PPC TMM Flashcards
The Palisades Plant Process Computer (PPC) system is used to:
A. perform Heat Balance Calculations.
B. enter Operator Rounds data into NOMS.
C. generate Switching and Tagging Orders.
D. access the Lotus Notes E-Mail system.
A. perform Heat Balance Calculations.
Which ONE of the following describes the operational design of the Uninterruptible
Power Supply provided for the Plant Process Computer?
A. On a loss of Battery Charger 0-207 ANO MCC 3/MCC 4, Battery 0-204 can be
manually aligned to Inverters Y-21 0/Y-220 using Bypass Switches S9003/S9007.
B. On a loss of Battery Charger 0-207 ANO MCC 3/MCC 4, Battery D-204 will be
automatically aligned to Inverters Y-21 01Y-220.
C. On a loss of Battery Charger 0-207, Battery 0-204 will be automatically aligned to
Inverters Y-21 0/Y-220.
O. On a loss of MCC 3/MCC 4, Battery 0-204 will be automatically aligned to Inverters
Y-210/Y-220.
B~ On a loss of Battery Charger 0-207 ANO MCC 3/MCC 4, Battery D-204 will be
automatically aligned to Inverters Y-21 01Y-220.
The Plant Process Computer is used to calculate …
A. Main Generator output in MWe.
B. the Variable High Power Trip setpoint.
C. the Thermal Margin Low Pressure setpoint.
D. Control Rod drop times for testing.
D. Control Rod drop times for testing.
Which of the following explains how the Palisades Plant Computer (PPC) interfaces
with the Meteorological Monitoring System?
A. The PPC is the primary means to access information from the Met Tower during
normal and transient plant operations.
B. The PPC is the backup method of obtaining Met Tower information if the
Emergency Preparedness Computer(s) is unavailable.
C. The PPC uses inputs from the Met Tower to automatically calculate off-site
radiation dose rates.
D. The PPC uses inputs from the Met Tower to automatically determine Protective
Action Recommendations (PARs).
A. The PPC is the primary means to access information from the Met Tower during
normal and transient plant operations
De-energizing which ONE of the following Preferred AC Buses will result in a loss of
Right Channel Plant Process Computer (PPC) indications?
A. Y-10
B. Y-20
C. Y-30
D. Y-40
B. Y-20
You are monitoring plant status using the Plant Process Computer (PPC) when you
notice a parameter value is displayed in orange.
The color signifies the parameter value …
A. exceeded its “Alarm” setpoint.
B. exceeded its “Warning” setpoint.
C. is bad data or out of range.
D. has been manually entered.
C. is bad data or out of range.
During a critical approach, all Group 4 Regulating Rods start to continuously withdraw
with NO operator action. What Control Room indicatinos can be used to determine that
a continuous rod withdrawal is occurring?
A. Associated core matrix indicating lights change from RED to AMBER.
B. EK-0911, “ROD POSITION 4 INCHES DEVIATION” annunciates.
C. Rod Deviation (RED) light is ON for Group 4 rod indicating lights on control panel
C-02.
D PPC GREEN indicating bars on Page 410 for Group 4 rod positions are getting
SHORTER.
D PPC GREEN indicating bars on Page 410 for Group 4 rod positions are getting
SHORTER
The Cutler-Hammer Interface has failed and therefore QCET indication is not available
on the PPC.
QCET temperatures can then be monitored using which one of the following?
A. TYT-0100 or TYT-0200
B. SPI Node
C. PIP Node
D C-11A recorders
D C-11A recorders
During a Loss of Coolant Accident inside containment the operator notes that the Plant
Process Computer (PPC) displayed value for containment pressure has changed color
from MAGENTA to WHITE. How is this information obtained on the PPC and what is
its significance?
A. Depress “URGNT” hard key. Containment pressure is now LESS THAN the alarm
level setpoint.
B. Depress “ALARM” hardkey. Containment pressure is now ABOVE the alarm level
setpoint.
C. Depress “EVENT” hardkey. A Containment High Pressure (CHP) has just actuated.
D. Depress “UPDATE” hardkey. Criteria for resetting Containment High Pressure are
now met.
A. Depress “URGNT” hard key. Containment pressure is now LESS THAN the alarm
level setpoint
During a critical approach, all Group 4 Regulating Rods start to continuously withdraw
with NO operator action. What Control Room indications can be used to determine
that a continuous rod withdrawal is occurring?
A. Associated core matrix indicating lights change from RED to AMBER
B. EK-0911, “ROD POSITION 4 INCHES DEVIATION” annunciates
C. Rod Deviation (RED) light is ON for Group 4 rod indicating lights 011 control panel
C-02
D. PPC GREEN indicating bars on Page 410 for Group 4 rod positions are getting
SHORTER
D. PPC GREEN indicating bars on Page 410 for Group 4 rod positions are getting
SHORTER
a. This is one indication available, but candidate misapplies the conditions, since it
actually indicates rod insertion.
b. This alarm would annunciate, but it would NOT be the determining indication for
these conditions.
c. This indication would exist, but it would NOT be the determining indication for these
conditions, since this light only means that some type of deviation exists, and not
specific to a rod withdrawal.
d. CORRECT - This is a valid indication to diagnose the condition.
The Cutler-Hammer Interface has failed and therefore aCET indication is not available
on the PPC.
aCET temperatures can then be monitored using which one of the following?
A. TYT -0100 or TYT -0200
B. SPI Node
C. PIP Node
D C-11A recorders
D C-11A recorders
a. This is a TYPE of temperature indication, but it is NOT CET related.
b. SPI does interface with the PPC, but not for the stated function.
c. PIP does interface with the PPC, but not for the stated function.
d. CORRECT - A valid alternate method of determining CET readings.
During a Loss of Coolant Accident inside containment the operator notes that the Plant
Process Computer (PPC) displayed value for containment pressure has changed color
from MAGENTA to WHITE. How is this information obtained on the PPC and what is
its significance?
A. Depress “URGNT” hardkey. Containment pressure is now LESS THAN the alarm
level setpoint.
B. Depress “ALARM” hardkey. Containment pressure is now ABOVE the alarm level
setpoint.
C. Depress “EVENT” hardkey. A Containment High Pressure (CHP) has just actuated.
D. Depress “UPDATE” hard key. Criteria for resetting Containment High Pressure are
now met.
A. Depress “URGNT” hardkey. Containment pressure is now LESS THAN the alarm
level setpoint
a. CORRECT· Per PPC operating manual the URGNT hardkey is used to
access the information, and it is interpreted as shown here.
b. Though this hard key does exist, it would not be used for the condition; candidate
also misinterprets the significance of the indication.
c. Incorrect usage of this hardkey; candidate also misinterprets the significance of the
indication.
d. UPDATE key is a commonly used key on the PPC, but not for this application;
further, candidate misinterprets signficance of the indication.
Given a failure of the Host Computer, which ONE of the following statements is
CORRECT regarding the impact on the Plant Process Computer (PPC) system?
A. Control Rod Position is available and can be read on the LED displays located on
Panel C-02.
B. Analog and digital inputs for plant parameters processed by the Cutler Hammer
interface are valid.
C. Main Feedwater Temperature and S/G Pressure input the Heat Balance Calculation
is not available.
D. Main Feedwater Flow input to the Heat Balance Calculation on the PPC is not
available.
A. Control Rod Position is available and can be read on the LED displays located on
Panel C-02.
Which of the following Group 4 Rod Positions would permit continued operations for the associated power level WITHOUT any operator actions? POWER LEVEL A. 40% B. 50% C. 60% D. 70% GROUP 4 ROD POSITION 30 inches 50 inches 55 inches 60 inches
B. 50% 50 inches
Which of the following describes a condition and the effect of that condition on Palisades Plant
Computer (PPC)?
A. A loss of the PIP node causes the Panel C-02 control rod LEDs to indicate incorrectly
B. A loss of the HOST computer causes the Panel C-13 rod matrix lights to indicate incorrectly
C. A loss of the HOST computer causes the Panel C-02 control rod LEDs to indicate incorrectly
D. A loss of the PIP node causes the Panel C-13 rod matrix lights to indicate incorrectly
A. A loss of the PIP node causes the Panel C-02 control rod LEDs to indicate incorrectly