PPAP Flashcards
1
Q
PPAP
A
Production Part Approval Proces
2
Q
How many requirements are?
A
18
3
Q
Requirement 0
A
Significant production Run.
1-8 hr
Minimun 300 consecutive parts
4
Q
Requirement 1
A
Design Record.
Part drawing specifications and/or electronics
Design in CAD
GD&T
5
Q
GD&T
A
Geometrical, dimensional and toleracing
6
Q
Requirement 2
A
Engineering Change Documents
7
Q
Requirement 3
A
Customer Engineering Approval
8
Q
Requirement 4
A
DFMEA
9
Q
DFMEA
A
Design Failure Mode And Effect Ananlysis.
10
Q
Requirement 5
A
Process Flow Diagram
11
Q
Requirement 6
A
PFMEA
12
Q
PFMEA
A
Process failure mode and effect analysis
13
Q
Requirement 7
A
Control Plan
14
Q
Requirement 8
A
Measurment System Analysis Studies
15
Q
Requirement 9
A
Dimensional results