PMP Wrong Questions Flashcards

Study questions that I got wrong

1
Q

An agile project is in its first of 12 iterations, and each iteration lasts two weeks. In the first iteration review, the stakeholders ask for monthly reports moving forward.

What should the project manager do?

A.Tell the team members to create monthly iteration reports.
B.Create monthly reports and send them to the stakeholders.
C.Coach and mentor the stakeholders on agile methodologies.
D.Ask the stakeholders to participate in monthly iteration reviews.

A

Solution: C. Coach and mentor the stakeholders on agile methodologies.

The stakeholders do not have a thorough understanding of agile practices, so the project manager should take time to coach and mentor them to increase understanding and awareness. This will enable stakeholders to provide feedback and make informed decisions within the agile framework. In an agile environment, there is an emphasis on frequent and iterative feedback loops which would be every two weeks in this case. Being that the iterations are two weeks long, a monthly report would not be appropriately aligned with agile practices.

The other options are incorrect because they do not align with the agile approach.

If the project manager agrees to provide monthly reports, the stakeholders would not fully understand how to operate within an agile environment. The project manager should explain the benefits and advantages of the agile approach and emphasize the importance of regular iteration reviews. Each iteration is two weeks long, so monthly reviews are not appropriate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A project manager wants to ensure that virtual team meetings are effective. What should the project manager do?

A.Record all the meetings for participants who cannot attend.
B.Determine the best communication methods based on location.
C.Prioritize the agenda with items that require more discussion.
D.Schedule meetings at convenient times for the majority of attendees.

A

Solution: B. Determine the best communication methods based on location.

The most effective approach for the project manager to ensure that virtual team meetings are successful is to determine the best communication methods based on location. This action addresses the unique challenges that virtual teams face, such as time zone differences, language barriers, and cultural differences. By tailoring communication methods to the specific needs of the team members, the project manager can foster a more inclusive and productive meeting environment.

The other answer choices are less effective.

Recording all the meetings for participants who cannot attend: While recording meetings can be beneficial for those who miss the live session, it doesn’t guarantee that virtual team meetings are effective overall. The project manager needs to address the real-time participation and engagement of attendees.

Prioritizing the agenda with items that require more discussion: While a well-structured agenda is crucial, it doesn’t address the underlying issues that may hinder virtual team meeting effectiveness. The project manager needs to focus on communication methods and team dynamics.

Scheduling meetings at convenient times for the majority of attendees: Considering the schedules of most attendees is important, but it doesn’t address the diverse needs of virtual team members across different locations and time zones. The project manager needs to find a balance that accommodates everyone.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A project manager is appointed to design and develop a strategy for a government organization. The project manager recognizes that the project has a limited amount of detailed information to prepare project estimates. However, several other government organizations have already successfully adopted the same strategy.

In this scenario, which type of estimating method should the project manager select?

A.Parametric modeling
B.Analogous estimation
C.Three-point estimating
D.Expert judgment

A

Solution: B. Analogous estimation

In this scenario, the project manager has limited information about the project, but they know that several other government organizations have already successfully adopted the same strategy. This suggests that there is sufficient historical data available to use analogous estimation. Analogous estimation is a project management technique that uses historical data from similar projects to estimate the cost, time, and resources required for a new project. It is a good choice for projects with limited information, such as the one described in the question.

The other answer choices are incorrect. Parametric modeling is a project management technique that uses mathematical formulas to estimate the cost, time, and resources required for a project. It is not as well-suited for projects with limited information as analogous estimation. Three-point estimating is a project management technique that uses three estimates (i.e. optimistic, pessimistic, and most likely) to estimate the cost, time, and resources required for a project. It is not as well-suited for projects with limited information as analogous estimation. Expert judgment is a project management technique that uses the expertise of experienced professionals to estimate the cost, time, and resources required for a project. It is not as well-suited for projects with limited information as analogous estimation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Question
A project manager has completed the project deliverable and has passed the acceptance criteria. Which statement confirms that project benefits have been achieved?

A.The deliverable has been approved and the value has been confirmed.
B.The deliverable solved all of the issues specified by the project sponsors.
C.The project has seen some improvements in the ability to make decisions.
D.The project was completed on schedule, without any complaints from end users.

A

Solution: A. The deliverable has been approved and the value has been confirmed.

When the deliverable has been approved and the value has been confirmed, this confirms that the project has met its objective and that benefits have been achieved.

The other answer choices are incorrect. There is no formal validation. They mention that the deliverable solved the issues, but there is no confirmation of the benefits.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A stakeholder is concerned that the project is falling behind schedule, based on unofficial information from the project team. Although some tasks have slipped, these tasks have free floats; otherwise, the project is on track. The project manager immediately contacted the stakeholder to show and explain the latest project status reports.

What should the project manager do next?

A.Issue a memo stating that the project status can only be shared through authorized channels.
B.Include the stakeholder in the project status mailing list.
C.Review the project’s communications management plan with the project team and update as necessary.
D.Revise the status reports to clearly identify delays that should be acted on.

A

Solution: C. Review the project’s communications management plan with the project team and update as necessary.

The stakeholder was acting on unofficial information. The communication management plan, if created properly, will avoid this situation and ensure that the correct messages are sent to different stakeholders. After addressing the short-term issue, the project manager should address it long-term by reviewing and updating the communication management plan.

The other answer choices are incorrect. Issuing the memo and including the stakeholder in the project status mailing list will not solve the incorrect unofficial information from being sent out. Revising the status report is not an appropriate response because the project is still on track.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A customer is upset because a critical issue for a project deliverable has not been resolved by the agile team, even though troubleshooting has been running for several weeks. During the daily meetings, the team complains about the technical challenge and their lack of knowledge to resolve the issue.

Which two actions should the project manager take to resolve this situation? (Choose two)

A.Escalate the case to a functional manager to bring a technical expert to the team.
B.Explain the situation to the customer and include an action plan.
C.Keep the team working on the sprint backlog in order to accomplish the next release milestone.
D.Update the issue and risk logs, including the action plan to resolve the issue.
E.Set up a new release date for this deliverable with the product owner.

A

Solution: A and B. Escalate the case to a functional manager to bring a technical expert to the team. and Explain the situation to the customer and include an action plan.

Considering that the customer is already upset and that the team has not been able to solve the situation, the way to solve this will be to get help from outside the team and explaining the plan to the customer.

The other answer choices are incorrect. Continuing to work without a solution is not the best approach as the issue is still looming; updating the issue and risk logs would have already happened since the beginning of the issue a few weeks ago; unless they know how to solve the issue, they will be unable to forecast an accurate release date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

An IT contract for a project states that all team members must be certified in IT security. The project manager discovers that one team member presented a fake certificate.

What should the project manager do first to handle this situation?

A.Update the project management plan to include resources to get the team member certified.
B.Update the issue log and remove the team member from the project.
C.Ensure the remaining team members have valid certificates.
D.Investigate why this situation was not discovered earlier.

A

Solution: B. Update the issue log and remove the team member from the project.

Fake documentation is unethical and may damage the reputation of the team and relationship with the client. It is important for the project manager to firstly log the issue and remove the team member from the project. The project manager may also report it to the reporting manager.

The other answer choice are incorrect. They are steps that can be taken after the issue is logged and the team member is removed. The project manager should verify that all other team members are truly certified and investigate how to prevent this issue from happening again.

This question and rationale were developed in reference to:

Mastering Project Human Resource Management (No Date) Harjit Singh//5. Acquiring Project Human Resources/ [Item Consider Criteria Governing Project Human Resource Selection

The project team acquisition decisions are usually based on certain selection criteria. The criteria used to score the project team members may include, but are not limited to, the availability (when needed), cost (within budget), experience, knowledge, ability, job skills, team skills, attitude, interest, location, time zones, and communication capabilities of the team members. Some of the elements of these criteria are described in the following:

Experience: The current experience level of the candidate human resource must be compared with the required experience level.
Interest: The candidate human resource’s level of interest in the project must be determined.
Team skills: The candidate human resource’s ability to work well with other project team members must be determined.
Availability: The availability of the candidate human resource must be determined. The project manager may need to work with the functional managers to determine the availability.
Knowledge: The competency and proficiency of the human resource being acquired must be determined to assign that resource to the appropriate role on the project.]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

One of the retrospective action items that has recurred for the past two iterations is related to the verification and validation of the delivered functionality before production readiness.

Which two solutions should the project manager use? (Choose two)

A.Adjust velocity for the project team to address additional testing.
B.Incorporate unit and integration test criteria as part of the validation.
C.Modify the methodology of delivery to test-driven development.
D.Review the working agreement for acceptance criteria with the project team.
E.Include a product backlog item to build an integration test suite.

A

Solution: B and D. Incorporate unit and integration test criteria as part of the validation and Review the working agreement for acceptance criteria with the project team.

The project manager should incorporate unit and integration test criteria as part of the validation and review the working agreement for acceptance criteria with the project team. Working agreements help define what “ready” means (so the team can take in work) and what “done” means (so the team can judge completeness consistently).

The other answer choices are incorrect because they do not meet the criteria for validation. They either suggest masking the problem without addressing the root cause or do not introduce specific testing measures.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A project manager has been assigned to a multimillion-dollar project already in execution. During a project status meeting, one of the team members mentions that there are some delays because a senior executive is not responding to communications.

What should the project manager do?

A.Establish a process to send daily reminders to the senior executive.
B.Remove the task from the critical path so it will not affect the project schedule.
C.Use networking to contact the senior executive to get a response.
D.Escalate the concern to the senior executive’s manager.

A

Solution: C. Use networking to contact the senior executive to get a response.

The project manager should contact the senior executive directly to get a response. Stakeholder engagement is important in this scenario.

The other answer choices are incorrect because they do not offer a direct solution for the communication issue. The senior executive may ignore the daily reminders; removing the task may impact the project as a whole; and escalating the concern to the senior executive’s manager without first trying to contact the senior executive is not good for rapport.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A project manager is working in the fifth month of an implementation for a construction project. The planner reported that the current schedule performance index (SPI) and cost performance index (CPI) are 0.8 and 0.9, respectively.

Which two options will help to accelerate the project? (Choose two)

A.Adjust the working procedures to streamline and improve efficiency with the current resources.
B.Change the critical path by replacing some critical path activities with activities that have float.
C.Increase the number of resources to get more people involved and get activities done faster.
D.Rearrange the schedule so that some activities on the critical path can be done concurrently to reduce the project duration.
E.Ask the resources to work overtime to accelerate the project and achieve better results.

A

Solution: A and D. Adjust the working procedures to streamline and improve efficiency with the current resources. and Rearrange the schedule so that some activities on the critical path can be done concurrently to reduce the project duration.

By adjusting the working procedures to streamline and improve efficiency with the current resources and rearranging the schedule so that some activities on the critical path can be done concurrently to reduce the project duration, the project manager can accelerate the project without having to add additional resources or ask the team to work overtime.

The other answer choices are not the best way to accelerate the project. Changing the critical path by replacing some critical path activities with activities that have float will not accelerate the project, as it will simply move the bottleneck to a different activity. Increasing the number of resources to get more people involved and get activities done faster may not be the most cost-effective way to accelerate the project. Additionally, adding too many resources to a project can actually slow it down due to communication and coordination challenges. Asking the resources to work overtime to accelerate the project and achieve better results may not be sustainable in the long term, as it can lead to burnout and decreased productivity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A vendor for a large and complex project has been performing more work than what was originally anticipated in the time and material contract. This type of contract caused the project to be behind schedule and over budget. The contract is about to expire.
What should the project manager do?

A.Create a request for quotation (RFQ) to formulate a list of new vendors.
B.Shift to a master services agreement with appendices for the additional work as required.
C.Consult the lessons learned repository to formulate a list of potential new vendors.
D.Try to negotiate a fixed-price contract with the current vendor.

A

Solution: B. Shift to a master services agreement with appendices for the additional work as required.

The project manager should shift to a master services agreement with appendices for the additional work as required. This will allow for additional work to be added to the contract without having to renegotiate the entire contract. A master services agreement covers a wide range of services, simplifies modifications to the contract, and emphasizes value delivery.
The other options are incorrect.
Creating a request for quotation would only be helpful if the project manager is considering replacing the current vendor. This can disrupt the project and lead to additional delays.
Consulting the lessons learned repository to formulate a list of potential new vendors is not ideal because time is a factor, the contract is about to expire, and the project is already behind schedule.
A fixed-price contract is not ideal for this situation. These types of contracts are often used when the project scope is well-defined and stable. A fixed-price contract could lead to additional cost overruns if the scope of work changes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A client’s interactions with the project team have been somewhat negative. Project team members don’t want to be part of the project any longer.
What should the project manager do?

A.Schedule a meeting with the client to discuss the team’s concerns.
B.Adhere to the client’s expectations and sentiments without waiver.
C.Negotiate with the client and the project team to settle differences.
D.Involve all team members in stakeholder engagement activities.

A

Solution: C. Negotiate with the client and the project team to settle differences.
The project manager should negotiate with both the client and the project team to settle any differences and find a solution that works for everyone. The project manager should balance the team’s concerns with those of the client. In this scenario, the project manager’s role is to understand the client’s priorities while also resolving the issue of team dissatisfaction. It is important to maintain open communication and collaboration among all parties involved in the project to ensure its success. Additionally, creating a positive project team environment and addressing any concerns or conflicts that may arise can help prevent similar issues in the future.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A project manager is leading a major product development project. The project is currently in the middle of the fifth sprint, and the product release is scheduled for next quarter. The project manager receives unexpected news that the company has just been formally acquired by a major competitor. This competitor already has a similar product in their portfolio.

What immediate action should the project manager take to address the situation effectively?

A.Perform a comparative product analysis to identify similarities between the products.
B.Collaborate with the project manager overseeing the competitor’s product to align project activities.
C.Seek support from the project sponsor and initiate the appropriate change management procedures.
D.Prepare a project termination report and document the lessons learned from the ongoing project.

A

Solution: C. Seek support from the project sponsor and initiate the appropriate change management procedures.

The project manager should seek support from the project sponsor because the sponsor links the project team with the strategy and big-picture view at the executive level of the organization. Initiating the appropriate change management procedures ensures effective transformation to the new organizational landscape and that adjustments are made with structured processes. Change management procedures can help to minimize disruption and ensure that the transition is successful.

The other options are incorrect because they are not immediate priorities and may not be practical until the project manager has a better understanding of the sponsor’s plans for the project. When manager knows whether the project will be continued, terminated, or merged with the competitor’s product, they can then take action accordingly. The project manager should focus on organizational changes and determining the future of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

A project is close to completion when an unidentified and influential stakeholder appears and threatens to put the project in jeopardy by not approving the closing documents.

Which two actions should the project manager have done to avoid this? (Choose two)

A.The project manager should have carried out stakeholder identification during the initiation stage of the project.
B.The project owner should have informed the project manager about the stakeholders of the project.
C.Identifying and analyzing stakeholders should have been performed as an ongoing task throughout the project duration.
D.The stakeholder should have come forward for proper identification at the beginning of the project.
E.Creating awareness of the stakeholders’ concerns should have been continuously occurring throughout the project.

A

A project manager for a new project is tasked with applying agile practices to improve team performance. Which approach should the project manager take?

A.Utilize active listening techniques to address the needs of the team.
B.Request a budget from finance for training the team members.
C.Assign a budget for team activities during the planning phase of the project.
D.Ensure team retrospectives are done regularly.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A project manager is planning the next release for the software development team. The team has completed two releases to date, and the product backlog for the next release has been confirmed.

Which of the following tools should the project manager use to plan the duration for the next release?

A.Product roadmap
B.Resource calendar
C.Work breakdown structure (WBS)
D.Burndown chart

A

Solution: C. Work breakdown structure (WBS)

The WBS is a hierarchical decomposition of the work to be done in a project. It is used to estimate the total effort required to complete the project. By breaking down the work into smaller tasks, the project manager can get a better understanding of the time and resources required to complete each task. This information can then be used to estimate the overall duration of the project.

The other answer choices are incorrect. The product roadmap is a high-level plan for the development of the product but it does not provide any information about the time required to complete each release. The resource calendar shows the availability of resources, such as people and equipment but it does not provide any information about the tasks that need to be completed or the time required to complete each task. A burndown chart is used to track the progress of a project. It shows the amount of work remaining to be done over time but it is not used to estimate the duration of a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A team member is unable to work for one week because of sick leave. The team member is currently assigned to a task on the critical path.

What is the next step the project manager should take?

A.Choose another team member to take over the task immediately.
B.Evaluate the possible impacts of a project delay.
C.Refer to the risk response plan to mitigate this issue.
D.Convince the team member to proceed with completing the task.

A

Solution: B. Evaluate the possible impacts of a project delay.

Evaluating the possible impacts of this change on the project should be the first action the project manager takes to determine its effect on cost, time, and other constraints.

Choosing another team member to take over or proceed with the task could be detrimental if no proper handover is provided. The issue cannot be mitigated before it is evaluated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

An agile project was scaled from the feasibility study phase to the implementation phase. Due to time constraints, the same team is assigned to the project, except for one team member who was replaced with a new team member. Many of the team members do not get along with the new team member and are unwilling to work in the next phase.

How should the project manager ensure that the team is ready for the next phase?

A.Perform an incremental delivery assessment.
B.Force the team to stay together.
C.Request a formal team commitment.
D.Remove the new team member.

A

Solution: C. Request a formal team commitment.

