Pressure Testing Mains and Services Flashcards

1
Q

Pressure tests must not be conducted up against _____ or _____?

A

Valves or stoppers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

New pipeline segments must not be operated until what two conditions are met?

A
  • MAOP is established
  • All and any hazardous leaks have been found, repaired, and retested
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What 3 criteria’s must Eversource approved mediums meet?

A
  • Must be air or inert gas
  • Must be compatible with pipeline material
  • Free from sediment material (clean)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

All thermometers, gauges, and meters used in pressure tests must be what ________?

A

Calibrated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly