When setting up the work breakdown structure (WBS) for a project, which of the following would generally NOT be taken into account
That the WBS allows access to only the project manager
A landscape contractor needs to purchase 120 shrubs in five-gallon containers to use in a project. A retailer is selling these shrubs for $10/each, with all orders past 100 shrubs being discounted by 5%. Waht is the total purchase price of the shrubs before tax?
$1,190.
If the question was worded as “over 100 shrubs”, the discount would apply to all 120 shrubs, and $1,140 would have been the correct answer.
The primary goal of a post-construction evaluation is to:
Ascertain if all elements of the project were built per the design drawings.
Which of the following parties would NOT be hired directly by the owner
Surveyors as Sub-consultant
Electrician as Sub-consultant
Owners have direct contractual relationship with prime consultant and the general contractor. Sub-consultants enter into contracts with the prime consultant or general contractor.
Which of the following items is generally a landscape architecture office’s single greatest expense?
Payroll
A field order differs from a change order in which of the following ways?
A field order has no cost or time implications for a contractor, whereas a change order does.
A client has a small residential property and would like a landscape architect to replace their lawn with plant material that requires less water. Which of the following items would be considered LEAST essential or relevant to the cope of design as requested?
Certificate of Title for the property in question
CoT provide proof of ownership for a piece of land.
Which of the following elements is NOT required to define a task?
A situation
Tasks are defined by objective, timeline, and level of effort
Division 2 of the Construction Specifications Institute (CSI) addresses which of the following categories?
Existing Conditions
A landscape architect designs a large, publicly accessible green roof on top of a parking structure. Planting design, construction detailing, and drainage are all included in the landscape architect’s scope of work. Two years after installation, design-related flaws to the waterproofing and drainage system cause extensive water damage to the parking structure and property owner immediately seeks legal recourse. Which of the following outcomes would NOT be possible as a cause of these events?
The landscape architect is unable to be prosecuted due to the statute of limitations expiring.
Two years has passed - it is unlikely that they would be protected due to the statutes of limitations expiring. Statute of limitations are set anywhere from 6-10 years for design and construction related issues.
Plant-related site maintenance costs can be reduced in which of the following ways?
Amending site soils prior to planting
Using drought tolerant plant material
Developing a site maintenance plan
1-2 inches of mulch is not sufficient enough to prevent weed growth or improve soil moisture and fertility.
On public projects, a bid from a contractor could be rejected because:
Contractor does not meet the bonding requirements for the project
Bid was submitted late due to a power outage at the contractor’s office
The bid form was altered by the contractor to include additional relevant information
public projects contain stringent requirements
Which of the following is generally NOT considered to e an advantage of a bar or Gantt-type chart schedule?
Can also be used for staff payroll
Simple and easy to understand. They are generally used to track deliverable and not for payroll
Which of the following statements about project work plans is FALSE
Project work plans should only be revised after construction commences.
To be valid and enforceable, a contract must:
Exist between two or more consenting parties
Be established while all parties are of a sound mental state