Predictive Approach Flashcards

1
Q

As soon as it becomes obvious that the project will be delayed, what should the project manager do?

A

The project manager should notify the client and present them with new alternatives.

They should be honest and transparent about delays.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Since requirements are fixed and deliverables will only be shipped at the end of the project, what type of approach should the project manager use?

A

Predictive approach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What approach is characterized by a single delivery but has dynamic requirements?

A

The iterative approach.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Which approaches involve frequent small deliveries?

A

Adaptive and incremental approaches.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What refers to the value of the work accomplished to date?

A

Earned Value will show you the value that the project has produced.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What estimating technique uses expert judgement by comparing a particular activity to a similarly completed one on a previous project in order to determine its duration or cost?

A

Analogous estimating technique relies on expert judgement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The work breakdown structure dictionary includes?

A

The WBS dictionary includes detailed information on work packages, such as descriptions, owners, prerequisites, successors, due dates, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What budget reserve is used for risks that were not identified during risk analysis, aka unknown-unknowns?

A

The management reserve.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What budget reserve is used for identified risks with predetermined risk response strategies, aka known-unknowns?

A

A contingency reserve.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

It is the responsibility of functional managers to?

A

Manage staff assignments.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The project manager should provide ________ to make sure that functional managers are aware of when and what resources is needed for the project.

A

Resource calendars.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What estimate is an estimation of the needed effort and cost to complete a project?

A

A Rough Order of Magnitude Estimate (ROM estimate), a ROM estimate is performed very early in a projects life cycle; during the project selection and approval period and prior to project initiation in most cases.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

If a project has more than one critical path, then …

A

then all critical paths must have exactly the same length.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What planning method is used to decompose and subdivide the project scope deliverables into more manageable, small work units?

A

Scope decomposition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Crashing the schedule involves, what?

A

Compressing it by adding more resources to the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Fast-tracking implies, what?

A

Performing originally sequential activities in a simultaneous way instead.

17
Q

Within a predictive approach, the ________ is the basis for cost estimation.

A

WBS

18
Q

_________ is a project planning method that consists of a gradual elaboration of details to the WBS over time.

A

Rolling Wave planning allows work to progress on current and near-term deliverables while the planning for potential work packages continues.

Rolling Wave method is used to address uncertainty rather than prioritizing, organizing or sequencing activities.

19
Q

________ is a technique used at the end of a project or phase in order to identify any deviation in deliverables or difference between actual and planned behaviors.

A

Variance analysis

20
Q

________ represent an opportunity for project stakeholders to review project progress along with planned future actions.

A

Stage-gate or phase review meetings

Project stakeholders can assess whether or not the project is on track to meet the organization’s expectations.

21
Q

________ are limiting factors for your project that can impact delivery, quality, and overall project success.

A

Project constraints

An imposed delivery date or a predefined budget are considered project constraints.

22
Q

_______ acknowledges the existence of a threat, but no proactive action is taken.

A

Risk acceptance.

23
Q

____ involves no proactive action apart from a periodic. Review of the threat to ensure that it does not change significantly

A

Passive acceptance.

24
Q

______ is an unplanned response to deal with unidentified risks and risks that are passively accepted.

A

A workaround.