Prelims Coverage Flashcards

1. The Construction Industry 2. Contracts and Specifications 3. Construction Project Organization 4. Planning and Scheduling (PERT/CPM)

1
Q

the process that sets up a portable plant, bring
material to the site, and on completion of the work moves the
plant away, leaving its output standing

A

Construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Legally binding document that describes the
responsibilities and rights of the parties

A

Contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Formation of Contracts

A
  1. Owner Issues an Invitation to Bids
  2. Contractor prepares and submits bid
  3. Owner reviews and accepts bid
  4. A contract document is developed, reviewed and agreed upon by parties
  5. The contract is signed by parties
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  • Companies and individuals engaged in the business of construction
    – They operate under a contract arrangement with the owner
A

Construction contractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

2 types of construction contractors

A
  1. General Contractors
  2. Specialty Contractors
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

engage in a wide range of construction
activities and execute most major construction projects

A

General contractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

limit their activities to one or more construction specialties

A

Specialty contractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Construction Documents and Contracts

A
  1. Bidding Requirements
  2. Contract Forms
  3. Contract Conditions
  4. Specifications
  5. Drawings
  6. Addenda
  7. Contract Modifications
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Enumerate the Bidding Documents

A
  1. Bidding Requirements
  2. Contract Forms
  3. Contract Conditions
  4. Specifications
  5. Drawings
  6. Addenda
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Enumerate the Project Manual Documents

A
  1. Bidding Requirements
  2. Contract Forms
  3. Contract Conditions
  4. Specifications
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Enumerate the Contract Documents

A
  1. Contract Forms
  2. Contract Conditions
  3. Specifications
  4. Drawings
  5. Addenda
  6. Contract Modifications
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Enumerate the Bidding Requirements

A
  1. Invitation to Bid
  2. Instructions
  3. Information
  4. Bid Form
  5. Bid Bond
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Enumerate the Contract Forms

A
  1. Agreement
  2. Performance Bond
  3. Payment Bond
  4. Certificates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Enumerate the Contract Conditions

A
  1. General Conditions
  2. Supplementary conditions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Enumerate the Specifications

A
  1. General Requirements
  2. Site Construction
  3. Concrete
  4. Masonry
  5. Metals
  6. Wood and Plastics
  7. Thermal & Moisture Protection
  8. Doors and Windows
  9. Finishes
  10. Specialties
  11. Equipment
  12. Furnishings
  13. Special Construction
  14. Conveying Systems
  15. Mechanical
  16. Electrical
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

convert design data into construction information and to clearly communicate that information to building industry, code officials, product manufacturers, suppliers and fabricators.

A

Working Drawings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

3 primary aspects of a set of working drawings

A
  1. Configuration/ Size
  2. Height
  3. Construction
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

involves the activities
necessary to effect and determine the fulfillment of the contract
requirements by the parties to the construction contract.

A

Construction Contract Administration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Any undertaking with a defined STARTING and ENDING
point and defined OBJECTIVES by which completion is
identified.

A

Project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Project attributes

A
  1. has a well-defined objective
  2. temporary
  3. requires resources
  4. has primary customer
  5. has a specific time frame
  6. carried out through a series of interdependent tasks
  7. involves uncertainty
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

the people
involved in or affected by project
activities

A

Project Stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Stake holders in a Construction Project

A
  1. Project sponsor
  2. Project Manager
  3. Project Team
  4. Support Staff
  5. Customers
  6. Users
  7. Suppliers
  8. Opponents to the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Construction Project Participants I

A
  1. Owner
  2. Architect/Engineer
  3. Contractor
  4. Subcontractors
  5. Product representatives
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Construction Project Participants II

A
  1. Supplier
  2. Manufacturers
  3. Consultants
  4. Testing Laboratories and Inspection Agencies
  5. Financial adviser and institutions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Construction Project Participants III

