Which product summarizes progress and is used to decide whether to amend the project scope or stop the project?
End Stage Report
If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?
Issue Report
Upon what environment is PRINCE2 based?
Customer/supplier
Which is a purpose of the Managing Product Delivery process?
Project Plan
Which describes risk impact?
The effect of the risk on the delivery of project objectives
Customer’s quality expectations form a specific and precise list of Acceptance criteria are often expressed in broad terms as a means to gain common
understanding of general quality requirements.
Mastered
If an informal issue is defined as a problem or concern, where should it first be recorded?
Daily Log
Which is an objective of the quality review technique?
To assess that a product conforms to set criteria
Which risk response type is appropriate to respond to an opportunity?
Exploit
Which statement describes the responsibilities of a risk actionee?
Carrying out a risk response action to respond to a particular risk
Which is a purpose of a Project Brief?
Ensure that there is a common understanding of the starting point for the project
Which is a purpose of a Project Product Description?
Define the quality required of the project’s product
Which role is responsible for the management of a risk assigned to it?
Risk owner
Which is NOT a purpose of the Organization theme?
Define the level of tolerance for each level of the project management team
Which characteristic distinguishes a project from regular business operations?
Introduces business change
Which statement defines a risk?
An uncertain event, or set of events that, should it or they occur, will have an effect on the achievement of objectives
Which of the following is the Business Case used for during the Managing a Stage Boundary process?
Justify the continuing viability of the project
Which statement describes the Implement’ step within the recommended risk management procedure?
Take planned action to respond to a risk
Which is NOT an objective of the Controlling a Stage process?
Update the Business Case with any changes agreed with the Project Board
Update the Business Case with any changes agreed with the Project Board
Both 1 and 2 are true
If a project’s benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?
Corporate/programme management
Which is a type of issue?
An off-specification
Which statement about the Directing a Project process is FALSE?
Covers the day-to-day activities of the Project Manager
Identify the missing word in the following sentence, A project’s output is produced during a project but the [?] for the project are often only realized after the project
has closed.
benefits