Prequalification questionnaire, Single Stage Tender and Tender Returns and Analysis Flashcards
751 What is a prequalification questionnaire? (231)
This is a pre tender exercise to ascertain if a company is suitable to tender of the works it asks questions about their level of experience, capacity and financial standing.
752 What is the purpose of a PQQ?
To whittle down the number of potential candidates to invite to tender. This saves time for both parties, the Client in having to tender to those it may not wish to work with and the contractors for work they are unlikely to win.
753 What might a PPQ ask for?
- Company details
- Relevant information about technical and professional ability
- Project case studies
- Financial information such as company accounts
- References
- Health and safety records and policy
- Environmental management policy
- Equality opportunities policy
- Insurance documents
754 A credit check is usually part of a PQQ. Where could you get this done?
Dun and Bradstreet report or credit agency like Experian.
Single Stage Tendering
755 What is single stage tendering?
A competitive tendering process where by all those tendering bid on the same information (usually RIBA stage 4, detailed design) in an attempt to win the work.
756 What are the key advantages of single stage tendering?
- Competitive pricing as all companies are in direct competition.
- Fixed price - Employer fixes the price at the end of the tender period
757 What are the key disadvantages of single stage tendering?
- Little to no buildability input from the contractors
- The price is only as good as the design information
- Contractors may be unwilling to tender in a good economic climate (too much competition)
757 What are the key disadvantages of single stage tendering?
- Little to no buildability input from the contractors
- The price is only as good as the design information
- Contractors may be unwilling to tender in a good economic climate (too much competition)
758 If you had a £25m new build project under D & B (single stage) how long would you allow for the tender period?
Depends largely on how complex the project is. There is time needed to develop the design and then actually price that design. Allow 10 – 12 weeks as a starting point and increase or decrease, as necessary.
759 What is two stage tendering? (239)
Stage one – The Client provides an outline project design and the contractors then compete for preferred status. Usually chosen on the quality of their bid, quality of their team, prelims & OH & P. The preferred contractor then joins the design team on a consultancy basis using a Preconstruction Services Agreement (PCSA)
Stage 2 – Once the design is sufficiently progressed the contractor enters into a detailed contract negotiation with the employer to agree the final price, contract conditions and programme.
760 What are the key advantages of two stage tendering?
- Overlaps design and construction. Early start on site may be possible
- Early appointment of the contractor can assist in buildability
- Employer may be involved in sub-contractor selection
- Opportunities to VE the contractors design
- Improved risk identification
761 What are the key disadvantages of two stage tendering?
- Contractor has less incentive to price the 2nd stage competitively
- Additional cost of the contractors PCSA fee
- Potential for the negotiation to fail and the parties do not go into contract
762 What is negotiated tendering?
This is single stage tender when a single contractor submits a tender return for the project. Both Parties then negotiate the contract price.
763 What are the key advantages of negotiated tendering?
- Simplicity
- Speed. Negotiated tenders can have programme advantages if undertaken in good faith.
- Client has flexibility in choosing who they want to work with.
- Time and cost saving from not having to prep the tender, wait for returns and then analyse
- Call allow ECI
764 What are the key disadvantages of negotiated tendering?
- May not be competitive. Might actually be at a premium
- Potential for delay of the negotiations become protracted
- Heavy reliance on trust
- Can be seen as anticompetitive and exclusive