PPT2 Flashcards

1
Q
  1. A _______ is an agreement with specific terms and conditions between two or more persons or between Owner & the Contractor in which there is a promise to execute or do some work.
A

Labor contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. In a Labor Contract, all materials required for the construction are supplied by the _______.
A

Owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. The owner pays the contractor the labor amount as stipulated in the contract based on _______.
A

percentage accomplishment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. A Labor Only Contract means the contractor provides labor workforce from _______, _______, _______, _______, and _______ necessary to complete the project.
A

supervision, interpretation of plans, skilled workers, tools, and equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. In any project, a _______ is always an assurance to both Owners and Labor contractor that the project will be done as long as materials are on stock.
A

guaranteed material inventory

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. The _______ is responsible for providing adequate labor and carrying out and completing the particular scope of work.
A

Contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. GMQ stands for _______.
A

Guaranteed Materials Quantity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. Labor-Only Contracting refers to an arrangement where the contractor merely _______, _______, or _______ workers to perform a job or work for a principal.
A

recruits, supplies, or places

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. If contractor exceeds the no. of guaranteed quantity, he ­­­_______ to finish the project. If he does not exceed and has surplus quantity, then _______.
A

spends for the excess materials required just to finish the project; keeps the surplus materials as his savings and profit.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. GMQ means that _______% of the materials forecast (estimate) for a given time shall be guaranteed by the owner to the contractor.
A

50

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. It is very important that the estimates are within the parameters of the project inventory and following strictly the _______, _______, and _______.
A

quantity, specifications, and estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  1. One advantage of a Labor Only Contract for the owner is the assurance of _______ of materials.
A

quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  1. The owner saves costs because he saves the profit on _______ cost.
A

material

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  1. Another advantage for the owner is that project _______ is faster.
A

project turnover

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  1. A disadvantage for the owner is that the quality of _______ is most of the time compromised.
A

workmanship

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  1. In a Labor Only Contract, the GMQ system is advantageous to the _______.
A

contractor

11
Q
  1. Another disadvantage for the owner is that _______ on materials is rampant.
12
Q
  1. A pakyaw system means that labor rates are _______, but there are no government-imposed benefits to the workers.
A

a bit higher

13
Q
  1. Workers in a Labor Only Contract are under a no work, no pay system, also known as _______.
A

project basis employment

14
Q
  1. In a Labor Only Contract, excess/surplus on GMQ is to the _______.
A

contractor

14
Q
  1. A disadvantage for the contractor is inclement _______ conditions.
15
Q
  1. Another disadvantage for the contractor is slow delivery of _______.
A

owner-supplied materials (OSM)

16
Q
  1. Safety concerns such as _______ are disadvantages in a Labor Only Contract.
16
Q
  1. A sudden increase in _______ imposed by the government is another challenge for the contractor.
17
Q
  1. Changes in the _______ can cause issues for the contractor in a Labor Only Contract.
18
Q
  1. Contractor provides labor work force
A

Supervision, Interpretation of Plans, Skilled Workers, Tools, Equipment.

18
Q
  1. Different types of construction contracts
A

Lump Sum Contract, Labor Only Contract, Cost Plus Contract, Unit Price Contract, Time and Materials Contract, Guaranteed Maximum Price Contract (GMP), Design and Build Contract, Turn-Key Contract, Build-Operate-Transfer (BOT), PPP Contract.

19
Q
  1. The parameters of the project inventory follow strictly the
A

quantity, specifications and estimates.

20
Q
  1. Advantages of a Labor Only Contract for the owner
A

Assurance of quality materials, Cost savings, Faster project turnover.

21
Q
  1. Disadvantages of a Labor Only Contract for the owner
A

Quality of workmanship may be compromised, High risk of pilferage, GMQ favors the contractor.

22
Q
  1. Advantages of a Labor Only Contract for the contractor
A

No government-imposed benefits, Project basis employment, Surplus from GMQ is to the contractor.

23
Q
  1. Disadvantages of a Labor Only Contract for the contractor
A

Inclement weather conditions, Slow delivery of owner-supplied materials (OSM), Sudden increase in wages, Plan changes, Safety concerns.