Precedent's Reverse Flashcards

1
Q

Contract acceptance is when mailed. Includes fax and email as well.

A

Queen v. Commercial Credit Corp 1983

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Option to purchase mining claims. Implied an extended deadline. Changed mine, tried to execute original contract. Courts ruled it would be inequitable for the optionee if the extended rule was not upheld.
Estopped from reverting to strict contractual rights.

A

Conwest Exploration v Letain 1963

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Owner had right to implied extension.

Was not heard by supreme court.

A

Owen Sound Public Board Library V. Mail Development 1979

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Party forged a guarantee; second party atttempted to execute a second gurantee under threat of disclosure of forgery.
Ruled that the second guarantee was made under duress so unenforceable.

A

Mutual Finance V John Wetton and Sons 1937

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Unlicensed Electrictian did not get paid for time and materials.

A

Koctis v. D’Angelo 1958

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Unlicensed plumber was paid for materials.

A

Monticchio V. Torcema Construction 1979

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Contract A and Contract B.

A

Ron Engineering V Ontario 1981

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

All bidders must be treated equally.

Owner breached by preferring local contractors, but did not stipulate that in the tender documents.

A

Chinook Aggregates Ltd. V. Abbotsford 1989

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Lowest bid need not be accepted. Include a rules clause in bid documents.

A

Martel Building Ltd. V. Canada 2000

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Owner rented dock space. Ship was damaged.
Implied term was ship would be safely moored at low-tide.
Obvious and did not need to be stated.

A

The Moorcock Doctrine 1889

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Staircases installed were not up to code.

Implied term was that building code would be followed. Obvious and did not need to be stated.

A

Ford Homes V. Draft Masonry 1983

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Heating tape caused plastic pipe to fail and factory burned down.
Contract had a clause limiting liability, but due to the fundamental breach of contract (No reasonable engineer would have used a plastic pipe) the clause was not valid.

A

Harbutt’s Plasticine v. Wayne Tank & Pump 1970

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Defendant argued that condition was never met and therefore no contract was entered into.
Since no contract was entered into at all, Parol Evidence rule was not applicable.

A

Pym V. Campbell 1856

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The disclaimer on the can was not sufficient as compared to a competitors disclaimer.

A

Lambert V. Lastoplex Chemicals 1971

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Hunter didn’t follow simple instructions and hurt himself. Lost as it was his fault.

A

Lem V. Barotto Sports & Ponsness-Warren 1976

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Inspectors employer was held vicariously liable.

A

Dutton V. Bognor Regis United Building Co. 1972

17
Q

Both the agency and the agent were held liable. Employee owed a duty of care to the insurance company.

A

Northwestern Insurance V. O’Bryan 1974

18
Q

Engineer negligently left a note of a set of plans that said “Good Plans. Etc”
Contractor acted on them and the construction failed.
Engineer argued he didn’t know he was being consulted.
Engineer and Contractor held 50-50 responsible.
Engineer appealed and was found 75% responsible.

A

Canam Contracting V. Huffman 1993

19
Q

Architect designed a building, hired engineer’s to do soil testing. Engineer recommended more testing, architect declined.
Both were held liable 60% architect 40% engineer.

A

Corp. Dist of Surrey V. Carrol Hatch 1979

20
Q

A lawyer can be liable to a client in tort as well as contract for damages for failing to meet standard of care.

A

Central Trust V. Rafuse 1986

21
Q

Defendant held liable for lost profits while crane was out of service. Had duty to warn.

A

Rivtow Marine V. Washington Iron Works 1973

22
Q

Defendant’s employees negligently damaged electrical supply to building.
Sued for employee wages.
Defendant won, as the wages would have been paid either way.
Would have been successful if sued for loss of profits.

A

MacMillan Bloedel v Foundation Co 1977

23
Q

Ship ran into a bridge and blocked a canal.
Owner of ship was found responsible.
2 claimants. 1 asked for loss of profits of 2 ships which had been delayd for 2 weeks.
1 asked for cost of shipping goods over land.
Neither claim was allowed.
Liability is only extended when physical harm to property has been threatened.

A

Bethlehem Steel Corp V. St Lawrence Sea Authority 1977

24
Q

Barge collided with bridge owned by public works.
Sufficient proximity to justify liability.
Tracks to and from bridge were owned by CN Rail and therefore they were entitled to recover economic loss.

A

CN Railway V. Norsk Pacific Steamship Corp 1990