The most helpful option is for the project manager to request a formal team commitment. An intra-team commitment mechanism is useful to review team norms and refresh the team’s commitment to the project and the new phase. Most of the projects fail to team fatigue and reluctance to change management during scale-up phases.

The option to perform an incremental delivery assessment and forcing the team to stay together do not address the concerns that the members have where their inability to get along take priority over delivering the work. The other option to remove the new team member may not address the situation if the work is unable to be delivered effectively with the reduced team size.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

During a retrospective meeting, project team members complain that open issues that were not fixed during the iteration are impacting their velocity. What should the project manager do to improve productivity?

A.Ensure team members attend daily standup meetings to discuss the impediments.
B.Document the issues in the issue log and wait to solve them at another time.
C.Extend the daily standup meetings to discuss the issues in more detail.
D.Escalate the issues to the project sponsor to get them solved immediately.

A

Solution: A. Ensure team members attend daily standup meetings to discuss the impediments.

The project manager should ensure team members attend daily standup meetings to discuss the impediments. Project managers should build their servant leadership skills of facilitation, coaching, and impediment removal.

The other answer choices are incorrect. These options suggest documenting the issue and taking action later; extending daily standups which is time-consuming; and escalating the issue and deflecting responsibility to the sponsor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

A project manager works at a construction company. The current project is a three year, multimillion-dollar initiative to rebuild a stadium. The first phase of the project has been completed within the three month timeframe and within budget.

What should the project manager do next?

A.Move on to the next phase.
B.Secure approval from the program manager.
C.Proceed with the contractual closure of the phase.
D.Begin the administrative closure process.

A

Solution: C. Proceed with the contractual closure of the phase.

The project manager should proceed with the contractual closure of the phase. The contractual closure of the phase is the process of finalizing all activities for the project, phase, or contract. Upon receiving closure, next phase can be started as per plan and budget.

The other answer choices are incorrect. Moving on to the next phase without closing the previous phase is not good practice; approval does not come from the program manager; and the administrative closure process occurs as part of final project closure activity, not phase completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

A Scrum team is halfway to its release. During the sprint demo, new software is selected by one of the developers and presented to the team. The new software was not planned work but meets the date for the release. Several prioritized features for the next two sprints are disrupted.

What actions should the team do to minimize the disruption?

A.Work with the product owner on the backlog to introduce the new software.
B.The scrum team makes the decisions themselves as a self-organized team and presents the change during the demo .
C.The developers reach out to the scrum master regarding the change to determine where and when the change can be discussed.
D.The scrum team evaluates the new software and informs the client about the impact to the release plan

A

Solution: A. Work with the product owner on the backlog to introduce the new software.

The project manager should work with the product owner on the backlog. The backlog is the only source of input for a scrum team to perform work. Only the product owner has the right to reprioritize work in the backlog. The product owner works with the scrum team as required to prioritize the backlog.

The other answer choices are incorrect. While the scrum team is a self-organized team they do not have the right to unilaterally introduce product changes. Product changes must be introduced via the backlog as decided by the product owner. While the scrum team will reach out to the Scrum Master, the option is only partially correct. Changes to the product must come through the backlog as determined by the product owner. Evaluating the new software may result in possible rejection of the product by the product owner as the product owner has not been allowed to understand and if in agreement reprioritize the backlog.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

A project manager in Location A works with a local team, while developers are in another remote location, and a quality assessor is in yet another remote location. The project manager is aware that these distances mean that the team could struggle with lag when needing to communicate.

What could the project manager do to mitigate this issue?

A.Increase the number of standup sessions per day.
B.Source new team members locally.
C.Create a fishbowl window.
D.Decrease the need for team communications through backlog grooming.

A

Solution: C. Create a fishbowl window.

There are a myriad of tools that project managers can employ to facilitate working with virtual and remote teams. Geographically distributed teams need virtual workspaces. A fishbowl window alleviates lag by providing a long-lived video link that remains open during the workday for a dispersed team. In this way, people can see and engage spontaneously with each other, reducing the collaboration lag otherwise inherent in the geographical separation.

The other answer choices are incorrect because they either do not solve the issue of communication lag or they are not feasible.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

At the start of a project, the team chose to leverage an agile approach to deliver the project, using user stories to capture requirements. As part of the organization’s control framework, the internal compliance department will request a copy of the approved requirements document.

What should be done to meet this compliance request?

A.Review the project approach with compliance, ensuring they understand how it will meet the control objective.
B.Print and assemble all user stories into one package at the end of the project and have the product owner approve them.
C.Assign the compliance requirement as a task on the project’s Kanban board for the product owner.
D.Review the project approach with compliance, indicating that the control objective is not required because the project is using agile.

A

Solution: A. Review the project approach with compliance, ensuring they understand how it will meet the control objective.

In order to meet the compliance request, the project manager should review the project approach. This encapsulates onboarding of compliance to ensure that there is understanding of the agile development approach, and how using the agile approach will ensure compliance with the control objective.

The other answer choices are incorrect. “Print and assemble…“This option is related to the waterfall development approach. Besides there action of onboarding compliance to the agile approach and satisfying the requirement is missing in this answer. “Assign the compliance requirement…“This option does not resolve the question that compliance has posed besides inappropriately deflecting accountability to the product owner to explain how the agile approach will meet compliance requirements. “Review the project approach…“Agile development does not presuppose non compliance to control objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

In a large organization, a project is experiencing communication difficulties. Team members and functional leaders are expressing that they are informed too late or not included in project discussions, or are simply unaware of important project delivery information.

How should the project manager address this situation?

A.Ensure adherence to the agreed process as stated in the communications plan.
B.Send a regular email update to each functional manager regarding the project’s status and next steps.
C.Coordinate a meeting with the team leaders to find a solution.
D.Refer to the RACI chart on who needs to know what and when and ensure compliance.

A

Solution: A. Ensure adherence to the agreed process as stated in the communications plan.

The project manager should review the communications plan and ensure adherence to the agreed process as stated within. The project manager should develop an appropriate approach and plan for project communication activities based on the information needs of each stakeholder or group, available organizational assets, and the needs of the project. This plan needs to be reviewed and updated.

If there is any communication gaps during the project, it is never too late to include key stakeholders and improve communication.

The other answer choices are incorrect because they do not mention the importance of a communications plan to address the communication difficulties.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

A project manager works in an organization using a hybrid project delivery approach. The scope of the project is to implement a new human resources system. The infrastructure will be delivered by another project, and both projects are part of a business transformation program aimed to improve human resources processes. The project schedule needs to be finalized, but the project manager of the other project is unable to provide delivery dates for the infrastructure.

What should the project manager do?

A.Wait for the infrastructure project to have a schedule and then develop the human resources system project’s schedule.
B.Discuss the situation with the other project manager, agree on a few milestones, and then continue working on the human resources system project’s schedule.
C.Develop a schedule based on the information available from the program management team and then progressively align the milestones with the infrastructure project.
D.Develop a schedule based on the information available and ask the other project manager to align the infrastructure milestones with the human resources project’s delivery dates.

A

Solution: C. Develop a schedule based on the information available from the program management team and then progressively align the milestones with the infrastructure project.

Program milestones are established and must be followed. In this case, the project schedules should be aligned with those milestones. They should know the dependencies between projects in the program and adjust their schedules accordingly.

