE2’s recommended approach to defining and analyzing the products
B. The ‘initiating a project’ process
C. Producing the project mandate
D. PRINCE2’s recommended issue and change control procedure
A
At which level does the project board set tolerances? A. Programme B. Project C. Stage D. Work package
C
Why may it be appropriate to increase the length of several short management stages?
A. The project needs more time to resolve risky, innovative aspects
B. The project needs more time to complete the initiation activities
C. The project board does not have confidence in the management team
D. The project board wants to reduce the project management overhead
D
Which describes a purpose of the ‘quality’ theme?
A. To facilitate control by defining the activities to deliver the specified products
B. To provide the means to check that the products meet specified criteria
C. To summarize completed quality activities for input to the end stage report
D. To define what the project must deliver in order to gain acceptance