Predictive, Plan-Based Methodologies – 17% Flashcards
1
Q
Tuckman’s Ladder (ITTO: Acquire resources)
A
Forming (F), Storming (S), Jorming (N), Performing (P), Adjourning (A)
2
Q
Cost estimating approaches (process: Estimate costs in Planning)
A
- Expert Judgment
- Analogous Estimating - Top down, Pasted projects, Not very detailed
- Parametric Estimating - Statistical relationships between historical data and variables (če smo za eno ploščico položit rabil 1 minuti, rabimo za celo kopanlico N minut)
- Bottom-up Estimating - Separate estimate for each activity and aggregated up to summary nodes on WBS (Greatest Level of specified detail, Highly accurate, labor intensive)
3
Q
Estimating activity durations
A
- Analogous - relies on historical information, early in the project
- Parametric Estimating - Statistical relationships between historical data and variables (če smo za eno ploščico položit rabil 1 minuti, rabimo za celo kopanlico N minut)
- Three point estimate - Calculates an expected duration using a weighted average of 3 estimated, Optimistic, Pessimistic, Most Likely.
(O+P+4M)/6 - Bottom-up - You break down the work to the lowest levels and then aggregating the work
4
Q
Business Requirements plan
A
What needs to be done in order to meet the certain business objectives
5
Q
Process: Develop project charter. Outputs:
A
Project charter and assumption log
6
Q
What is a team charter?
A
Document that outlines what will be acceptable
behavior within the project. (Should include things like the general rules of conduct for meetings, decision- making, and one-on-one conversations)
7
Q
What If Scenarios (Monte
Carlo)
A
nekej, check