Preliminary Analysis Flashcards
Step 1 of the MAP
1
Q
What are the outputs of Prelim Analysis?
A
Issue Commander’s Initial Guidance
Issue Warning Order
Conduct Planning Time Appreciation
Identify Imposed Key Timings
2
Q
What is the recommended percentage allocation for each of the MAP steps?
A
IPB - concurrent with MA and ongoing Prelim - 10% MA - 20% COA Dev - 20% COA Analysis - 40% Orders and Execution - 10%
3
Q
When considering time appreciation, what is the ‘rule’ that should be applied to your planning and your subordinates planning?
A
The one-third / two-third rule
4
Q
When does the MAP (and therefore Prelim Analysis) start?
A
On receipt of a OPORD, a FRAGO, an WNGO, or from higher HQ guidance.