The other answer choices are incorrect. They do not take into account the entire program management principles and are not aligned with the program manager as a key stakeholder in this case.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Before a project evaluation meeting, a key stakeholder complains that the project does not deliver the expected business benefits. The project manager needs to prepare for the meeting to effectively address the complaint. What should the project manager do first? A.Review the change control log for approved variances in the project deliverable. B.Review the communications management plan and stakeholder engagement plan. C.Review the project performance metrics and acceptance test results. D.Review the project objectives and success criteria.
Solution: D. Review the project objectives and success criteria. Project success is measured by the achievement of project objectives and success criteria. The project manager should review these two to understand the key stakeholder's complaints before taking action. The other answer choices are incorrect while the change control log may provide insights into changes that have been made to the project deliverables, it does not directly address the issue of whether the project has delivered the expected business benefits. The communications management plan and stakeholder engagement plan may provide information on how stakeholders have been engaged throughout the project, but it does not directly address the issue of whether the project has delivered the expected business benefits. The project performance metrics and acceptance test results may provide information on how well the project has met its technical requirements, but they do not directly address the issue of whether the project has delivered the expected business benefits.
26
A team member in a hybrid organization informs the project manager of a new way to execute an activity with a shorter duration. The project manager has not used the new process before, but a trusted team member explains that their previous experience with the process validates the efficacy of the new process. Which two actions should the project manager take? (Choose two). A.Involve the team member's functional manager. B.Postpone the decision until the next sprint. C.Update the work breakdown structure (WBS). D.Assess the impact of adopting the new process. E.Communicate the impact with key stakeholders.
Solution: D and E. Assess the impact of adopting the new process and Communicate the impact with key stakeholders. The project manager should assess the impacts of implementing the new process and communicate the findings with key stakeholders. Assessment will help identify the opportunities and threats of implementing the new process. It is necessary that the project manager communicates the results of the analysis with key stakeholders. The other answer choices are incorrect. They may occur after the impact is assessed and the stakeholders are made aware. Involving the functional manager may not be necessary at this stage. Postponing the decision is not efficient, the project manager should assess the impact first because the new process may help execute an activity with a shorter duration, which would benefit the project. Updating the WBS is not necessary at this time because no decision has been made at this point.
27
A member of the project team who was hired for six months to complete a specific task has decided to leave the project in the fifth month to pursue another job opportunity. What should the project manager's immediate action be? A.Modify the contract to ensure the team member will complete the packages in the fifth month. B.Determine what remaining packages might be affected and ensure that adequate resources are available. C.Confirm the terms of the team member's contract to close their participation appropriately. D.Check the contingency reserve for extra resources to hire a new member to finish these packages.
Solution: C. Confirm the terms of the team member's contract to close their participation appropriately. The first step the project manager should take to ensure a smooth transition and minimize any disruption to the project. It is important to understand the terms of the contract, such as the notice period and any outstanding deliverables, to determine the appropriate course of action. The other answer choices are incorrect because they are not the first step the project manager should take. Modifying the contract at this point is not practical and may not be legally viable. Determining the affected packages and ensuring resources is important, but it should come after understanding the contractual obligations. Checking the contingency reserve for new resources can be a later step, but first, the project manager needs to understand the scope of the situation.
28
An organization is trying to adopt agile approaches to execute projects for their customers. During project planning, the product owner proposed that any release to the customer should be approved by the legal department before it is shipped. The development team is disappointed as it may potentially delay releases and the delivery schedule. Since other departments in the organization do not use agile, what should the project manager's role be as a servant leader? A.Advise senior management to introduce agile techniques to all departments to ensure seamless services to customers. B.Continue with standardized organizational procedures to ensure compliance with policies and avoid creating problems. C.Inform the customer about the organizational procedures and ask them to discuss this with the organization's leadership. D.Work with the legal department and other applicable departments to review the processes that support the project delivery.
Solution: D. Work with the legal department and other applicable departments to review the processes that support the project delivery. As a servant leader, the project manager should work with the legal department and other applicable departments to review the processes that support the project delivery. This will help ensure that the legal requirements are met while also minimizing delays to the delivery schedule. The project manager's role as a servant leader is to facilitate collaboration and communication between different departments and stakeholders to ensure project success. The other answer choices are incorrect. Advising senior management would be a time-consuming and complex initiative that may not directly solve the issue. Continuing with organizational procedures and ignoring the issue is not proactive, will not resolve the issue, and could negatively impact the project. Informing the customer and asking them to discuss this with the organization's leadership transfers the responsibility for the issue to the customer and is inappropriate. The project manager must facilitate and remove obstacles, not other stakeholders.
29
A project is in the execution phase when new team members are onboarded. Before onboarding the new team members, what should the project manager do to reduce the impact of this action on project performance? A.Conduct a session to update the existing social agreement on how the team will work collaboratively. B.Schedule a session to let the existing team members explain to the new ones about the current social contract. C.Organize a meeting with all of the team members to communicate the current social agreement. D.Plan a meeting with the new team members to explain the rules included in the social contract.
Solution: A. Conduct a session to update the existing social agreement on how the team will work collaboratively. When new team members join an existing team, a new team is created. The project manager should conduct a session to update the existing social agreement on how the new team will work collaboratively. Setting the ground rules of the new team is a key factor and the role of the project manger in facilitating the participation of everybody to reach an agreement. The other answer choices are incorrect because they do not suggest updating the current social agreement to accommodate the new team members.
30
A project is nearing completion and a stakeholder wants to know how the project outcomes will impact the organization. What should the project manager review with the stakeholder? A.Business case B.Benefits management plan C.Project charter D.Assumption log
Solution: B. Benefits management plan The project manager should review the benefits management plan with the stakeholder as it is the best document to describe how and when the benefits will be delivered and the outcome's impact on the organization.
31
A complex, multimillion-dollar, multi-year product development project requiring unique knowledge is 70% complete. Contract termination is a possibility due to project deliverables and execution being not acceptable. Despite the strained relationship, the vendor is ready for rework at no penalty. What should the project manager do to manage this situation? A.Ask the customer to permit rework as the vendor has unique knowledge of the product. B.Finalize the new definition of done (DoD) with the customer and make the vendor bear the cost of rework. C.Facilitate the negotiation of the acceptance criteria between the customer and vendor. D.Direct the vendor to rework the deliverable since they did not meet the requirements.
Solution: C. Facilitate the negotiation of the acceptance criteria between the customer and vendor. The best course of action for the project manager in this situation is to facilitate the negotiation of the acceptance criteria between the customer and vendor. This is because it is the most collaborative and consensus-building approach. It also allows the project manager to ensure that the rework is done in a way that meets the needs of both the customer and the vendor. The other answer choices are incorrect and are less effective. Asking the customer to permit rework as the vendor has unique knowledge of the product is a good idea, but it is important to get the customer's agreement before proceeding with the rework. Finalizing the new DoD with the customer and making the vendor bear the cost of rework could be good if the vendor is not willing to rework the deliverables at no penalty. However, it is important to be mindful of the cost of rework and the impact it will have on the project schedule. Directing the vendor to rework the deliverable since they did not meet the requirements is the most direct approach, but it could damage the relationship between the customer and vendor. Additionally, it is important to make sure that the vendor is willing and able to rework the deliverables to the customer's satisfaction.
32
An agile project is midway through its ten iteration cycles. During the last iteration, the team had to work overtime to accomplish the goal. In the iteration retrospective, the team agreed that they took more time than planned because they did not have the required experience when they executed the assigned tasks for the first time. What should the project manager do? A.Ask the project sponsor for additional team training. B.Ask the sponsor to approve a change request for more time in future iterations. C.Ask the team to re-assess their effort estimates in the iteration planning session. D.Ask the product owner to reprioritize the product backlog.
Solution: C. Ask the team to re-assess their effort estimates in the iteration planning session. The team learns from previous iterations how to do things better. The actions to address any shortcomings are taken as part of the next planning session. The next action should be to assess whether the team now has sufficient experience to perform the tasks within the planned timeframe for the next iteration. The other answer choices are incorrect. The options to seek additional training and reprioritize the product backlog may not affect the team's ability to complete in the next iteration. The option to ask the sponsor to approve delayed timelines is also unnecessary if the team assesses that it now has the necessary experience to complete the next iteration within schedule.
33
A new product development project has been launched. The project sponsor has reviewed the results of the risk analysis as documented in the risk register and is confident the project will be successful. However, key investors are not as confident and want more information about the project and risks before investing. What should the project manager do? A.Present a detailed analysis of the market, business plan, and risk management plan to investors. B.Prepare and present a cost-benefit analysis to investors. C.Assess and describe all the risks associated with the product development and launch to the stakeholders. D.Plan development activities to engage stakeholders in various phases of the project.
Solution: A. Present a detailed analysis of the market, business plan given by the product owner, and risk management plan to investors. The project manager should present a detailed analysis of the market, business plan, and risk management plan to investors will provide the information necessary for investors to make a choice in whether to invest. The other answer choices are incorrect. Cost-benefit analysis is only part of the information needed to make an educated decision on whether to invest. Presenting a risk analysis and management plan is only part of the information needed to make an educated decision on whether to invest. Stakeholder involvement may or may not ensure continued investment in the product.
34
An innovative project is leveraging artificial intelligence (AI) to identify chemical compounds for the development of new products. The AI processing phase can vary in duration, ranging from three days to two weeks, and the outcomes are unpredictable. The project's primary objective is to deliver at least one product specification within a fixed two-month timeframe while adhering to a strict budget that cannot be increased. What action should the project manager take to optimize the use of the fixed budget and deliver the highest possible business value? A.Ensure that the specification iterations are limited to 50% of the overall project duration. B.Ensure that the AI processing is limited to 25% of the overall project budget. C.Plan an iteration directly after AI processing to analyze and prioritize the development goals. D.Plan the specification work as a predictive task with a fixed duration to guarantee value.
Solution: C. Plan an iteration directly after AI processing to analyze and prioritize the development goals. By planning an iteration immediately following the AI processing, the project team can analyze the results, prioritize the development goals based on the findings, and focus the remaining budget on the most valuable tasks. The other options are incorrect. Limiting the specification iterations to 50% of the overall project duration does not directly address the issue of maximizing the business value within the remaining budget. Additionally, it might not be feasible given the unpredictable nature of AI processing times. Limiting the AI processing to 25% of the overall project budget might not be feasible or beneficial. AI processing is a crucial part of the project, and it's unpredictable by nature, constraining it could lead to sub-optimal results. Planning the specification work as a predictive task with a fixed duration doesn't account for the unpredictability of the AI processing, and it may not necessarily maximize the business value of the remaining budget. This approach might not align well with the nature of innovative projects, which often need to be flexible and adaptive.
35
During project execution, the audit team determined that critical regulatory requirements are not being met. What should the project manager have done first to avoid this problem? A.Updated the issue log with regulatory requirements. B.Assessed the internal and external regulatory environments. C.Had the audit team review the project management plan. D.Included a member of the audit team on the project.
Solution: B. Assessed the internal and external regulatory environments. At the beginning of the project, understand the regulatory requirements based on the type of project and the industry will allow the team to include tasks in the plan geared to meeting the requirements, ensure enough resources are allocated to addressing the requirements and reducing the amount of rework that would result from not doing the assessment.
36
A company must launch a global product to respond to a competition threat. As part of an agile approach, the team chooses Region X as the baseline to test the first iteration. While the product meets standards and requirements in Region X, it does not comply with two of the other regions' standards. What should the project manager do? A.Ensure that the product meets the standards and requirements in Region X and plan future iterations to address the noncompliance with the standards in the other regions. B.Document this as a noncompliance in the quality management plan and correct it in the next iteration. C.Re-plan all of the iterations to meet all three regions' standards within the scope of the work. D.Connect with customers from each region to reach an agreement on the existing design.
Solution: A. Ensure that the product meets the standards and requirements in Region X and plan future iterations to address the noncompliance with the standards in the other regions. An agile approach refines work items and delivers them frequently. It also assures controlling quality to comply with the requirements throughout the project. In the case of non-compliance, the project manager should plan iterations to implement other requirements and standards. The project manager should prioritize ensuring that the product meets the standards and requirements of the region where it will be launched first. Once the product is launched in Region X, the project manager can then plan future iterations to meet the standards and requirements of the other regions. This approach allows the project manager to respond to the competition threat while also ensuring that the product meets the needs of all of the target markets. The other options are incorrect because are not the most realistic and feasible solutions. Documenting this as noncompliance in the quality management plan is incorrect because it does not address the fact that the product does not meet the standards and requirements of two of the other regions. The project manager needs to take action to modify the product to meet those standards. Re-planning all iterations is incorrect because it is not feasible to re-plan all of the iterations to meet all three regions' standards within the scope of the work. This would require a significant amount of rework and could delay the launch of the product. Connecting with customers is incorrect because it does not resolve the issue of the product not meeting the standards and requirements of two of the other regions. The project manager needs to take action to modify the product to meet those standards.
37
The project manager is responsible for a major project that involves working with many vendors. A key project concern is related to the quality and timely delivery of procured products and services as committed by the vendors. What should the project manager do to ensure that the products meet the quality requirements and are delivered on time? A.Raise an item in the risk register to capture potential impacts related to delays in the procurement of products and services, mitigating the risk of suboptimal quality. B.Conduct procurement performance reviews on a regular basis with all contracted vendors to ensure that products and services are all delivered or will be delivered on time and as per the agreed-upon contract. C.Delegate the management of the procurement process and the interaction with all vendors to the organization's procurement department as they have the tools and means to deal with a large number of vendors. D.Review vendor management plan with all vendors to ensure they are in agreeance with the plan, mitigating the risk of undelivered and low quality products.
Solution: B. Conduct procurement performance reviews on a regular basis with all contracted vendors to ensure that products and services are all delivered or will be delivered on time and as per the agreed-upon contract. By conducting procurement performance reviews on a regular basis, the project manager can proactively identify and address any potential issues with vendor performance. This will help to ensure that the project meets its procurement objectives and that the products are delivered on time and meet the quality requirements. The other answer choices are incorrect because they are not enough to ensure that the products meet the quality requirements and are delivered on time, and the project manager needs to monitor vendor performance to identify and address any potential problems.
38
Early in a project, the project manager realizes that one of the key team members is not prepared to perform the assigned task. How should the project manager address this issue? A.Ensure training is built into the resource management plan. B.Review the training requirements with the team member. C.Review each required task with the team member when it starts. D.Escalate the issue to the resource's functional manager for resolution.
Solution: B. Review the training requirements with the team member. By reviewing the specific skills and knowledge needed for the assigned tasks, the project manager can identify any gaps and develop a plan to address them. This could involve providing additional training, mentoring, or shadowing opportunities. The other answer choices are not as effective. Review each required task with the team member when it starts: While this approach could provide the team member with some initial guidance, it does not address the underlying lack of preparation. Without proper training or support, the team member may struggle to perform the tasks efficiently and effectively. Escalate the issue to the resource's functional manager for resolution: While the functional manager may be able to provide some assistance, it is ultimately the project manager's responsibility to ensure that their team members are prepared to perform their assigned tasks. This includes identifying and addressing any training needs. Ensure training is built into the resource management plan: While this is a good long-term solution, it does not address the immediate issue of the unprepared team member. The project manager needs to take action now to ensure the team member can contribute to the project.
39
The project manager discovers that a stakeholder provides inaccurate status reports to the steering committee. Moreover, the stakeholder does not have accurate information on the project. What should the project manager do first? A.Update the communications management plan to ensure that the stakeholder receives the necessary information. B.Schedule a meeting with the stakeholder to discuss the inaccurate reporting and provide accurate information. C.Send regular updates to the steering committee to keep them informed about the project. D.Escalate the issue and request that all reports be preapproved before they are sent to the steering committee.
Solution: B. Schedule a meeting with the stakeholder to discuss the inaccurate reporting and provide accurate information. By scheduling a meeting with the stakeholder, the project manager can take a proactive approach to addressing the issue of inaccurate reporting. The meeting will provide an opportunity to identify the root cause of the problem, discuss potential solutions, and develop a plan to improve the accuracy of the stakeholder's reporting. This will help to ensure that the steering committee has the information it needs to make informed decisions and that the project is able to stay on track. The other answer choices are not as effective. Update the communications management plan to ensure that the stakeholder receives the necessary information: While this is a good long-term strategy, it will not address the immediate issue of the stakeholder providing inaccurate information. The project manager needs to first determine why the stakeholder is providing inaccurate information and then take steps to correct the situation. Send regular updates to the steering committee to keep them informed about the project: While this is important, it will not address the issue of the stakeholder providing inaccurate information. The project manager needs to ensure that the stakeholder is providing accurate information, not just that the steering committee is receiving accurate information. Escalate the issue and request that all reports be preapproved before they are sent to the steering committee: This is an extreme measure that should only be taken if all other options have been exhausted. Preapproving all reports will slow down the communication process and may not prevent the stakeholder from providing inaccurate information.
40
A project manager recently took over a project from a project manager who left the company. The new project manager is aware that the previous project manager had a very authoritarian style of management and made all the decisions regarding the project. The new project manager notices that a senior supervisor's morale is low. What should the new project manager do? A.Increase the supervisor's level of authority. B.Identify the cause of the morale issue. C.Modify the role of the supervisor in the project. D.Speak with the supervisor and update the project issue log.
Solution: B. Identify the cause of the morale issue. The new project manager should first gather additional information to identify the root cause of the low morale issue. Hence this option is the correct answer. The other answer choices are incorrect. Increasing the supervisor's level of authority or modifying the role of the supervisor in the project or speaking with the supervisor and updating the project issue log will not improve the senior supervisor's morale.
41
A project is following a strategic plan that includes key milestones that have been aligned with stakeholders. As the work is being executed, new tasks arise along with important dependencies that prevent the work from progressing as planned. The team is unable to determine who should make decisions and take action on the new tasks and dependencies. What should the project manager do? A.Use a RACI chart to facilitate team task accountability. B.Use a Gantt chart to ensure milestones are accomplished. C.Ask the sponsors who have responsibility. D.Use a work breakdown structure (WBS) to ensure requirements are covered.
Solution: A. Use a RACI chart to facilitate team task accountability. A RACI (responsible, accountable, consult, and inform) chart shows the project resources assigned to each work package. It is used to illustrate the connections between work packages, or activities, and project team members. The other answer choices are incorrect. A Gantt chart shows schedules without assigning responsibility; the sponsors should not need to be consulted if a RACI is in place and agreed; and the WBS does not include the decision-making authority.
42
