Post midterm Flashcards
Contractor pays owner’s damages
Inexcusable Delay
Each party absorbs own damages
Excusable Delay
Owner pays contractors damages
Compensatory Delay
Owner pays for increasing work or decreasing time
Acceleration
An owner may accelerate the completion date of the contract in three ways:
- Decrease the amount of time
- Changing or incresing amount of work
- refusing to grant time extention when the contract requires it
refers not only to conditions that were unforeseen but also to those not reasonably foreseeable
unforeseen conditions
- CCDC, MMCD, Master format type of contracts
Units price
A stipulated price contract
Lump sum or fixed price
Why standard construction contracts?
- Standardized + consistent
- Based on years of legal experience + designed by lawyers
- Allocating risk between contractors + owners + consultants
- *Advantages**
- Owner knows price in advance
- contractors entitled to keep any profits as cost savings measures
- lower admin costs for contractors
Disadvantages
-contractor is assuming more risk
( eg. Responsible for any cost over runs)
- Contractor could take more risk for delays (eg. Bad weather
- Owner’s perspective price can change
- Quality -> contractor ma not want to use cheaper materials -> to avoid that have clear specifications and a strong QC(quality control) process -> another way to avoid this is to have prequalified process
- used for projects with well-defined scope of work + price
Stipulated price contract (CCDC)
Used when scope of work is well defined and quantities may not be as well defined but can be estimated.
Advantages
Disadvantages
- Less paperwork in dealing with extra work
- Less risk to contractor in regards to making profit
- If you don’t really have a good estimate at start (owner perspective) àcost overruns
- more paper work for tracking quantities
/Unit price
- Is a contract in which the contractors is paid actual cost of goods + service performed plus a fee
- used when the scope of work is not well defined
AdvantagesDisadvantages - Lower risk for contractor (all work is paid for)
- typically, don’t have to propose a tender
- Owner can get more involved in the method and manner of contract
- Quality is likely higher
- Less paperwork with changes and extras
- Cost is likely higher than stipulated price
- Gives contractor opportunity to inflate prices
- Little incentive to complete work in a timely manner
Cost plus
An event that extends the time for completion
has signficance and is substantial
Time is of essence
3 things needed to prove a delay to recover damage
- The delay was the fault of some other party
- A delay had to occurred
- The delay cost the claimant money -→ quantifiable additonal cost
Heads of damage are the recoverable categories of damage
Example:
additional labour costs due to the lengthened time on site
increased labour and material costs because payment must be made
later than originally anticipated, and after prices have risen
costs resulting from productivity loss and loss of profit
additional site and head office overhead
costs of extending warranties and obtaining additional bonding
loss of interest on holdback
Heads of Damages
is that point in the progress of a project at which
the owner can actually occupy and use a facility for its intended purpose
Substantial completion
The greatest importance to the contractor of final completion is that the
release of the….
Holdback
Difference between sustainable and final completetion
The bulk of the construction work will have been completed at the point of
substantial completion. Only minor work items and small deficiencies need to be
addressed after a project has been defined as being substantially complete.
FInal complete is where the warenty kicks in
is a claim for payment for
work done on a construction project or
materials supplied to it.
Builders lien
is required because other types of
security commonly used when goods or services are
provided on credit do not work in the construction
industry: a car can be seized, but paint or concrete
would be worthless if reclaimed
Lien Legislation
the claimant must prove that
labour or materials were provided in accordance
with the contract, that payment was not made, and
that all the requirements of the lien legislation were
complied with
To “perfect” the lien
How can you remove a lien
the owner can
provide substitute security: cash, letter of credit, lien
bond
is a percentage of the contract value that must be
held back from progress payments – creates pool of funds
Holdback
re contracts of indemnity and are governed by principles of contract
law.
Insurance polices
A promise to directly compensate or reimburse another party
for a loss or cost incurred.
Contract of indemnity