A
  1. Attorneys
  2. Insurance Advisers
  3. Bonding companies
  4. Authorities and regulatory agencies
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Project Categories

A
  1. Public Projects
  2. Private Projects
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Phases of a Project

A
  1. Business Planning
  2. Conceptual Design
  3. Detailed Design
  4. Procurement
  5. Construction
  6. Testing, Start-up, & Implementation
  7. Operations & Utilization
  8. Decommissioning
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

the application of knowledge, skills, tools, and techniques to project activities in order to meet project requirements (meet or exceed stakeholders’ expectation from a project)

A

Project management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Basic Resources of Construction

A
  1. Workers and subcontractors
  2. Equipment and construction plant
  3. Materials
  4. Money
  5. Time
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

A set of processes, tools and templates, designed to be used together to manage a project through its lifecycle

A

Project Management Framework

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

9 Project Management Knowledge Areas I

A
  1. Time Management
  2. Cost Management
  3. Quality Management
  4. Human Resources Management
  5. Communications Management
  6. Risk Management
  7. Procurement Management
  8. Integration Management
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Project Management Triple Constraints

A
  1. Time
  2. Cost
  3. Scope
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Project Risk Classifications

A
  1. Socioeconomic Factors
  2. Organizational Relationships
  3. Technological Problems
34
Q

Elements under Socioeconomic Factors

A
  1. Environmental Protection
  2. Public Safety Regulation
  3. Economic Instability
  4. Exchange rate fluctuation
35
Q

Elements under Organizational relationships

A
  1. Contractual relationships
  2. Attitudes of participants
  3. Communication
36
Q

Elements under Technological Problems

A
  1. Design assumptions
  2. Site conditions
  3. Construction procedures
  4. COSH
37
Q

Ways to decompose a project into stages:1

A
  1. Sequential processing
  2. Parallel processing
  3. Staggered processing
38
Q

two basic approaches to organize for project implementation

A
  1. Separation of organizations
  2. Integration of organizations
39
Q

Organization of Project Participants

A
  1. Matrix Organization
  2. Project Oriented Organization
40
Q

refers to a project management team consisting of a professional construction manager and other participants who will carry out the tasks of project planning, design and construction in an integrated manner.

A

Professional construction management

41
Q

In this approach an owner must have a steady flow of on-going projects to maintain a large work force for in-house operation. However, the owner may choose to subcontract a substantial portion of the project to outside consultants and contractors for both design and construction, even though it retains centralized decision-making to integrate all
efforts in project implementation.

A

Owner-Builder Operation

42
Q

the direct opposite of the owner-builder approach in which the owner wishes to retain the maximum amount of control for the design- construction process.

A

turnkey operation

43
Q

Key factors for successful projects

A
  1. well-defined scope
  2. extensive early planning
  3. good leadership, management, and first line supervision
  4. positive client relationship with client involvement
  5. proper project team chemistry
  6. quick responses to changes
  7. engineering managers concerned with the total project
44
Q

The process of identifying all the activities necessary to successfully complete the project.

A

PROJECT PLANNING

45
Q

The process of determining the sequential order of the planned activities, assigning realistic durations to each activity, and determining the start and finish dates of each activity.

A

PROJECT SCHEDULING

46
Q
  • establishes the project completion date, which governs the scheduling of work for both the designer and contractor.
  • sets priorities for the components that make up the project.
A

Responsibility of the owner

47
Q
  • develops a design schedule that meets the owner’s schedule.
  • this schedule should include a prioritization of work in accordance with the owner’s needs and should be developed with extensive input from all designers who will have principal roles in the design process
A

Responsibility of a Designer

48
Q

-develops a schedule for all construction activities in accordance with the contract documents.
-should include procurement and delivery of materials to the job, coordination of labor and equipment on the job, and interface the work of all subcontractors

A

Responsibility of a contractor

49
Q

A graphical time-scale of the schedule. It is easy to interpret; but it is difficult to update, does not show interdependences of activities, and does not integrate costs or resources with the schedule.

