How much was the cost of water at the Tampa desal plant during the 7-year period of operating inefficiency?
$3,507 per acre-foot
How much were the cost overruns at the Tampa Bay desal plant?
44% cost overruns.
$110 million budgeted initially, $158 million was final cost.
What was the initial capital budget for Carlsbad, and what was the final cost?
Initial capital budget was $300 million.
Final cost was $900 million.
200% cost overrun.
What did Poseidon Carlsbad estimate as its average cost for electricity compared with estimates from 2 independent consultants?
Poseidon Resources estimated $0.116/kWh.
Consultants estimated $0.075/kWh.
This is a 54% under-estimation.
What did Poseidon Tampa Bay estimate as its average cost for electricity compared with actual costs?
Poseidon Resources estimated $0.04/kWh.
Actual costs were $0.09/kWh.
This was 125% overbudget