A project manager is planning for a complex project that must deliver a high-quality product within the agreed-upon budget. The project stakeholders are eager to see the product launched and are pressuring the team to deliver the product as soon as possible. The project manager must determine the project's estimated duration and address stakeholder expectations. How should the project manager determine a realistic project duration estimate? A.Confirm stakeholder delivery expectations. B.Estimate the duration of each project task. C.Analyze industry benchmarks and standards. D.Tell the team to create a detailed release plan.
Solution: B. Estimate the duration of each project task. Estimating task duration helps ensure the project is completed on time, within budget, and to the satisfaction of stakeholders. By estimating task durations accurately, project managers can provide stakeholders with a realistic timeline for project completion. This helps manage stakeholder expectations and reduces the likelihood of disappointment or frustration. It also helps to identify potential roadblocks and dependencies. The other answer choices are incorrect. Confirming stakeholder delivery expectations is not an effective or reliable way to estimate project duration. An industry benchmark is a standard or reference point often used to compare an organization's performance to that of its peers or competitors. A detailed release plan provides a false sense of predictability to stakeholders and requires significant effort to maintain later in the life cycle as the situation evolves. A high-level release plan is more appropriate for complex projects.
43
At project initiation, a quote for the required services was requested from a vendor, and the work was estimated at US$100,000. As the project progressed, requirements were updated following the company's procurement process, and a modified quote was received for more than US$250,000. The allocated contingency funds are not sufficient to cover the difference. What should the project manager do? A.Restart the procurement process and select a new vendor. B.Review the contract type that will be awarded to the vendor. C.Proceed with the best offer as per the procurement process. D.Engage the steering committee and escalate the issue.
Solution: D. Engage the steering committee and escalate the issue. The project manager should engage the steering committee and escalate the issue. This is the best way to ensure that the project can proceed without being delayed or derailed by the increased cost of the services. The steering committee may be able to provide additional funding for the project or may be able to help the project manager find ways to reduce the cost of the services. The other answer choices are not as effective. Restarting the procurement process and selecting a new vendor is a drastic measure that should only be taken as a last resort. It is likely to delay the project and may not result in a lower cost. Reviewing the contract type that will be awarded to the vendor is not enough to address the issue of the increased cost of the services. Proceeding with the best offer as per the procurement process is not a good idea, as it will likely result in the project exceeding its budget.
44
A key stakeholder is upset about the new features in the current iteration for the product. The key stakeholder was unavailable during the last review and did not have the opportunity to provide input. What should the project manager have done to prevent the stakeholder from being upset? A.Waited until all stakeholders approved the change before implementing B.Ensured that updated project information is always accessible to all stakeholders C.Met individually with every stakeholder to avoid disagreement D.Scheduled meetings only when all stakeholders could be present
Solution: B. Ensured that updated project information is always accessible to all stakeholders It is imperative that stakeholders have updated project information that is accessible. This transparency is necessary to ensure all involved are well aligned about the product outcome. The other answer choices are incorrect. Waiting for the stakeholders to be present or to approve, or meeting with them individually does not avoid disagreement and may cause unnecessary delays.
45
A lengthy upgrade project is being delivered in a series of phased outputs. The end users will face some level of disruption during each phase prior to the outputs being achieved. What should the project manager do to ensure that the intended value is being delivered at each phase? A.Gather feedback using surveys of the end user experience and analyze the results. B.Review the actual costs incurred to ensure that the project remains on budget. C.Validate the scope to ensure that the required quality of outputs is being met. D.Track progress toward each benefit, based on the benefits management plan.
Solution: D. Track progress toward each benefit, based on the benefits management plan. In order to ensure that the intended value is being delivered or on track to be delivered, the project manager should track progress toward each benefit, based on the benefits management plan. The other answer choices are incorrect because they do not mention the benefits management plan. The benefits must be identified and measurements put in place to track progress towards the benefits.
46
A company is transitioning from using a predictive approach to a hybrid predictive-agile project implementation. The leadership team is concerned about benefits realization and is closely following up on one of the project iterations with the project manager. What should the project manager do in this situation? A.Update the leadership team with a quantifiable value report for each iteration. B.Demonstrate the business value to the leadership team and get their buy-in. C.Keep delivering iterations of the solution and show the benefit increments to the leadership team. D.Wait for the leadership team to share the benefits realization updates for each iteration with management.
Solution: C. Keep delivering iterations of the solution and show the benefit increments to the leadership team. As the team is transitioning to a hybrid predictive-agile environment, the project team will use new metrics that matter to the management team. Metrics for agile projects often provide a historical track record so project teams can use such data for improved forecasts and decision making. In the agile environment delivering business value is the responsibility of the project team, who will collaboratively produce the benefit incrementally.
47
One of the project vendors is late in providing a related product solution, which is affecting the release due dates. What should the project manager do to help the agile team manage this impediment? A.Work with the vendor to understand the alternatives. B.Review and update the release date with the team. C.Have the technical lead escalate the issue to the functional manager. D.Have the team members and experts work together on a solution.
Solution: A. Work with the vendor to understand the alternatives. The project manager should take ownership of the impediment and work with the vendor to find solutions or alternatives. The project manager can work with the vendor to identify potential alternatives that could mitigate the delay. The project manager also needs to understand the full scope and impact of the delay. The other answer choices are incorrect because before taking action, the project manager should have a thorough understanding of the issue and possible paths forward. Reviewing and updating a release date without assessing the delay and having an accurate release date is not good practice. Escalation may be necessary, but the project manager should gain insight into the issue and potential resolutions beforehand. There is also not typically a functional manager in an agile environment. The team cannot make decisions or find a solution without involving the vendor.
48
A project team is working on backlog items within a four-week sprint. Suddenly, a critical team member announces that they will unexpectedly be absent for one week, leaving ongoing tasks incomplete. What would be the most appropriate action for the project manager to take in this situation? A.Support a knowledge transfer between the team member who will be away and the other project team members. B.Add a temporary resource to the team to help increase velocity and complete the items for this sprint. C.Remove a few items from the current sprint after getting the approval of the product owner. D.Increase the sprint duration so the team can complete all the planned items and present them to the product owner.
Solution: C. Remove a few items from the current sprint after getting the approval of the product owner. Removing a few items from the current sprint, with the approval of the product owner, is the most appropriate action in this situation. It allows the team to focus on completing the most critical and valuable tasks within the sprint's original time frame. The other options are incorrect because they are not as suitable for this scenario. Knowledge transfer takes time and may not be feasible given the sudden and unexpected nature of the team member's absence. Knowledge transfer is a good practice in general, but it may not be the most appropriate action for this specific situation. Adding a temporary resource to the team is not the most practical option and may not be efficient or cost-effective for such a short duration, and it could disrupt the team's workflow. Changing the sprint duration disrupts the sprint planning and review process and can lead to various issues, including reduced predictability and potential scope creep.
49
During a project team meeting, team members have identified a list of risks that may occur during the project. The project sponsor would like to meet with the project manager to evaluate the importance of each risk. What type of analysis should the project manager perform in preparation for a meeting with the sponsor? A.Qualitative risk analysis B.Quantitative risk analysis C.Monte Carlo risk analysis D.Expert judgment analysis
Solution: A. Qualitative risk analysis. Qualitative risk analysis evaluates the importance of each risk in order to categorize and prioritize individual risks for further attention Qualitative risk analysis is the consideration of a range of characteristics such as the probability of occurrence, degree of impact on the objectives, manageability, timing of possible impacts, relationships with other risks, and common causes or effects. The other options are incorrect because they are not the best way to evaluate the importance of each risk identified by the team. Quantitative risk analysis is incorrect because it examines the combined effect of identified risks on the desired outcome. A Monte Carlo risk analysis is a technique that computes or iterates the project cost or project schedule many times using input values, selected at random from probability distributions of possible costs or durations, to calculate a distribution of possible total project cost or completion dates. Expert judgment may be used for risk analysis, but it is not a primary technique used to evaluate the importance of individual risks. Expert judgment may be subject to biases and may only offer a limited perspective. Therefore, the correct answer is qualitative risk analysis.
50
During a predictive project, the project manager is in the process of finalizing the exit criteria for a significant system development project. At this stage, a stakeholder responsible for risk and compliance informs the project manager that an additional deliverable must be completed due to recently passed legislation by the local government. This requested change is expected to have an impact on the scheduled release date of the project. What should the project manager do? A.Meet with the stakeholders and advise them that the request was not part of the exit criteria. B.Collaborate with the stakeholder and submit a change request to the Change Control Board (CCB). C.Escalate the issue to the sponsor to avoid delaying the project release date. D.Add this new risk to the risk register and monitor because changes are outside the project scope
Solution: B. Collaborate with the stakeholder and submit a change request to the Change Control Board (CCB). When a stakeholder requests a change that impacts the project's scope and schedule, it's essential to collaborate with the stakeholder to fully understand the nature and implications of the change. Following that, submitting a formal change request to the Change Control Board (CCB) is the proper approach. The CCB is responsible for evaluating changes and making informed decisions about their approval or rejection. By submitting a change request, the project manager can ensure that the impact of the change is assessed and that the stakeholders are informed of the potential consequences. The other options are incorrect because they do not address the fundamental need to properly evaluate and manage the requested change through a formal process. Advising the stakeholder that the request was not part of the exit criteria is not enough, as the legislation requires the additional deliverable. Escalating the issue to the sponsor may not be necessary, as the CCB is already empowered to approve changes. The sponsor's involvement should come after a thorough assessment and formal change request submission. Adding the new risk to the risk register and monitoring it is not enough, as it does not address the need to approve the change request. Treating this situation solely as a risk may not be sufficient to manage the change effectively.
51
A company has launched a new strategic project. The goal and scope of the project were loosely defined at the executive committee meeting, and the stakeholders have been appointed. The project manager needs to hold the kickoff meeting. However, most of the stakeholders are in different locations and some are on vacation. What should the project manager do? A.Hold the kickoff meeting with the available stakeholders and update others later. B.Postpone the kickoff meeting until the stakeholders have returned. C.Schedule one-on-one sessions with the stakeholders before they leave. D.Arrange a virtual team kickoff meeting with the stakeholders.
Solution: D. Arrange a virtual team kickoff meeting with the stakeholders. A virtual team kickoff meeting allows the project manager to engage with all stakeholders, regardless of their location or vacation schedule. This ensures that all stakeholders receive the same information and have an opportunity to ask questions. Additionally, virtual team kickoff meetings can be recorded and shared with stakeholders who are unable to attend live. The other answer choices are incorrect. Holding the kickoff meeting with only some stakeholders present can lead to a lack of alignment and understanding among stakeholders. Additionally, updating stakeholders who were not present can be time-consuming and may not be as effective as providing them with the information in person. Postponing the kickoff meeting can delay the start of the project and may not be feasible if the project has a tight deadline. While one-on-one sessions with stakeholders can be helpful for gathering input and addressing concerns, they do not provide the same level of engagement and interaction as a group meeting.
52
A project manager is managing a project using an agile approach. The project is nearing its final stages, and the team is reviewing the project deliverables. During this review, it becomes evident that a crucial feature is missing from the project's artifacts. This feature is necessary for the system to comply with a new government regulation. How should the project manager resolve this issue? A.Ask the product owner to create a user story for the next sprint. B.Meet with the project team to reevaluate the product roadmap. C.Draft a project termination report and record the lessons learned. D.Continue with the delivery and update the definition of done (DoD).
Solution: A. Ask the product owner to create a user story for the next sprint. A crucial feature is missing, so the appropriate action is to work with the product owner to capture it as a user story and prioritize it for inclusion in the next sprint. By creating a user story for the missing feature, the product owner can prioritize it in the backlog and ensure that it is developed and delivered quickly and efficiently. The other options are incorrect because they are not as effective. Meeting with the project team to reevaluate the product roadmap may not be necessary and should not be the most immediate action to address the missing feature. The product roadmap is typically not reevaluated in response to a single missing feature. Drafting a project termination report and documenting the lessons learned is premature. It would only be necessary if the project could not be completed successfully. Continuing delivery and updating the DoD does not address the missing feature. Continuing with the delivery without addressing the missing feature could lead to non-compliance and other issues. While updating the DoD is important for future sprints, it doesn't immediately address the issue at hand.
53
An organization is halfway through a five year project and everything has progressed as scheduled. The latest project assessment indicates that the project will not be in compliance with a recently introduced international regulation. What should the project manager do? A.Proceed with the project because the new regulation is not part of the initial project requirements. B.Conduct a workshop with the project steering committee to review the new regulation and find a resolution. C.Leverage the contingency reserve to fund the additional tasks required for the new regulation. D.Ask for funds from the management reserve because the new regulation is an unknown risk.
Solution: B. Conduct a workshop with the project steering committee to review the new regulation and find a resolution. The project manager needs to work with the project steering committee to find a resolution and ensure compliance with the new regulation The other answer choices are incorrect. Proceeding without addressing the new regulation will result in non-compliance upon project completion. The project manager should not ask for new funds or leverage the contingency reserve without getting the approval of the change control board.
54
A project was undertaken to set up a new business function in the company. Several months after completion, the project manager is still handling business operations for the project while working on another project. What should the project manager have done at the beginning of the project to prevent this? A.Ensured that the revision to the organizational structure was a deliverable. B.Included the transition plan as a deliverable in the project closing process. C.Clarified the RACI chart with the project sponsor at the project's onset. D.Ensured that the recruitment process was included in the project management plan.
Solution: B. Included the transition plan as a deliverable in the project closing process. By including the transition plan as a deliverable in the project closing process, the project manager can proactively prevent the issue of ongoing business operations and ensure that the project is successfully handed over to the business operations team. This will help to free up the project manager's time so that they can focus on other projects. The other answer choices are not as effective. While a revision to the organizational structure may be a necessary step in setting up a new business function, it is not a deliverable in the project management sense. The project manager should focus on delivering the project deliverables that are outlined in the project scope statement. A RACI chart is a useful tool for clarifying roles and responsibilities, but it does not address the specific issue of handing over the project to the business operations team. The project manager needs to develop a transition plan that specifically outlines the steps for handing over the project. The recruitment process may be a necessary step in setting up a new business function, but it is not a deliverable in the project management sense. The project manager should focus on delivering the project deliverables that are outlined in the project scope statement.
55
A project team is in the planning phase of a complex project. The project has an end-date constraint to launch a new product with which they have no previous experience. The project sponsor is requesting a detailed schedule, but the team is unable to predict when tasks will occur throughout the project lifecycle, especially because some of them are dependent on deliverables by other business units. What life cycle methodology should the project manager use in this situation? A.A hybrid life cycle including a prioritized product backlog approved by the sponsor B.A predictive life cycle including a schedule in agreement with all business units C.An agile life cycle including a detailed schedule in agreement with all business units D.An iterative life cycle including task durations and a budget approved by the sponsor
Solution: A. A hybrid life cycle including a prioritized product backlog approved by the sponsor A hybrid development approach is a combination of adaptive and predictive approaches. This means that some elements from a predictive approach are used and some from an adaptive approach are used. This development approach is useful when there is uncertainty or risk around the requirements. Considering that the project is complex and will need to go through multiple stages, the team is unable to predict when tasks will occur, or their duration, but the project needs to be completed by a fixed due date, the project manager would best be advised to choose a hybrid approach that would include working with the project sponsor to prioritize the functionalities or deliverables in the backlog. The other answer choices are incorrect. A predictive life cycle is incorrect because it is a development approach in which the project scope, time, and cost are determined in the early phases of the life cycle. A predictive life cycle should be applied to projects with a clearly defined scope, which is not the case here. An agile life cycle is incorrect because it should be applied to projects with unknown scope/timeline, such as proof of concepts (POC) or technology projects. In addition "detailed schedule in agreement with all business units" is not yet possible. An iterative life cycle is a small chuck or interaction of the agile methodology. In addition, as stated in the there is no information on task durations, and the budget cannot be estimated/approved by the sponsor at this point.
56
In order to determine a new hybrid approach for a project, the project manager decides that an assessment of the organizational culture is needed. The project manager should consider a balance between which two elements? A.Exploration and stability B.Speed and traditional models C.Flexibility and predictability D.Disruption and conformity
olution: C. Flexibility and predictability Flexibility and predictability are the most important things in the organization's culture for the project manager to determine the appropriate hybrid approach. When assessing organizational culture to determine a new hybrid approach for a project, the project manager should consider balancing flexibility and predictability. The other answer choices are incorrect. Exploration and stability may be helpful, but it does not directly address the need for balancing flexibility and predictability. Speed and traditional models may be helpful, but it does not directly address the need for balancing flexibility and predictability. Disruption and conformity may be important factors to consider, but they do not directly address the need for balancing flexibility and predictability.
57
After completing the stakeholder analysis, the project manager is in the action planning phase. What should the project manager do with the stakeholders that have no interest or influence in the project? A.Closely monitor these stakeholders B.Highly encourage these stakeholders C.Attentively focus on these stakeholders D.Visibly harness these stakeholders
Solution: A. Closely monitor these stakeholders Stakeholders who have no interest or influence in the project may not be actively involved in the project, but they may still be affected by the project's outcome. It is important to keep these stakeholders informed of the project's progress and address any concerns. By closely monitoring these stakeholders, the project manager can ensure that they are not negatively impacted by the project and that they are aware of the project's progress. The other answer choices are incorrect. Highly encouraging these stakeholders is not necessary because they are not interested in the project, so they are unlikely to be persuaded to become more involved. Attentively focusing on these stakeholders is not necessary because they are not influential, so they do not need to be given a lot of attention. Visibly harnessing these stakeholders is not necessary. These stakeholders are not interested in the project, so they are unlikely to be willing to help the project succeed.
58
A customer requested a change to a functionality that is being delivered in the next iteration. The specialist responsible for this functionality was recently assigned to another project. What should the project manager do first? A.Request a new resource from HR. B.Request a new resource from the project sponsor. C.Negotiate for the resource's availability. D.Tell the customer that the new change is not possible.
Solution: C. Negotiate for the resource's availability The project manager should negotiate for the resource's availability first. The project manager should explain to the project sponsor the impact of the customer's request on the project and the need to have the specialist available to make the change. The project sponsor may be able to negotiate with the other project manager to have the specialist temporarily assigned to the current project. The other answers are incorrect. If the project sponsor is unable to get the specialist's availability, then the project manager can request a new resource from HR. The project manager should not tell the customer that the new change is not possible without first trying to negotiate for the resource's availability or requesting a new resource from HR.
59
A project manager is developing a project management plan to submit to the project sponsor in two weeks. The project sponsor, however, wants to review the early resource estimates before the deadline. What should the project manager do? A.Ask the sponsor to wait until the Work breakdown structure (WBS) is done. B.Share a draft copy of the Budget Estimate Sheet (BES) with the sponsor. C.Re-share the Statement of Work (SOW) with the sponsor. D.Share a draft copy of the Resource Breakdown Structure (RBS) with the sponsor.
Solution: D. Share a draft copy of the Resource Breakdown Structure (RBS) with the sponsor. The RBS is a document that outlines the project's resources, including the types of resources, the quantities of resources, and the costs of resources. The RBS visualizes how resources are allocated across employees and teams at every stage of the project. This information would be more relevant to the sponsor's request than the BES, WBS, and WBS dictionary for reviewing the early resource estimates. The other answer choices are incorrect. WBS Dictionary is a document that provides detailed deliverable, activity, and scheduling information about each component in the work breakdown structure. Work Breakdown Structure (WBS) is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables. Statement of work (SOW) is the all-encompassing scope to be carried out by the project team to accomplish the project objectives.
