Prince 2 framework Flashcards
What is the PM structure/ project organisation?
It is the four levels of a PM structure (project organisation).
How many levels does the PM team have and what are they?
Three level.
Top level = project board level
Middle level = PM
Lower level = team manager level
The project team is temporary and is disbanded once the project is complete.
Who comes under the project board?
Senior user
Executive
Senior supplier
^ Project board is part of the project management team and is above PM and team manager.
What is the highest within the PM structure?
At the top of the PM structure you have the corporate or programme management level. This level is outside the project and so do not participate in the project and so aren’t part of the project team.
What is the project board responsible for?
Responsible for the success of the project and has the necessary authority to take decisions and approve all major plans. They approve the completion of each stage and authorise the start of the next (is called directing a project).
What is a programme?
A temporary flexible organisation structure created to coordinate, direct and oversee the implementation of a set of related projects and activities in order to deliver outcomes and benefits related to the organisations strategic objectives.
It is a group of related projects in an organisation.
What is the highest level if there is no programme?
Corporate management would be the top layer (PRINCE2 term for the higher level of management in a company).
What is the executive role?
The main person responsible for the project, they are supported by the senior user and senior supplier.
They represent the business interests of the project and own the business case.
The role gives a single point of accountability for the project.
What is the executive responsible for?
Designing and appointing the PM team, including the rest of the project board and project manager.
What is the senior user role?
They represent the user interests and is responsible for the specification. They specify the needs of the users and check that the final products meet the required specification.
Their main concern is ‘Will it work?’.
Senior users also specify the expected benefits at the start of the project and reports to the project board on the benefits that are being realised during the project.
What is the senior supplier role?
They represent the interests of those designing, developing, facilitating and implementing the project’s products.
Their main concern is ‘Can it be done?’ and whether it can be done within the agreed time, cost and quality requirements.
What is the PM role?
PM is appointed by the executive with approval from corporate or project management. PM runs the project on behalf of the project board on a day-to-day basis and has the responsibility to produce the required products to the required quality within the specified time and cost.
What is the team manager role?
They have the responsibility to produce the products that were assigned in work packages by the PM and to provide regular status reports on their progress. Allows the PM to monitor their work. Team managers create their own team plans to manage the development of the assigned products.
What are the four management levels? Where are they shown?
The process model shows four management levels.
Level 1 = Corporate or programme management
Level 2 = Direction
Level 3 = Management
Level 4 = Delivery
What is level 1 of the management levels?
Corporate or programme management
This is the top level, the only thing created in this level is the project mandate.