A

GANTT CHART

50
Q

A general title for the technique of defining and coordinating work by a graphical diagram that shows work activities and the interdependences of activities.

A

NETWORK ANALYSIS SYSTEM (NAS)

51
Q

CPM is the commonly used NAS in project management. It provides interrelationships of activities and scheduling of costs and resources.

A

CRITICAL PATH METHOD

52
Q

The performance of a task required to complete the project

A

ACTIVITY

53
Q

A diagram to represent the relationship of activities to complete the project.

A

NETWORK

54
Q

The estimated time required to perform an activity.

A

DURATION

55
Q

The earliest time an activity can be started.

A

EARLY START (ES)

56
Q

The earliest time an activity can be finished and is equal to the early start plus the duration.

A

EARLY FINISH (EF)

57
Q

The latest time an activity can be finished.

A

LATE FINISH (LF)

58
Q

The latest time an activity can be started without delaying the completion date of the project.

A

LATE START (LS)

59
Q
  • A list of basic steps that can be used to guide the process of developing a network analysis system for project planning and scheduling
A

WORK BREAKDOWN STRUCTURE

60
Q

FACTORS THAT AFFECT THE DURATION OF AN ACTIVITY

A
  1. QUANTITY AND QUALITY OF WORK
  2. NUMBER OF PEOPLE / LABOR
  3. NUMBER OF EQUIPMENT OF THE ACTIVITY 4. LEVEL OF WORKERS’ SKILLS
  4. AVAILABILITY OF EQUIPMENT
  5. WORK ENVIRONMENT
  6. EFFECTIVENESS OF SUPERVISION
  7. ETCETERA
61
Q

3 ways to determine the duration of activity:

A
  1. by analyzing historical records
  2. by referencing commercially available manuals
  3. from the experience and judgment of a person
62
Q

the amount of time that a task can be delayed without affecting the completion date of the project.

A

Total Float (TF)

63
Q

the amount of time that the activity can be delayed before any successors will be delayed

A

Free Float (FF)

64
Q

Primary resources in construction phase

A
  1. Labor
  2. Materials
  3. Equipment
65
Q

graphical representation of a project’s timeline, tasks, and the dependencies between those tasks

A

PRODUCT EVALUATION AND REVIEW TECHNIQUE

66
Q

is the shortest possible time an activity could possibly be completed, assuming that everything goes well

A

Optimistic time

67
Q

is the longest the activity could ever require, assuming that everything goes poorly

A

pessimistic time

68
Q

is the time the activity could be accomplished if it could be repeated many times under exactly the same conditions

A

most likely time

69
Q

3 durations of PERT

A
  1. optimistic time
  2. pessimistic time
  3. most likely time
70
Q

a graphical representation that shows the sequencing of activities in the project

A

CPM DIAGRAM

71
Q

the preceding activity

A

Predecessor
Activity

72
Q
A
72
Q

the following activity after the preceding activity

A

Successor
Activity

73
Q

4 SUCCESSOR/PREDECESSOR RELATIONSHIPS

A
  1. FINISH TO START
  2. START TO START
  3. START TO FINISH
  4. FINISH TO FINISH
74
Q

-assumed in a pure CPM
Network Diagram
-preceding activity must
be completed before
starting the following
activity

A

Finish-to-Start (F-S)

75
Q

the successor activity
can start at the same
time or later than the
predecessor
activity

A

Start-to-Start (S-S)

76
Q

the predecessor
activity must start before
the successor activity can
finish

A

Start-to-Finish (S-F)

77
Q

the successor activity
can finish at the same
time
as or later than the
predecessor activity

A

Finish-to-Finish (F-F)

78
Q

amount of time that an activity follows or is delayed from the start or finish of its predecessor; can be a negative number

A

Lag

79
Q
A
80
Q

is the opposite of lag, which is the amount of time that an activity precedes the start or finish of its successor

A

Lead