60
A company outsources the execution of a project with a fixed-price contract to a supplier. During execution, the supplier agrees to deliver additional customer requirements that were not included in the contract. To fulfill the expanded scope, both parties add more resources to keep the project on the planned schedule. Which technique is being applied in this project? A.Fast tracking B.Crashing C.Resource leveling D.Lead and lag
Solution: B. Crashing If the scope increases without increasing the schedule, the crashing technique achieves compression by adding more resources.
61
After 20% of a project was completed, the customer made the decision to change the provider for data center implementation. The new provider project manager requested a meeting with the customer to clarify how the project will be impacted if the requirements are not well gathered. Which are the project areas that could be impacted if the requirements are not well gathered? (Choose 3.) A.Cost B.Quality assurance C.Schedule D.Quality customer service E.Quality planning
Solution: A, C and E. Cost, Schedule and Quality planning Data gathering techniques that can be used but are not limited: Brainstorming Interviews Focus groups Questionnaires and surveys Benchmarking
62
An organization is under a business transformation. The project manager has been assigned to a project related to one of the new business lines. What should the project manager and team do before defining the scope of the project? A.Lead a procurement meeting. B.Create a work breakdown structure (WBS). C.Adapt and tailor existing assets. D.Sign off on the business case.
Solution: C. Adapt and tailor existing assets. The project team will need to tailor existing assets to meet the project’s needs. The team should take advantage of the organization’s existing assets, when appropriate, rather than procuring new ones. The most effective strategy, in general, is to use existing assets that are already in use within the organization. Procuring new assets isn't the best strategy, and building a WBS and signing off come after.
63
While preparing a project's third progress report, the project manager identifies that the project will experience delays due to late material deliveries. The two previous project reports indicated that the project was on track. What should the project manager do next? A.Discuss it with the project team to determine the most appropriate way to respond. B.Add it to the issue log and include it in the project report. C.Contact the procurement manager to expedite delivery of the material. D.Escalate the issue to the project owner and request a schedule change.
Solution: B. Add it to the issue log and include it in the project report PMBoK Sixth Edition in chapter 4 states,: "4.3.3.3 ISSUE LOG Throughout the life cycle of a project, the project manager will normally face problems, gaps, inconsistencies, or conflicts that occur unexpectedly and that require some action so they do not impact the project performance. The issue log is a project document where all the issues are recorded and tracked. Data on issues may include: Issue type, Who raised the issue and when, Description, Priority, Who is assigned to the issue, Target resolution date, Status, and Final solution. The issue log will help the project manager effectively track and manage issues, ensuring that they are investigated and resolved. The issue log is created for the first time as an output of this process, although issues may happen at any time during the project. The issue log is updated as a result of the monitoring and control activities throughout the project's life cycle" The question identifies that there can be delays in the project schedule as planned due to delivery issues. Therefore, the correct procedure for the project manager is to record the issue in the Issue Log. The Distractors are correctly written and are valid distractions
64
The team and product owner are reviewing user stories in the iteration planning meeting. While reviewing stories, it is identified that some of the high-value stories have more associated risks. What should the agile project manager do? A.Recommend that the team include risky stories in early iterations rather than later ones. B.Recommend that the team choose stories with low risk for easy completion to keep team motivation high. C.Work with the product owner to decide on the stories that should go during the iteration. D.Use the Pareto analysis to decide which stories can be completed the fastest.
Solution: A. Recommend that the team include risky stories in early iterations rather than later ones Risk management should be iterative in agile projects. Any risk items or stories that are identified as higher risks should be addressed earlier by adding them in appropriate sprints rather than to wait for the risks to hit the project. The other answer choices are incorrect. Focusing on low risk stories will leave out the high risk stories that should be prioritized; the team, not the product owner, should determine the stories; Pareto analysis is not the right tool to use.
65
What can a project manager do to communicate the formal project announcement and relevant information to stakeholders, and then gain their commitment? A.Create the project charter. B.Conduct a kick-off meeting. C.Develop the communications management plan. D.Prepare and distribute the responsible, accountable, consult, and inform (RACI) matrix.
Solution: C. Developed communications plan. By developing a communications plan, the project manager can ensure that the stakeholders are kept informed of the project's progress and that they have a way to communicate their concerns. This can help to avoid the situation where stakeholders are complaining and declining meetings. The other options are incorrect. Creating the project charter is a good idea, but it is not the most important thing to do in this situation. The project manager needs to address the issue of stakeholder communication first. Conducting a kick-off meeting is a good way to communicate with stakeholders, but it is not enough on its own. The project manager needs to have a plan for ongoing communication with stakeholders. Distributing a RACI matrix is a tool that can be used to clarify the roles and responsibilities of the stakeholders. However, it is not a substitute for a comprehensive communications plan.
66
Since the beginning of a project, the product owner keeps asking during ceremonies about the budget spent for each product iteration. The product owner seems much more interested in the cost rather than the product itself. What should the project manager have done earlier to change the product owner's behavior? A.Worked on different approaches of estimating to give confidence of the cost spent in each product increment B.Worked on a communications management plan with reports of budget spent in each iteration versus planned to avoid these discussions during ceremonies C.Worked with the product owner to clarify their role in an agile project and the scope of the agile ceremonies D.Worked on a fixed-price contract to switch the product owner's attention to value instead of money
Solution: C. Worked with the product owner to clarify their role in an agile project and the scope of the agile ceremonies The Project Manager should take this opportunity to mentor the Product owner on the role of the team[Product Owner being a part of the team] in Agile projects, which appears to have been missed earlier. Hence this is the correct answer. The team is not concerned with the budgetary aspects in Agile projects. Hence the remaining options are incorrect.
67
A project manager with a directive behavioral orientation is leading a virtual team of software developers. The project manager wants to build a high-performing team that is motivated and productive. The team is working on a complex project with a tight deadline. How should the project manager lead this team? A.Build rapport and develop strong relationships with team members. B.Motivate team members with achievement awards. C.Influence team decisions and control the delivery process. D.Implement communication channels to announce task completion.
Solution: D. Implement communication channels to announce task completion. In this situation, the project manager has a directive behavioral orientation and is task-oriented and results-driven. Directive orientation is characterized by a focus on results, a willingness to take charge, and a preference for clear and concise communication. These qualities are essential for a project manager who is responsible for ensuring that a complex project with a tight deadline is completed successfully. The other answer choices are incorrect. Building rapport and relationships is aligned with affiliation orientation, motivating team members is aligned with achievement orientation, and influencing and controlling team members is aligned with power orientation.
68
Which is the process that the project manager performs to prioritize individual project risks for further analysis or action by assessing their probability of occurrence and impact, as well as other characteristics? A.Quantitative Risk Analysis B.Qualitative Risk Analysis C.Identify Risks D.Plan Risk Management
Solution: B. Qualitative Risk Analysis The choices list four processes within Risk Management. They are done in the order of 1) Plan Risk Management, 2) Identify Risks, 3) Qualitative Risk Analysis, 4) Quantitative Risk Analysis. Qualitative Risk Analysis prioritizes identified risks by assessing their probability and impact, and is relatively simple, compared to Quantitative Risk Analysis. Quantitative analysis uses mathematical models to calculate risk responses, and can be time consuming and expensive. Therefore, only the highest priority risks are advanced to quantitative analysis.
69
A supplier reports that they are over capacity, which may delay their delivery. What should the project manager update? A.Risk register B.Stakeholder register C.Issue log D.Project schedule
Solution: A. Risk register PMBoK Sixth Edition Chapter 4 and 11 states: " 11.2.3.1 RISK REGISTER The risk register captures details of identified individual project risks. The results of Perform Qualitative Risk Analysis, Plan Risk Responses, Implement Risk Responses, and Monitor Risks are recorded in the risk register as those processes are conducted throughout the project. The risk register may contain limited or extensive risk information depending on project variables such as size and complexity. On completion of the Identify Risks process, the content of the risk register may include but is not limited to: List of identified risks. Each individual project risk is given a unique identifier in the risk register. Identified risks are described in as much detail as required to ensure unambiguous understanding. A structured risk statement may be used to distinguish risks from their cause(s) and their effect(s). Potential risk owners. Where a potential risk owner has been identified during the Identify Risks process, the risk owner is recorded in the risk register. This will be confirmed during the Perform Qualitative Risk Analysis process. List of potential risk responses. Where a potential risk response has been identified during the Identify Risks process, it is recorded in the risk register. This will be confirmed during the Plan Risk Responses process. Additional data may be recorded for each identified risk, depending on the risk register format specified in the risk management plan. This may include: a short risk title, risk category, current risk status, one or more causes, one or more effects on objectives, risk triggers (events or conditions that indicate that a risk is about to occur), WBS reference of affected activities, and timing information (when was the risk identified, when might the risk occur, when might it no longer be relevant, and what is the deadline for taking action). 4.4.3.1 LESSONS LEARNED REGISTER The lessons learned register can include the category and description of the situation. The lessons learned register may also include the impact, recommendations, and proposed actions associated with the situation. The lessons learned register may record challenges, problems, realized risks and opportunities, or other content as appropriate. The lessons learned register is created as an output of this process early in the project. Thereafter it is used as an input and updated as an output in many processes throughout the project. The persons or teams involved in the work are also involved in capturing the lessons learned. Knowledge can be documented using videos, pictures, audios, or other suitable means that ensure the efficiency of the lessons captured. At the end of a project or phase, the information is transferred to an organizational process asset called a lessons learned repository" Therefore, the correct answer is: "Risk Register", because that is where all the risks related to the project should be recorded. The Distractors are correctly worded and accepted This question and rationale were developed in reference to:
70
A project incurs a 4-week delay. If delayed another 2 weeks or longer, the project will be penalized. In order to be able to deliver on time, the team is offered an appealing financial compensation and 2 days of vacation. What theory is being applied? A.Achievement theory B.Expectancy theory C.Maslow’s theory D.Contingency theory
Solution: B. Expectancy theory Expectancy theory proposes that employees are motivated when they are given assignments they feel confident they can achieve, when they value the compensation you offer and when they believe you will compensate them as promised. The aim of need achievement theory is to explain why certain individuals are more motivated to achieve than others. Maslow's hierarchy of needs is a theory of motivation which states that five categories of human needs dictate an individual's behavior. Those needs are physiological needs, safety needs, love and belonging needs, esteem needs, and self-actualization needs. The contingency theory emphasizes the importance of both the leader's personality and the situation in which that leader operates.
71
What leadership quality must a project manager have? A.Honesty B.Aggressiveness C.Powerful D.Servant leader
Solution: A. Honesty Honesty is a leadership quality that a project manager must possess. Project managers must report the realities of the project and should be transparent. Aggression and power are to forceful, and servant leadership is more for agile practices.
72
A project manager is managing the build of an off-shore data center. In addition, the project manager is the custodian of the assets procured by the project. The project manager is informed by a team member that an asset was lost, and the team member is ready to pay for the missing asset. How should the project manager handle this situation? A.Request your team member to purchase, replace and update the asset register with a new asset tag B.Inform the customer, purchase the new asset, and update the asset and risk register C.Inform management, replace the asset with the help of an insurance claim, and update the asset register D.Inform customer and management immediately, launch an investigation, update the risk register and take action based on outcome
Solution: D. Inform the customer and management immediately, launch an investigation, update the risk register, and take action based on the outcome The correct answer is to inform the customer and management immediately, launch an investigation, update the risk register, and take action based on the outcome. Risk management is everyone's job. Without an investigation, it may be difficult to accurately identify where the failures were, who is responsible, how to respond, and how to prevent this from happening again. Choosing not to inform the customer and management is inappropriate because all risk owners and risk action owners must be briefed on any changes that may affect their responsibilities. Updating the risk register is imperative as this is an incident that may be repeated and may trigger corrective actions to avoid a repeat. There are a lot of unknowns here that rule out the other options. Risk responses should be appropriate for the significance of the risk, cost-effective in meeting the challenge, realistic within the project context, agreed upon by all parties involved, and owned by a responsible person. Projects that are performed under contract may have contract terms that specify how these types of situations should be handled. Requesting that the team member purchase the replacement is incorrect because there should be an investigation before making that decision. Further, the project manager is the custodian of the assets, so the team member may not be considered financially responsible at all. We do not know if there is an insurance policy associated with the asset or the extent of coverage, so that is not necessarily an option.
73
A company, which is conducting a critical bidding process, included a penalty clause in an agreement specifying that the selected supplier must pay a significant liquidated damages penalty in the event of non-performance. Given that this bidding process is extremely attractive to the supplier with a medium risk threshold, how should the supplier's project manager budget for it? A.Increase the quote to mitigate the risk and support the above clause. B.Advise management not to participate in the request for proposals (RFP) since it is a big risk. C.Advise management to purchase insurance coverage to transfer the risk and include it in the budget. D.Record it as a risk in the risk register and review it regularly to avoid the penalty.
Solution: C. Advise management to purchase insurance coverage to transfer the risk and include it in the budget. Transferring a risk involves shifting ownership of a threat to a third party to manage the risk and to bear the impact if the threat occurs. Risk transfer often involves payment of a risk premium to the party taking on the threat. Transfer can be achieved by a range of actions including, but not limited to, the use of insurance, performance bonds, warranties, guarantees, etc. Agreements may be used to transfer ownership and liability for specified risks to another party. Transferring the risk is a preferable strategy for average risk threshold takers. Increasing the quote for this project may lead to not getting this project, especially when the bidding process is attractive for the vendor/supplier with an average risk threshold. Avoiding the risk solely based on penalty charges is incorrect because the project can't be eliminated, especially when it is attractive for the vendor/supplier with an average risk threshold. Recording the penalty charge as a risk in the risk register alone is not going to help.
74
Tools, such as checklists, brainstorming, SWOT analysis, and assumptions analysis are used for which of the following? A.Risk sharing B.Risk identification C.Risk analysis D.Risk enhancement
Solution: B. Risk identification Tools like checklists, brainstorming, SWOT analysis, and assumption analysis, are used to identify risks. The other options are incorrect because they do not typically use the tools listed. Risk sharing is a risk response strategy whereby the project team allocates ownership of an opportunity to a third party who is best able to capture the benefit of that opportunity. Risk analysis involves the activities related to defining the characteristics of a risk and the degree to which it can impact objectives. Risk enhancement is a risk response strategy whereby the project team acts to increase the probability of occurrence or impact of an opportunity.
75
The degree to which risk management is pursued can be the difference between success and failure. In an attempt to avoid project failure, what risks should be assessed and categorized? A.All identified risks B.Only risks identified as high probability of occurrence C.Only risks identified as high potential impact D.All risks identified as high probability of occurrence and high potential impact
Solution: A. All identified risks The correct answer is all identified risks. Risk management allows organizations and teams to increase the predictability of outcomes, both qualitatively and quantitatively. The project manager should assess and categorize all possible risks. Project team members should proactively identify risks throughout the project to avoid or minimize the impacts of threats and trigger or maximize the impacts of opportunities. Both threats and opportunities have a set of possible response strategies that can be planned for implementation should the risk occur. The remaining options are incorrect because failing to assess and categorize all risks leaves the team unprepared and vulnerable.
76
You are managing a project with significant regulatory aspects. A vendor responsible for a core module is undergoing an organization-wide transformation and it is unlikely that the deliverable will be ready on time. Your risk mitigation plan is to use paper forms until the module is implemented but this strategy is likely to slow down the frontline interactions. What kind of risk could you introduce to the project? A.Secondary risk B.Residual risk C.Primary risk D.Compliance risk
Solution: A. Secondary risk A secondary risk can be defined as a risk created by the response to another risk. In other words, the secondary risk is a consequence of dealing with the original risk.
77
Several team members are discussing the project manager's management techniques and the team cannot agree if the focus is on management or leadership. What is the valid option? A.Acts as a manager as it focuses on control, efficiency and effectiveness B.Act as Leader as you join People, Direction and Speed C.Act as a manager as you enter Command and Doing the right things D.None of the above
Solution: D. None of the above
78
An organization conducted an external audit in an Offshore Data Centre (ODC). The audit team noticed that the project manager is using an old version of the risk register template. The auditor raised a Non-Conformity (NC). How could the project manager have avoided this gap? A.It is not the project manager’s mistake since they are using the risk register template provided by their organization B.It is always better to conduct one round of internal audit before allowing an external audit to avoid such a gap C.It is suitable to conduct a risk management plan before preparing the risk register D.It is appropriate to update the risk register with a new template and close the NC
Solution: C. It is suitable to conduct a risk management plan before preparing the risk register The risk management plan may be developed as part of the project kick-off meeting, or a specific planning meeting may be held. Attendees may include the project manager, project team members, key stakeholders, or other team members who are responsible for the risk management process for the project. Others outside the organization may also be invited, as needed, including customers, sellers, and regulators. A skilled facilitator can help participants remain focused on the task, agree on key aspects of the risk approach, identify and overcome sources of bias, and resolve any disagreements that may arise. Additionally, as part of the risk plan, monitoring the risk process should be conducted periodically to ensure that the risk plan and risk register are properly updated. The other options are incorrect. It is not a matter of having the right template to secure updated registers. Project managers should comply with the risk plan to have an updated risk register, and reviewing it periodically is part of the monitoring risk process. Reactive actions do not guarantee to avoid the problem again.
79
After the kickoff meeting for an industrial project, the assigned project manager must lead the team in identifying project risks. As team members are distributed in 6 countries, which risk identification method is best used in this situation? A.Affinity diagram B.Decision tree analysis C.The Delphi technique D.Monte Carlo analysis
Solution: C. The Delphi technique The correct answer is the Delphi technique. The Delphi technique uses facilitated anonymous polling to identify risks. The facilitator gathers the initial poll responses and circulates them without attribution to the entire group. The group members may then revise their contributions based on those of others. The process often generates a consensus after a few iterations. This makes it an appropriate method to use when participants can’t meet in one place, like the team members in 6 different countries. The other answers are incorrect because they are not risk identification techniques, they are risk analysis techniques. Monte Carlo analysis is a quantitative risk analysis technique that computes or iterates the project cost or project schedule many times using input values, selected at random from probability distributions of possible costs or durations, to calculate a distribution of possible total project costs or completion dates. Decision tree analysis is a quantitative risk analysis technique used to determine partial and global probabilities of occurrence An affinity diagram is a qualitative risk analysis technique used to organize specific ideas or factors that contribute to a risk. It helps to sort risks by similarities or generic risk categories.
80
A key stakeholder has submitted several requests for new functions for a product under development. The project manager just completed the scope definition for the product's next version release and communicated the scope statement to all stakeholders. What should the project manager do next? A.Revise the communications management plan to define the number of new feature and function requests that can be submitted. B.Review the acceptance criteria for the product deliverables as defined in the scope statement. C.Meet with stakeholders to emphasize their alignment with product objectives and the goals of the project. D.Review the scope management plan to determine how new functionality requests are to be accommodated.
Solution: D. Review the scope management plan to determine how new functionality requests are to be accommodated The scope management plan documents how the project and product scope will be defined, validated, and controlled. The key benefit of this document is that it provides guidance and direction on how scope will be managed throughout the project. The other choices are incorrect, as they have nothing to do with handling NEW changes to project scope.
81
After monitoring a product’s development after the first three releases, the product owner wants to launch a product even though it lacks some features identified in the minimum viable product (MVP). A stakeholder is not satisfied with this version and feels it needs to meet the previously agreed-upon MVP definition. How should the project manager proceed? A.Review the positives and negatives of releasing the product in its current format and bring this analysis to the project sponsor to decide. B.Work with the stakeholder and the product owner to try and find alignment but support the product owner as they are ultimately responsible for the product. C.Schedule a meeting with all stakeholders and the product owner to review the project’s Pareto Chart. D.Empower the project team to decide how to proceed as the product’s development is the project team’s responsibility.
Solution: B. Work with the stakeholder and the product owner to try and find alignment but support the product owner as they are ultimately responsible for the product "Work with the stakeholders..." (Correct option) On agile projects, teams are empowered to make decisions. It is important to support the team through the process. In Agile, a product owner is responsible for refining and prioritizing the items in the back log. "Review the positives..." This option is not correct because the product owner must be involved to resolve the issue and assist with the decision. "Schedule a meeting..." A Pareto chart is a type of chart that contains both bars and a line graph, where individual values are represented in descending order by bars, and the cumulative total is represented by the line. Reviewing Pareto chart is not going to help us in this scenario "Empower the project team..." The project team would not prioritize the items in the back log.
82
The stakeholders and project team working on an agile project meet with the project manager at the end of an iteration. The project manager learns that the schedule is slipping, although all work was planned to meet the high-level objectives outlined in the project scope. What should the project manager have done to keep the project on track? A.Worked with the team to understand their expectations of using the agile approach. B.Empowered team members to self-organize specific tasks to meet the objectives. C.Prioritized work that could have had an early finish to allow for early benefits realization. D.Selected and sequenced the work in order to meet the high-level objectives.
Solution: B. Empowered team members to self-organize specific tasks to meet the objectives. For agile projects, rather than a project manager prioritizing, selecting, and sequencing work, they should ensure that higher-level objectives are explained and the team members are empowered to self-organize specific tasks as a group to best meet those objectives. This leads to the creation of practical plans with high levels of buy-in from the team members. The other answer choices are incorrect. The project manager does not prioritize work or select and sequence the work. The agile team prioritizes work after the product manager has decided on a Minimum Viable Product (MVP). Working with the team to understand expectations does not address prioritizing work.
83
During the execution phase of a project, a change in the baseline requirements needs to be done. As the project manager, which of the following is necessary to be performed? A.Invoke the project's change management procedure. B.Re-estimate the impacts on cost and schedule. C.Validate among stakeholders. D.Root cause analysis.
Solution: A. Invoke the project's change management procedure "Invoke the..." (Correct option). Any changes to baseline requirements must be done using the change management procedure. "Re-estimating..." this option is not the first option that is followed. "Validation..." this option forms part of the change management procedure. "Root..." This is not a problem therefore there is no need for RCA.
84
A project manager conducts a lessons learned meeting and project team members mention that they are not always aware of the progress occurring during sprints. What can the project manager do to address this concern? A.Mentor the team about how to use the project iteration board. B.Assign a project team member to prepare daily status reports and distribute to all team members. C.Coach the team about how to use the project backlog report. D.Establish a process to address the confusion at the next retrospective session.
Solution: A. Mentor the team about how to use the project iteration board "Mentor the team..." (Correct option). The project iteration board shows the project's status. All project members should know how the iteration board can assist in their tasks. "Assign a project team..."This approach does not assist the individual team members to learn how to find the project status on their own. "Coach the team..."The project backlog report is generally used for stakeholder communication whereas the project iteration board is used by the team. "Establish a process..." Establishing a new process when existing best practice processes exist will confuse the team.
85
Midway through a project, a project manager learns that the project management planning application is failing to record updates to the project. What should the project manager do in this situation? A.Task a project team member to manually update the project plan from now on. B.Inform the project management office (PMO) and have them resolve this issue. C.Update the project plan to allow the project team to focus on the project deliverables. D.Record this issue in the issue register and work with the sponsor to implement a new project management application.
Solution: C. Update the project plan to allow the project team to focus on the project deliverables The project manager should look at resolving any impediments, such as updating the project plan manually, and protecting the team in needing to be engaged in project deliverables. Assigning a team member to update the project plan will take them away from their other project tasks. Implementing a new project management application is a whole separate project. The project manager may inform the PMO and ask for the issue to be resolved but the main priority is to get the plan updated and keep the project team focused.
86
A project manager is assigned to join a several year project mid-way. The project was stopped years ago due to organizational change and a local financial crisis. It has now been restarted. 70% of the budget is already consumed. The performance indices are CPI= 0.42 and SPI= 0.2.During a meeting with stakeholders, the project manager also finds there are major scope changes that could lead to delay. What is the best course of action to take as project manager? A.Change the earned value management tracking technique. B.Change the contract according to new changes. C.Negotiate scope changes with stakeholders and keep it minimized as possible. D.Close this project and request a new project from the project sponsor.
Solution: D. Close this project and request a new project from the project sponsor "Close this project...(Correct option)"Since there have been issues in the past and major scope changes are anticipated, its better to close this project and charter a new project. "Change the earned value management..." Changing the performance measurement technique will not affect the project performance and there is no issue with the adopted performance measurement technique i.e.; Earned Value Management. "Change the contract..." Change the contract is incorrect as the changes are yet to be evaluated and finalized. "Negotiate scope changes..." with stakeholders is incorrect as it will not rectify the issues that have occurred in the past and may lead to stakeholders disengagement.
87
A complex manufacturing project has multiple stakeholders in multiple locations. The project is entering a high-activity phase and the project manager needs to ensure that all stakeholders are kept informed with timely updates. What should the project manager do first? A.Schedule training sessions on effective communications with all stakeholders. B.Determine the most appropriate technology to use to communicate with all stakeholders. C.Schedule regular status reports to be sent to all stakeholders. D.Revise the communications management plan to have a more frequent update schedule.
During a project status meeting, the project manager discovers that stakeholders have different expectations that are not aligned. None of these expectations have been met, which has created tension in the meeting. What should the project manager do to keep things moving on the project? A. Update the risk register to reflect the difference in expectations as a high risk. B.Ask stakeholders to send their expectations by email to ensure that they are included in the project plan. C.Meet with stakeholders privately and update the responsibility matrix. D.Show stakeholders that the current status is aligned with the work breakdown structure (WBS).
88
A team for a project is composed of individuals from different backgrounds, ages, and interests. The team is struggling to work together. How would meeting with the team to develop mutual values and a shared vision enable the project manager to facilitate better teamwork? A.An official team meeting to discuss the importance of teamwork would motivate the team and improve project performance. B.A better understanding of team members' priorities would create a common language that would foster cooperation. C.Understanding each team member's viewpoint would pinpoint areas where education and training was necessary. D.By developing its own understanding of the goals and objectives of the project, the team would gain confidence.
Solution: B. A better understanding of team members' priorities would create a common language that would foster cooperation The question is asking how meeting with the team will enable the project manager to facilitate better teamwork. "A better..." is the correct answer as it speaks to how, with a developing better understanding from where each of the team members is coming from helps to develop a shared vision and enhance teamwork "An official team..." is an approach to improve project performance, however, the question is asking about factors that will enable the project manager to facilitate better teamwork. "Understanding each team..." may be an appropriate course of action to define necessary training, however that does not answer the question. "By developing..." may help the team to gain confidence, however does not answer the question
89
During the planning phase for the expansion of a services company, stakeholders conducted a feasibility study to establish the type of new service the company should provide. During an alternatives analysis, another type of service was determined to be more effective. The change control board (CCB) has approved the change request for the alternative service. What should the project manager do? A.Implement the change as approved. B.Modify the change to reduce the impact on the schedule and budget. C.Request justification from the CCB for the change. D.Conduct a cost-benefit analysis of the alternative service.
Solution: A. Implement the change as approved "Implement the change..." (Correct option). This is the only viable option as in approving the change the CCB board would have taken all possible implications into consideration. The other options are incorrect as only a portion of the question is answered.
90
A project is entering the user acceptance testing phase. After several business end users raised questions and concerns, the project manager discovered that critical business requirements were omitted from the business requirements analysis. What should the project manager do to resolve this issue? A.Interview the team that conducted the analysis to learn why these business requirements were omitted. B.Modify the requirements management plan and communicate to the stakeholders that the project schedule might be impacted. C.Schedule a meeting with the project sponsor to report end users' concerns. D.Meet with the change control board (CCB) to review change requests.
Solution: D. Meet with the change control board (CCB) to review change requests The correct answer is "Meet...". If there are critical business requirements that failed to be included, a change request must be submitted to begin the process of review to see if they need to be. "Interview..." is not valid because, interviewing team that conducted requirements analysis is not going to help in this scenario "Modify..." is not valid because, requirements management plan can't be changed just like that and publish it to the stakeholder without CCB review and approval. "Schedule..." is not valid because, meeting a project sponsor and report the end user's concern is not going to help address the current situation without bringing to the notice of CCB
91
A new project is about to start and is subject to strict time and budget constraints. When reviewing the lessons learned repository, the project manager learns that constant scope creep caused a similar project to fail. What should the project manager do now to avoid project failure? A.Refuse to accept out-of-scope change requests that would increase project duration and budget. B.Manage stakeholder expectations to exclude the possibility of changes in order to meet project goals. C.Adjust the project scope and schedule to stay within constraints and avoid potential changes. D.Establish formal change approval processes to guide teams to deliver essential features first.
Solution: D. Establish formal change approval processes to guide teams to deliver essential features first Having formal change approval processes is the best way to ensure compliance with the project plan and minimize scope creep. The key benefit of this process is that the scope baseline is maintained throughout the project and any changes are formally recognized along with impact on the budget and schedule. The other answer choices are incorrect because they do not minimize the chances of scope creep. Controlling scope is the process of monitoring the status of the project and product scope and managing changes to the scope baseline.
92
During a high-risk project, several risks have been materialized and responses have been implemented, However, the project still appears to be in trouble. The project manager is concerned that the risk management rules are not being carried out as specified. What should the project manager do to identify the weaknesses of the risk management process? A.Transfer the risks. B.Update the risk register. C.Request a risk audit. D.Analyze the risks.
Solution: C. Request a risk audit Periodic risk audits help to identify the strengths and weaknesses in handling risks. This entails identifying any barriers to the effectiveness of the risk management process. Risk audits evaluate whether or not the risk management rules are being carried out as specified and whether or not they are adequate. These audits can help to determine whether or not the process is still relevant and is being used effectively. The other options are incorrect because they do not address the core issue. Transferring the risks may not be appropriate and does not solve any process-based issues or weaknesses. Updating the risk register is not applicable at this stage because it has not yet been determined why the project seems to be in trouble. Risk analysis defines the characteristics of a risk and the degree to which it can impact objectives. In this case, there is no clear indication as to why the project appears to be in trouble, so risk analysis is not an effective way to identify the weaknesses of the risk management process.
93
After completing a project, the team meets to conduct a lessons learned session. During this meeting, the team sees that all deliverables were completed to the defined parameters. However, during the testing, there were a large number of errors identified. What should the project manager have done in this situation? A.Set up a meeting with the testing team to get more information about the testing methods to be used. B.Evaluated when the mitigation strategy will be implemented to prepare for future projects. C.Conducted a Monte Carlo analysis which will determine potential outcomes and responses. D.Planned for these errors in the risk register as something to look for in future projects.
Solution: C. Conducted a Monte Carlo analysis which will determine potential outcomes and responses Variability risks are uncertainties about the characteristics of a planned event to a decision. The number of errors found during testing may be higher or lower than expected, this is a variability risk. They can't be identified and managed because they are non-event-related. The project manager can use a Monte Carlo analysis, with the range of variation as probability distributions, and actions to reduce the impact of this risk on the outcome. Since variability risks cannot be identified and managed, they would not have a mitigation strategy, or be in the risk register. Since the project is completed and the deliverables met the parameters, there is no need to understand the testing methods further.
94
An organization has just has been shortlisted to win a project for implementing three magnetic resonance units in the main hospital for the country. The hospital's CEO asked the project manager for an updated proposal where the implementation time is reduced by 30%. Who should the project manager consult with to reduce the estimates in the most realistic way? A.Hospital radiology team B.Project team C.Project sponsor D.Hospital procurement officer
Solution: A. Hospital radiology team The project manager should consult with the hospital radiology team to obtain their insights and expertise regarding the implementation of the magnetic resonance units. They can provide valuable input on the specific requirements, technical aspects, and potential challenges involved in the implementation process. By involving the radiology team, the project manager can gather realistic information and identify opportunities for reducing the implementation time without compromising the quality or safety of the project. The other answer choices are incorrect. In this scenario, the project team, project sponsor, and hospital procurement officer may not have all the relevant information to reduce the implementation time for the magnetic resonance units.
95
A project manager is leading a team that is developing a new software product. The deadline for the product launch is approaching, but the team is very behind schedule. The project manager has tried to motivate the team and help them catch up, but they have been unwilling and unsuccessful. What should the project manager do first? A.Meet with the project sponsor to discuss and develop a revised project plan. B.Request a project deadline extension and continue motivating the team. C.Use the forcing method to require the team to work overtime to meet the deadline. D.Escalate the issue to the functional manager for additional resources.
Solution: A. Meet with the project sponsor to discuss and develop a revised project plan. The most important thing for the project manager to do is meet with the project sponsor to discuss the situation and develop a revised project plan. The project manager should be transparent with the project sponsor about the team's progress and challenges. The project manager should also work with the project sponsor to develop a revised plan that is realistic and achievable. The other answer choices are incorrect as they are last-resort options. Requesting a project deadline extension, using the forcing method, and escalating the issue to the functional manager should be a last resort. The project manager should work with the project sponsor to develop a revised plan and motivate the team before escalating the issue.
96
A project manager is new to the organization and is assigned to replace the project manager of an active project. What should be one of the first things the project manager does? A.Schedule meetings with the project stakeholders to learn more about the project deliverables. B.Setup meetings with the team members to discuss the project’s status and risks. C.Conduct a Pareto analysis to identify which tasks need to be prioritized. D.Prepare by reviewing the risk register and mitigation strategies.
Solution: B. Setup meetings with the team members to discuss the project’s status and risks. An understanding of agile and it's marriage to risk is important to effectively get an overview from the entire team of the risks a project will face. Project manager should understand the project status and risks first from the team members. This is the right choice scheduling meeting with stake holders is the second step after understanding the project status and risk Conducting pareto analysis is the fourth step after understanding the project status and deliverables Without understanding project status, it is difficult to understand the risk register
97
During a daily standup, a stakeholder unexpectedly joins the meeting and criticizes the performance of one of the team members. After this, the team member is very distracted from their work and their productivity noticeably decreases. What should the team member do in this scenario? A.Schedule a meeting with the stakeholder to discuss the stakeholder’s actions during the standup. B.Email the stakeholder to request that future communications should come through the project manager. C.Meet with the scrum master to discuss what occurred and how it has affected productivity. D.Meet with the project manager and sponsor to request reassignment to a different project.
Solution: C. Meet with the scrum master to discuss what occurred and how it has affected productivity. The scrum master's role is to remove obstacles and impediments from the team. In this case, the stakeholder approaching a team member is interfering with the team. The scrum master should talk with the stakeholder to understand their concerns and ensure they know the correct process for handling disputes with the team. The choices relating to the team member communicating directly with the stakeholder are not likely to be productive, as the question indicates that there already is a conflict between them that needs to be addressed by a third party. Requesting reassignment to a different project does not address the underlying problem.
98
In a scaled agile framework, which responsibilities of a release train engineer can be performed by a project manager? (Choose 3). A.Managing risks B.Coaching on global technical excellence C.Escalating impediments D.Coaching on global continual improvement E.Coaching on team continual improvement
Solution: A, C and D. Managing risks, Escalating impediments and Coaching on global continual improvement. The Release Train Engineer is a Program Level role who facilitates program level processes and execution, drives continuous development, manages risks and escalates impediments The following can be done by Project Manager as well: Managing Risk Escalating impediments Coaching on global continual improvement.
99
A project manager is part of a project that has a scrum team. The team members are unfamiliar with the distinction between risks and issues and prefer to use the concept of impediments. For which of the following would the team be unable to apply the concept of impediments? A.One of the junior members of the team cannot work at full capacity for a week. B.One of the competitors announced the imminent release of a new version of their product. C.The administration of the building announced that for the next couple of weeks there will be maintenance work on the air conditioning system. D.The project manager is on leave and scrum master has to take a lead for distinguishing risk from issues.
Solution: B. One of the competitors announced the imminent release of a new version of their product. The competitor launch does not prohibit the team from doing work and does not impact team velocity. Thus, it would not be considered an impediment.
100
Which agile project parameter is least likely to change during project execution? A.Project vision B.Definition of done C.Product owner D.Product backlog
Solution: A. Project vision The Project Vision describes why the project is initiated, and any change would change all other parameters. The other listed parameters are more likely to change than Project Vision.
101
An agile team finds it difficult to complete a checklist because they have different interpretations of what the project aims to achieve. How can the project manager help them gain a common understanding of the project's overall purpose? A.Review the project vision. B.Review the full list of user stories. C.Review the Agile Manifesto. D.Conduct the first sprint retrospective.
Solution: A. Review the project vision. The Project Vision describes the overall purpose of the project and potentially its key benefits. Project objectives without a vision may describe the desired end result and time frame, but they do not form an underlying meaning for the work. Sharing a common project vision and having the same understanding about tracking the progress towards this vision is one of the key factors in the success of a project and team.
102
Which of the following steps should an Agile project manager of a newly formed virtual team take to help the organization succeed? (Choose 2). A.Provide clear goals, direction, or priorities. B.Help establish cooperation and trust. C.Let the team decide and evolve their roles and responsibilities. D.Neglect "Face time" and regular check-ins with team members.
Solution: B and C. Help establish cooperation and trust and Let the team decide and evolve their roles and responsibilities. In Agile, the team is "self-organized" so the project manager should build trust and let individuals get comfortable taking responsibility in their roles in a virtual setting instead of providing directions, as suggested in answer choice A. Neglecting face time and check-ins will reduce communication and negatively impact the project.
103
A software developer who is working on a critical component has to take emergency leave from the project. Due to time constraints, the project manager cannot hire a new replacement developer for the team. What should the project manager do to manage the situation? A.Move the critical component to the final iteration it can be worked on after the developer returns from leave. B.Request the project sponsor to extend the project until the developer returns and finishes the work. C.Prolong the iteration to allow time for the developer to return and complete the component. D.Ask team members to find a way to complete the missing developer's work in this iteration.
Solution: D. Ask team members to find a way to complete the missing developer's work in this iteration. The best choice is to find a way to complete the absent developer's work as originally scheduled (in this iteration) by relying on other team members. The other choices involve waiting for the developer to return from leave, and while they are possible, nothing in the question states that other team members do not have the skills to fill in and maintain the project schedule as much as possible.
104
A team member informs the project manager during a project meeting that a due task was not completed on time because of a last-minute work crisis. What should the project manager do? A.Check the task dependency, priority and impact of delay on the whole project B.Talk to to the team member privately, ask him/her to work overtime on the task C.Ask other team members to step in and assist in the completion of the task D.Review the task progress with the team and decide the course of action
Solution: D. Review the task progress with the team and decide the course of action The project manager is responsible for timely delivery, if task not completed on time, it can be reviewed and rescheduled after impact analysis on whole project. The team may already have made some progress, or have plans in place to finish the task. The PM should understand the progress and then decide course of action. Other team members may not have the correct skills for the task, and asking them to help may jeopardize other tasks. There is no need to talk to the team member privately. The PM can check the dependency, priority, and impact to the project, after they understand the current progress and plan for the delayed task.
105
During an iteration the team realizes that the project will overrun the budget. This is due to the support resources being involved for longer than planned. Company policy requires immediate notification when there is any change to the budget. What should project manager do to manage the project budget? A.Estimate the additional project cost and plan to propose the new budget to the change review board. B.Reduce the resources and ask the team to manage tasks within the planned cost. C.Discuss with the project team to reduce the use of support resources by the project. D.Accept the cost overrun risk, depending on the contingency amount of the project.
Solution: C. Discuss with the project team to reduce the use of support resources by the project. Resource sharing is one of the key approaches to optimize costs. To manage the project budget, the project manager should discuss with the project team to reduce the use of support resources by the project. The other answer choices are incorrect. These options are more for a predictive approach. A change review board is not common practice in agile; the project is not plan driven so there is no cost constraint.
106
A project advisory team is working remotely from the core project team. There is a constant flow of information between these two teams, and both teams approve project documents. Any delays in approvals will result in additional expense. Which practice would assure the project manager that all of the documents are on hand, updated, and approved properly? A.Let the advisory and core teams develop and maintain their own document categorization and naming systems. B.Require each member of the advisory and project teams to maintain updated records. C.Have the sponsor maintain and approve changes within a single document registry. D.Oversee a single document registry and change control system that both teams use.
Solution: D. Oversee a single document registry and change control system that both teams use. Document control is an important part of project change control. A single document registry will ensure that there is version control and all the documents are accessible to all the stakeholders from a single repository. The project manager should oversee a single document registry and change control system that both teams use. The other answer choices are incorrect. Multiple document registry systems will cause inconsistency, confusion, and delays. It is not the sponsor's role to maintain a document registry.
107
Team members express frustration because their functional manager does not listen to their opinions. They seem reluctant to devote themselves to the remainder of the project. What should the project manager do? A.Demonstrate support for the team by discussing their goals and beliefs. B.Break the remaining work into smaller tasks and divide the tasks among the team. C.Ask the team to prioritize the tasks remaining in the project. D.Discuss the team's concerns with the functional manager.
Solution: A. Demonstrate support for the team by discussing their goals and beliefs. The primary goal of a project manager in relation to the project team is to ensure that the team has the time and resources to do their job and to remove any barriers they may encounter. By standing up for the team's beliefs the project manager is demonstrating their support for the team. Breaking the remaining work into smaller task, dividing the tasks and asking the team to prioritize the task will not solve the frustration the team members are facing. Discussing with team's concerns with the functional manager may not help to resolve the motivation of the team members to focus and complete the remainder of the project.
108
In which stage of Tuckman's stages of team development do the team members begin to resolve conflicts effectively? A.Forming B.Storming C.Norming D.Performing
Solution: C. Norming Following the conflict of the storming phase, the team learns to work more effectively in the norming phase, including resolving conflicts. Norming is the correct choice. Norming is the stage at which the project team starts to function as a collective body. At this point, project team members know their places on the team and how they relate to and interface with all the other members. They are starting to work together. There might be some challenges as work progresses, but these issues are resolved quickly, and the project team moves into action. Effective team conflict resolution skills are not present in the forming and storming stages. They are well developed in the performing stage, but the question asks at which stage they begin to arise. The other options are incorrect. The forming stage is when the project team first comes together. Members get to know each other’s names, position on the project team, skill sets, and other pertinent background information. This might occur in the kickoff meeting. During the storming stage, project team members jockey for positions on the team. This phase is where people’s personalities, strengths, and weaknesses start to come out. There might be some conflict or struggle as people figure out how to work together. Storming might go on for some time or pass relatively quickly. At the performing stage, the project team becomes operationally efficient. This is the mature project team stage. Project teams that have been together for a while are able to develop synergy. By working together, project team members accomplish more and produce a high-quality product.
109
A project manager is assigned to a new multinational project. This will be the project manager's first time working with team members from different countries. What should the project manager do to prepare themselves for the project? A.Attend cultural sensitivity training to understand and respect cultural differences. B.Brush up on language skills if necessary to facilitate effective communication. C.Conduct team-building exercises to foster collaboration and trust among team members. D.Develop an awareness of local customs with the understanding that culture is learned.
Solution: A. Attend cultural sensitivity training to understand and respect cultural differences. When working with team members from different countries, it's crucial for a project manager to be culturally sensitive and aware. Cultural sensitivity training can help project managers understand and navigate the nuances of working with a multicultural team, promoting effective communication, collaboration, and respect for cultural differences. The other options are incorrect. Brushing up on language skills is incorrect because it may not be feasible or unilaterally effective. Effective communication involves more than just language; it also encompasses cultural nuances, customs, and non-verbal communication. Even if the project manager speaks the languages of all of their team members, it is still important to be aware of cultural differences in communication. In this scenario, the project manager is seeking to prepare themselves to manage a multinational project, which they have never done. Conducting team-building exercises should come after cultural sensitivity training, as it's important to first establish an understanding of cultural differences and build a foundation of respect and effective communication. Developing an awareness of local customs is always a good idea, but the project manager will be working with team members from different countries, learning local customs is not the most effective way for the project manager to understand and respect the different cultural backgrounds of their team members. Cultural sensitivity training offers a more comprehensive and structured approach to understanding and respecting different cultural backgrounds.
110
A project's statement of work (SOW) requires that the project be delivered in nine months. The project manager believes that the timeline is not realistic. What should the project manager do? A.Involve the change control board (CCB) in the Perform Integrated Change Control process B.Submit a written request to the project sponsor for additional resources and budget C.Meet with subject matter experts (SMEs) and the project sponsor to set expectations D.Negotiate a new timeline with the project sponsor
Solution: C. Meet with subject matter experts (SMEs) and the project sponsor to set expectations If a project timeline is not realistic, then the project manager needs to provide the proof to the sponsor so that a realistic expectation can be set. The SMEs can provide that information and allow the sponsor to decide on a course of action. The Change Control Board evaluates and approves additions or deletions of scope. A written request for additional resources and negotiating a new timeline could be an approach, but not the first thing one would do.
111
An organization is redesigning and relaunching a key product. The stakeholders are all company executives and want to ensure that the product launch will be a success. What should the project manager do to ensure project success? A.Implement a detailed communication management plan so that stakeholders are kept informed of the project status. B.Communicate the critical nature of this project to the team and escalate any issues to the sponsor. C.Ensure that all of the stakeholders attend the daily standups so that they can adjust the project as needed. D.Work to identify and align performance indicators with the deliverable.
Solution: D. Work to identify and align performance indicators with the deliverable. In order to measure the successful delivery and completion of any initiative, it is critical to determine the performance indicators beforehand. The Project Manager can ensure project success by identifying & aligning the performance indicators with the deliverable. Implementing a detailed communications management plan is incorrect as that is not the issue. Also, the stakeholder continues to receive communications. A project manager would not escalate to the project sponsor. All of the stakeholders do not attend the daily standups.
112
A project is in the execution phase when the project manager needs to assign new resources to the existing project team. What should the project manager do to ensure the team works effectively and meets project requirements on time? A.Create accessible library services. B.Conduct a brainstorming session. C.Integrate skills development activities. D.Monitor project team cohesiveness.
Solution: C. Integrate skills development activities. When a project manager needs to assign new resources to an existing project team, it is important to integrate skills development activities into the project execution phase. This will help to ensure that all team members have the skills and knowledge they need to do their jobs effectively and meet project requirements on time. A highly skilled and capable team is more likely to work effectively and meet project requirements on time. Skills development activities ensure that team members are equipped to handle their roles and responsibilities competently. The other options are incorrect because they are not the most immediate actions to ensure the team's effectiveness during the execution phase of the project. Creating accessible library services is incorrect because it does not directly address the team's skills and capabilities and does not ensure effectiveness in the execution phase. Conducting brainstorming sessions is incorrect because they are not directly related to skills development or ensuring the team's effectiveness. Monitoring team cohesiveness is important for assessing team dynamics and collaboration, but it is not a proactive way to ensure the team works effectively and meets project requirements on time. The project manager should focus on helping the new resources integrate into the team and develop the skills they need.
113
During project execution, the team finds that changes must be made to a component sourced from an outside supplier. The component is being used in the project. What should the project manager do? A.Meet with the component supplier to discuss the product warranty. B.Review the contract terms and the Procurement Management Plan. C.List the potential risks that would result from the change. D.Process a change request to modify the project management plan.
Solution: B. Review the contract terms and the Procurement Management Plan. The procurement management plan describes how a project team will acquire goods and services from outside of the performing organization. The contract's terms and conditions will specify how changes will be handled. Thus, the contract and Procurement Management Plan will define how to proceed, and should be reviewed first. The other answer choices are incorrect because the contract terms must be followed and therefore must come first.
114
During project initiation, the project manager learns that a key stakeholder will leave the project for a month to consult on another strategic project. What should the project manager do first? A.Update the issue log and notify the other stakeholders. B.Ask the functional manager to provide a replacement while the stakeholder is unavailable. C.Interview the stakeholder to gather relevant information and expert judgment. D.Update the risk management plan to include the impact of the stakeholder's absence.
Solution: A. Update the issue log and notify the other stakeholders. The FIRST thing the PM needs to do is to capture this as an issue and communicate this to the other stakeholders. Until then, no action can or should be taken. This question and rationale were developed in reference to:
115
During a status review meeting, it was determined that the product will not meet project scope requirements in a particular scenario. What should the project manager do? A.Perform risk analysis and update project scope. B.Initiate integrated change control process. C.Review the baselines to determine the critical path. D.Inform customer and negotiate an extended deadline.
Solution: B. Initiate integrated change control process. The product not meeting project scope is a "Risk" that needs to be managed. This is managed through Integrated Change Control Process. Project scope may change to include this particular scenario after the CCP is initiated. There is no baseline review nor renegotiation with the customer until after the CCP is initiated.
116
A project manager is managing an agile project where the team is regularly missing user story due dates. What should the project manager do to resolve this situation? A.Work with the sponsor to move out the deliverable hand over date. B.Review the time allotted to iterations and sprints, adjusting them as needed. C.Meet with the project team to identify if further agile methodologies training is necessary. D.Implement a reward program for the project team to encourage completing stories on the due dates.
Solution: C. Meet with the project team to identify if further agile methodologies training is necessary. It is important for the project manager to meet with the team and analyze the issue before proceeding. This will help identify gaps in training to ensure user story due dates are met. Then, the project manager and team members can review the time allotted to iterations and sprints, adjusting them as needed. Working with the sponsor to push delivery dates will be unnecessary when the issue is resolved and a reward system may not work for a team with differing preferences.
117
A project manager is developing the schedule for a new software development project. The project network diagram shows two separate paths: Path A: Tasks 1-2-3-4 (all with a duration of 5 days each) Path B: Tasks 5-6-7 (durations of 3, 7, and 2 days respectively) There are no external dependencies between these paths. What is the critical path for this project? A.1-2-3-4 B.5-6-7 C.1-2-3-4-5-6-7 D.1-2-6-7
Solution: A. 1-2-3-4 The critical path refers to the longest sequence of dependent tasks that must be completed on time for the entire project to finish on schedule. Since there are no external dependencies between Path A and Path B, analyze their individual durations. Path A: Tasks 1-2-3-4 (all with a duration of 5 days each) has a total duration of 20 days (5 days/task * 4 tasks = 20). Path B: Tasks 5-6-7 (durations of 3, 7, and 2 days respectively) has a total duration of 12 days (3 days + 7 days + 2 days = 12). Because Path A has a longer total duration (20 days) compared to Path B (12 days), it represents the critical path for this project. The other answer choices are incorrect. The combination of both paths is not necessary since the paths are independent, thus there's no dependency between tasks 1-2-3-4 and 5-6-7, nor tasks 1-2 and 6-7.
118
A project management office (PMO) normally runs projects using the waterfall approach. A project currently in development is impacted by local regulations which are being updated regularly. The project team feels that implementing agile techniques would benefit the project due to the constantly changing regulations. What should the project manager do in this scenario? A.Leverage budget reserves to add vendors familiar with the regulations to the project team. B.Conduct an analysis of how incorporating agile methodologies will impact the project. C.Present this request to the PMO and the project sponsor. D.Implement the request and train the project team on agile methodologies.
Solution: B. Conduct an analysis of how incorporating agile methodologies will impact the project. The project should first conduct an analysis of how incorporating agile methodologies will impact the project requirement before making other changes to the approach. Using budget reserves to add vendors is not the correct action for this scenario. The Project Manager should do the due diligence on why the project should be changed to agile before presenting the request to the PMO and project sponsor. The Project Manager shouldn't be implementing the request and training the project team on agile methodologies without first getting approval from the stakeholder.
119
A project manager in a predictive environment has recently completed agile training and is starting to manage projects in an agile fashion. The organization is new to agile and not everyone understands the principles. How should the project manager gain support going forward? A.Hold a session with the stakeholders explaining the business value of prioritization, mindset, accountability, and improved quality. B.Conduct a cost benefit analysis for the new project comparing predictive and agile approaches and present it to the stakeholders. C.Invite the stakeholders to a backlog grooming session so that they understand the scope of work and the development approach. D.Send the stakeholders video links explaining agile approaches as well as supporting case studies from the industry.
Solution: A. Hold a session with the stakeholders explaining the business value of prioritization, mindset, accountability, and improved quality. The project manager is responsible for educating and engaging the stakeholders. The project manager should hold a session with the stakeholders explaining the business value of prioritization, agile mindset, accountability, and improved quality. The other answer choices are incorrect. Conducting a cost benefit analysis may not show results in favor of the agile approach; inviting stakeholders to instill understanding of the benefits of agile is not the objective of a backlog grooming session; holding a session shows more dedication to the stakeholders as opposed to sending a video lesson link.
120
A project manager has been assigned to a new project. During the initial review of the project charter, the project manager reaches out to the project sponsor to discuss important information that is missing in the document. What piece of information is appropriate for the project manager to request? A.Measurable objectives of critical success factors B.Detailed description and requirements of the final deliverable C.Work breakdown structure (WBS) D.Performance measurement baseline
Solution: A. Measurable objectives of critical success factors The project sponsor is generally responsible for the development of the business case for the project. That person would be the logical source of the objectives for project success. Detailed deliverable requirements, WBS, and performance management baseline are all lower level documents that the project manager should develop based on the criteria provided by the sponsor.
121
What methodology uses new approaches to implement solutions to problems that are encountered daily? A.Ideation 2.0 B.Scrum C.Kanban D.Hybrid
Solution: A. Ideation 2.0 Ideation 2.0 is about using new approaches to ideate solutions to the problems you encounter in your daily routine, helping you to design collaboratively while keeping in mind the necessary outputs to inform the initial prototype. The other answer choices are incorrect because they are not designed to address problems that are encountered on a daily basis.
122
A project manager is part of a project management strategy focus group that is brainstorming the ways projects will be used to add business value to the organization in the upcoming quarter. Which statement(s) describes broadly how organizations use projects to add business value? A.Projects are used to develop new products, processes, or services. B.Projects are used to modify existing products, processes, or services. C.Projects are used to deliver day-to-day activities, processes, or services. D.Projects are used to develop and modify products, processes, or services.
Solution: D. Projects are used to develop and modify products, processes, or services. Business value is added by projects to develop new products or modify existing products, processes, or services. Projects should deliver unique features, and do not deliver day-to-day activities.
123
A project team is brainstorming the best project management methodology to recommend to senior management for adoption. The project team's idea is characterized by frequent requirement changes, incremental and iterative changes, customer focus, and defined stages with specific documents produced to meet industry regulatory standards. Which project management methodology is preferred in this case? A.Agile B.Hybrid C.Predictive D.Waterfall
Solution: B. Hybrid Hybrid is correct as the team needs to adopt the hybrid approach as their projects require agile benefits such as being more customer centric, responding faster to change as well as predictive benefits of clear stages and documents. Hence a blend is recommended in this instance. Agile is incorrect as the defined stages with specific documents are required in order to meet industry regulatory standards. Predictive is incorrect as the project requires frequent requirement changes, incremental and iterative changes whereas predictive methodology is applied when when the scope of work and requirements for the project are clear and justify the detailed upfront planning. Waterfall is incorrect as the waterfall project management is a sequential, linear process of project management whereas this project requires frequent requirement changes, incremental and iterative changes
124
A megaproject had reached 10% completion when there was a sudden change of company ownership. After being put on hold for a few years, the project is now under study to resume. Who is responsible for approving the updated budget, assigning key resources and relaunching the project? A.Project sponsor B.Project management office (PMO) director C.Chief executive officer (CEO) D.Steering committee
Solution: D. Steering committee Steering committee is the correct answer. The project steering committee has authority for decisions at the organizational level, including assigning the project sponsor and approving starting or stopping a project. Other options are not correct per the explanation provided about the steering committee.
125
A local government provides subsidies for healthcare activities. An organization plans to leverage this subsidy for a project to provide health testing services for at-risk populations. After the project has started, the government announces that this testing service might not qualify for the subsidy. What should the project manager do? A.Escalate the project risk to a higher level. B.Meet with the project sponsor to redefine project benefits. C.Inform the stakeholders of the need to develop a contingency plan. D.Submit a change request to the change control board (CCB).
Solution: A. Escalate the project risk to a higher level. If there are potential conflicts between strategic goals and the portfolio of work, then the risk is escalated to the proper level of management. The project benefits haven't changed, there is no indication yet that a contingency plan is needed, and there would be nothing to substantiate a change request.
126
A project manager is a part of a project that is using the Scrum framework. The project manager needs to monitor the impediments log and facilitate the resolution of impediments raised by the team. What is the correct order of the five steps used to manage the impediments log? A.Prioritize, record, publish, communicate and address B.Record, publish, communicate, prioritize and address C.Record, prioritize, publish, address and communicate D.Prioritize, record, publish, address and communicate
Solution: C. Record, prioritize, publish, address and communicate The correct order is record, prioritize, publish, address, and communicate. Process Description Record The Daily Standup Meeting is the best time to document impediments in the Impediments Log as each team member reveals them. After the brief meeting, the Scrum Master will gather additional information so that the impediments can be prioritized. Prioritize Impediments should be prioritized based on their levels of importance and in relation to those on that are already on the log. Publish The Impediments Log should be made visible to everyone and posted for all to view. Address The Scrum Master should address the highest priority impediments from the log and ensure that it is removed so that the team can continue to reach the Sprint’s objective. Communicate When the impediment is removed, this information should be communicated to the involved parties and the Impediments Log is updated.
127
A project is in progress and the project plan follows waterfall but deliverables are incrementally given to the customer in an agile manner. The project team is comfortable with the hybrid approach and has successfully made important decisions for previous projects. How should the project manager proceed? A.Take control of the decision-making process. B.Provide the team with a detailed process for making decisions. C.Support the team’s choices and project decisions. D.Train the project team on decision-making techniques.
Solution: C. Support the team’s choices and project decisions. The best way for the project manager to proceed is to support the project team’s choices and allow them to assume control of project decisions. The project team has successfully made important decisions for previous projects, and they are comfortable with the hybrid approach. They are also familiar with the project plan, so they are well-positioned to make decisions that are aligned with the project's goals and objectives. The other answer choices are incorrect. The project manager taking control of the decision-making process would be a top-down approach that could stifle innovation and creativity. Providing the team with a detailed process would be rigid and could prevent the team from adapting to changes in the project's scope or requirements. Training the team members on decision-making would not be enough to ensure that the project team is successful.
128
An organization is launching a new product that is critical to the company's success. The stakeholders have identified three key factors for success: market adaptation, rapid response to market offerings, and agility. What should the project manager do to ensure the project's success? A.Work closely with the marketing team to promote the product and adapt to market changes. B.Ensure that the project has sufficient budget and resources to address any challenges. C.Be actively involved in the project by monitoring progress, making necessary changes, and capturing data. D.Invite the stakeholders to attend all standups to ensure they are actively involved in the project’s success.
Solution: A. Work closely with the marketing team to promote the product and adapt to market changes. The best answer is Work closely with the marketing team to promote the product and adapt to market changes. This is because the stakeholders have identified market adaptation as one of the key factors for success. The project manager can work with the marketing team to develop a marketing plan that will reach the target market and adapt the plan as needed to respond to changes in the market. The other answer choices are also important, but they are not as critical as market adaptation. Ensure that the project has sufficient budget and resources to address any challenges is important, but the project manager can still work with the marketing team to develop a marketing plan even if the budget is limited. Be actively involved in the project by monitoring progress, making necessary changes, and capturing data is also important, but the project manager can still do this even if they are not invited to all standups. Invite the stakeholders to attend all standups to ensure they are actively involved in the project’s success is important, but it is not as important as market adaptation.
129
The project manager's company won a digital transformation project request for proposal (RFP) with clear scope, time and cost. As part of the RFP clause, the project manager's company also provided the number of resources required to complete the project. This is a very high investment project, and the customer wants to monitor the progress regularly. Since it is a fixed price project, what approach should the project manager use? A.Use a predictive approach and send the daily status report to the customer. B.Use an Agile approach and showcase each successful completion of the story. C.Use a hybrid approach and showcase each successful completion of each module. D.Use a predictive approach and showcase each successful completion of each module.
Solution: C. Use a hybrid approach and showcase each successful completion of each module. Waterfall Plan – Agile Execution many organizations seek the security of waterfall planning and a more deliberate approach to project initiation while also seeking the agility and opportunities for incremental and rapid value realization that exist with agile execution. These organizations recognize that there is value in planning, but that the plans themselves are less valuable and, in most projects, will change. They therefore embrace change by executing their planned projects using agile tactics. This is a fixed time and cost project with a clear scope. The PM needs to use the hybrid approach to provide the customer with details of completion ofeach module The customer wants to monitor the progress regularly NOT receive daily status reports nor wants to analyze the completion of each successful story
130
As a predictive project enters the execution phase, a functional manager discovers that one of the materials to be used in the product will have a detrimental effect on the environment and urges the project manager to switch to a more environmentally friendly material. What should the project manager's initial response be? A.Develop a proof of concept plan to assess the feasibility and impact of the change and present it to the project sponsor. B.Immediately authorize the change in materials and initiate the transition to an environmentally friendly material. C.Inform the functional manager that material changes are not permitted during the execution phase of the project. D. Instruct the functional manager to submit a formal change request through the established change management process.
Solution: A. Develop a proof of concept plan to assess the feasibility and impact of the change and present it to the project sponsor. Predictive projects typically have a fixed scope, schedule, and budget. Changing any of these elements can have a significant impact on the project. Predictive projects may use proof-of-concept developments to explore options. A proof of concept is a small-scale experiment that can be used to test the feasibility of a proposed change. It ensures that any alterations to the project align with its objectives, scope, and timeline. Presenting the plan to the project sponsor for approval maintains proper project governance and change control processes. The other options are not suitable responses. Immediately authorizing the change without evaluating it can lead to unforeseen issues and could disrupt the project's ongoing execution. Telling the functional manager that changes are not permitted during the execution phase is overly restrictive and does not align with effective project management. The project manager should be willing to work with the functional manager to find a solution that meets the needs of the project and the environment. Change requests should be accompanied by an evaluation of any new risks that are introduced due to the addition to or change in scope. The project manager should work with the change control board and the change requestor to guide change requests through the change control process.
131
After comparing actual results to the performance measurement baseline, the project manager discovers that the project's work and cost performance measures are better than expected. The project manager doubts that these positive variances can continue until the end of the project. What should the project manager do? A.Conduct performance reviews with the team members. B.Update the risk register. C.Notify the stakeholders. D.Review the project management plan.
Solution: B. Update the risk register. The first action to take is to update the risk register. The project manager is perceiving a risk that project performance may deteriorate in the future, and will record it in the register, potentially with a response plan. There is no indication that team member performance reviews are warranted, nor that project processes need to be reviewed in the management plan. The stakeholders may or may not need to be notified, but even if they are, the risk register would be updated first.
132
A key project needs to be completed on time and exceed all established quality levels. Throughout the project, the project manager takes coffee breaks with the team and asks if they have ideas on how to improve their way of working. The project manager's approach is in line with which theory? A.Theory X B.Theory Q C.Theory Y D.Theory T
Solution: C. Theory Y Theory Y is the correct answer. Theory Y assumes that the team members want to contribute and reinforces team motivation by seeking input and assistance to obtain the best results. Theory X believe that the team members dislike their work and have little motivation, and an authoritarian style of management should be implemented. Theory Q and Theory T are distractors. There is no Theory Q or T.
133
A customer identifies performance issues on a newly implemented product. Why should the project manager estimate the cost of quality (COQ) for this project? A.To find the optimal cost to prevent failures in future iterations of this product. B.To assess the conformance and non-conformance cost during the life of this product. C.To assess the quality of the product to minimize future appraisal costs. D.To minimize rework and scrap associated with failure costs during project execution.
Solution: B. To assess the conformance and non-conformance cost during the life of this product. Cost of Quality (COQ) helps identify and quantify the financial impact of quality-related activities throughout the project lifecycle. In this scenario, estimating COQ provides valuable insights to identify savings. The other answer choices are incorrect. While COQ might inform future prevention strategies, the primary focus is analyzing costs associated with the current product. COQ analysis helps understand both prevention and appraisal costs, but cost minimization isn't the sole objective. It's about finding the optimal balance. COQ analysis considers all quality costs throughout the product lifecycle, not just project execution.
134
A project sponsor assigns a project manager to a new, critical project. This project has tight budget and time constraints. What should the project manager do first? A.Meet with functional managers to schedule team resources. B.Meet with stakeholders to obtain their buy-in and support. C.Meet with the project sponsor to understand the project's purpose and high level requirements. D.Update the requirements management plan to reflect the budget and time constraints.
Solution: C. Meet with the project sponsor to understand the project's purpose and high level requirements. The first steps in initiating a project are to understand the goal, the requirements and to create a charter. So meeting the project sponsor to understand the project's purpose and high level requirements is the first step. If the requirements and goal of the project are not yet known, the skill set of resources is not known, so it is too early to meet with functional managers or with stakeholders. The requirements documentation and charter must be completed before a requirements management plan can be drafted.
135
A project manager is committed to the success of a multinational project with tight deadlines. A new team member is continually late or misses status meetings. In a one-on-one with the project manager, the team member expresses the belief that working on deliverables is more important than attending status meetings. What should the project manager do? A.Reassign the team member to another project with more flexible deadlines. B.Document this behavior in the team member's personnel file. C.Encourage this team member's attendance, but be flexible if critical work is not affected. D.Meet with the team to ensure they understand that attendance at status meetings is required.
Solution: D. Meet with the team to ensure they understand that attendance at status meetings is required. Meet with the Team is the correct answer. It speaks to the setting of expectations and communication with the project team members. By being open and transparent, the PM ensures the message has been clarified with the team members. Reassign and document options may be steps the PM may take if the behavior continues after the expectations have been clarified with the team Encourage contradicts what the PM is observing and needing to communicate to the team.
136
A manufacturing project is in the implementation phase. During a status meeting, a team member tells the project manager that a solution has been found for a persistent failure on equipment used in the implementation; however, this solution is temporary, and the equipment could fail again in the future. Which document should the project manager update? A.Issue log B.Risk management plan C.Assumption log D.Stakeholder register
Solution: A. Issue log The issue log should be updated. This document helps the project manager track and manage issues throughout the project lifecycle, ensuring that they are investigated and resolved. In this case, the project has new information on an issue that should be captured on the issue log. The risk management plan is not correct, as it specifies how a project manages risk, and does not list identified risks or their response plans. The assumption log contains details about the assumptions and limitations that could affect the project. The stakeholder register records identified stakeholders and their expectations from the project. Nothing in the question indicates that changes to these documents is necessary.
137
A project manager is struggling to keep a technical system implementation on track after the loss of a key team member two months ago. The project has missed multiple milestones and is now in critical status. What should the project manager have done to prevent this situation? A.Replaced the key member with a more experienced one. B.Reassigned the key member's tasks to other team members. C.Motivated the team to meet all milestones and deadlines. D.Identified the risks early and developed a mitigation plan.
Solution: D. Identified the risks early and developed a mitigation plan. The project manager should have created a mitigation plan and identified risks like the loss of key team members. The other answer choices are incorrect. Replacing the key member may not be possible, or it may be time-consuming to find a replacement. Reassigning the key member's tasks to other team members may not be feasible, as it can add workload and stress to team members, potentially impacting overall productivity and efficiency. Motivating the team may not be enough to overcome the loss of a key team member and ensure milestones are met.
138
An organization has implemented agile for its recent projects, but all of the recent agile projects have missed their delivery milestones. The sponsors for the agile projects are regularly adding new requests to the projects. A project manager is given a new agile project and finds that it has a vague project objective and no clear definition of done (DoD). What should the project manager do? A.Set up a meeting with the project stakeholders to ensure the communication management plan is clearly defined. B.Ensure the sponsor allows the project team to include the most technical resources to better ensure project success. C.Work closely with the project team to develop and clearly define the project vision. D.Work with the project stakeholders to ensure that the project charter and deliverables are clearly defined.
Solution: C. Work closely with the project team to develop and clearly define the project vision. The project manager should work closely with the project team to develop and clearly define the project vision. This will help to ensure that everyone on the team understands and agrees to the project goals. The project manager should also work with the project team to define a DoD for each backlog item. This will help to ensure that everyone on the team is working towards the same goal and that the project delivers the expected results. The other answer choices are not as relevant or effective. Setting up a meeting with the project stakeholders to ensure the communication management plan is clearly defined is important but will not address the root cause of the problem, which is the vague project objective and no clear DoD. Ensuring the sponsor allows the project team to include the most technical resources to better ensure project success is important but it is not a guarantee of success. The project manager needs to make sure that the team has a clear understanding of the project goals and requirements. Working with the project stakeholders to ensure that the project charter and deliverables are clearly defined is not enough to ensure success. The project manager also needs to make sure that the team has a clear understanding of the project vision and DoD.
139
A project manager typically conducts retrospective sessions at the end of a project. However, the sponsor believes that retrospectives are a waste of time and budget, and instructs the project manager to significantly reduce or eliminate retrospectives in future projects. What potential outcome could arise from the sponsor's directive? A.The focus shifts towards discussing issues instead of identifying ways to improve for future projects. B.The opportunity to improve team processes based on specific project observations is missed. C.The emphasis is placed on stakeholder observations about project performance. D.The time management plan is not properly updated.
Solution: A. The focus shifts towards discussing issues instead of identifying ways to improve for future projects. In this scenario, the most likely outcome of the sponsor's directive is that the focus shifts toward discussing issues instead of identifying ways to improve future projects. Removing or reducing retrospectives can hinder the project team's ability to learn, adapt, and continuously improve its processes. The other answer choices are incorrect. One suggests that the removal or significant shortening of retrospectives would improve team processes based on specific project observations. reality, retrospectives are intended to reflect on the project as a whole and identify areas for improvement, not just based on specific project observations. While stakeholder observations are valuable, retrospectives primarily focus on internal team reflection and improvement. The time management plan itself is not directly dependent on retrospectives. Failing to update the time management plan would be a separate issue that should be addressed through effective project management practices, regardless of the presence or absence of retrospectives.
140
A project manager receives an email from a customer detailing reservations about the project deliverables. How should the project manager address the customer’s reservations? A.Meet with the customer to discuss the project scope. B.Note the reservations in the risk register and prepare a mitigation plan. C.Schedule additional time during the deliverable hand over to discuss the customer’s reservations. D.Set up a meeting with the product owner and the customer to discuss the criteria for an acceptable deliverable.
Solution: D. Set up a meeting with the product owner and the customer to discuss the criteria for an acceptable deliverable. To align the customer expectations with the upcoming deliveries the product owner should work with the customer to describe functional behavior as acceptance criteria (definition of Done).
141
A project manager secures project approval with a constrained budget due to fiscal limitations. The sponsor emphasizes no additional funds are available during the current fiscal year. The product owner is concerned that the tight budget will impact the project. What should the project manager prioritize? A.Monitoring the budget throughout the project and demonstrating the value of the project to the company. B.Meeting with the sponsor to express the need for a potential budget increase or the project will be delayed. C.Removing secondary deliverables from the project plan and monitoring the budget after each iteration. D.Requesting the sponsor to allocate funds from the next fiscal year to supplement the current budget.
Solution: A. Monitoring the budget throughout the project and demonstrating the value of the project to the company. Given the limited budget and unavailable additional funds, the primary focus for the project manager should be proactive monitoring, budget tracking, and communicating the value of the project. The other answer choices are incorrect. Expressing concerns about a budget increase is not the initial priority given the sponsor's clear statement about the budget. Removing deliverables might impact the project's scope and functionality, potentially compromising its success. Requesting funds from the next fiscal year contradicts the sponsor's statement and isn't a viable solution at this stage. It's essential to work within the approved budget and explore alternative solutions within the current fiscal year.
142
An expert resource avoids assignments that include working with a foreign contractor. How should the project manager resolve the situation? A.Question the expert privately about their reluctance or biases and insist on an inclusive attitude. B.Issue a disciplinary warning to the expert and advise their functional manager to send them to diversity training. C.Prevent delays and conflicts by hiring a consultant that the expert is willing to work with. D.Reprimand the expert about their discriminatory behavior during a team meeting to set the right example.
Solution: A. Question the expert privately about their reluctance or biases and insist on an inclusive attitude The project manager should understand the reason or root cause on why the expert resource is avoiding assignment before doing any disciplinary warning or other action to replace the expert resource.
143
A project manager is concerned that team members spend too much time assisting operations and maintenance staff with a recently completed and delivered project component. The project manager has referred to the organizational process assets document to validate that the component was signed off and ownership was transferred. To which additional documents should the project manager refer? A.Procurement statement of work (SOW) and work performance report B.Requirements management plan and change management plan C.Procurement management plan and project charter D.Final report and project document updates
Solution: D. Final report and project document updates When closing the project, the project manager reviews the project management plan to ensure that all project work is completed and that the project has met its objectives. The project documents are updated accordingly. The other documents - SOW, Work Performance Report, Requirements Management Plan, Change Management Plan, Procurement Management Plan, Project Charter - are all deliverables earlier on the project and not during project closure.
144
A project team implements a change that was approved by the change control board (CCB). The change was intended to minimize a risk but it had the opposite effect. What should the project manager have done to avoid this outcome? A.Confirmed the effectiveness of the risk response and monitored progress. B.Updated the assumption log with details concerning the risk. C.Performed a risk analysis to quantify project risk exposure. D.Developed a probability and impact matrix to determine the risk's priority level.
Solution: A. Confirmed the effectiveness of the risk response and monitored progress Project work should be continuously monitored for new, changing, and outdated individual project risks and for changes in the level of overall project risk by applying the Monitor Risks process. The Monitor Risks process uses performance information generated during project execution to determine if the response was effective.
145
A project team lead meets with the project manager before a scheduled kick-off meeting. The team lead is worried that expectations regarding project deliverables might not be realistic. What should the project manager do? A.Review the project business case and the results of the feasibility study. B.Facilitate a meeting between the project sponsor and the team lead to discuss the concerns. C.Meet with the stakeholders to discuss the concerns and record their conclusions in the stakeholder engagement plan. D.Identify the risks and agreed-upon risk responses and modify the risk register accordingly.
Solution: A. Review the project business case and the results of the feasibility study To ensure that the deliverables are realistic, the project manager needs to review the feasibility study and then evaluate the results. The objectives of the project will be determined in the business case, along with the feasibility study to determine the validity of the project. This may result in a go/no-do decision to initiate the project. None of the other choices will ensure this Meeting with the project sponsor or stakeholders will not be helpful before you know how feasible the project is. The risk register can be updated after the the validity of the project is determined.
146
A project manager must get approval for a complex project management plan from multiple stakeholders in various countries before the project can be kicked off. The time to gain approval is limited. What should the project manager first do? A.Schedule a meeting with the stakeholders and walk them through the project plan to gain their approval. B.Distribute the plan to the stakeholders for their review days before scheduling a meeting to obtain approvals. C.Tell the project sponsor that the stakeholder approvals will require more time and adjust the schedule. D.Obtain partial stakeholder approvals and track incomplete approvals as a risk to be managed later.
Solution: B. Distribute the plan to the stakeholders for their review days before scheduling a meeting to obtain approvals. By sending the project management plan to the attendees in advance, the PM can ensure that the meeting is most productive. The other choices are incorrect as they do not address the two vital constraints for the project namely diversified project stakeholders and limited time to gain approval. Some choices even create a greater risk to the project.
146
A stakeholder learns that the equipment purchased for a project is of higher quality than originally agreed upon. The stakeholder is concerned that this deviation has negatively impacted the budget. The stakeholder contacts the project manager and demands clarification. What action should the project manager have taken to avoid the situation? A.Updated the communications management plan. B.Shared results of risk analysis for the equipment. C.Performed integrated change control procedures. D.Conducted regular equipment quality assessments.
Solution: C. Performed integrated change control procedures. The project manager should have performed integrated change control procedures to seek approval for the change to the equipment before purchasing it. This would have prevented the stakeholder's concern from arising in the first place. Integrated change control is the appropriate process to address changes to the project's scope, quality, or other parameters. Even if the change is small and appears to have no impact, small changes can have unintended consequences. In the context of predictive project management, it is especially important to follow a change process, even for small, low-impact changes. Evaluating the impact of the change, obtaining necessary approvals, and communicating the decision to stakeholders ensures that the change is managed in a structured and controlled manner. The other options are incorrect because they do not directly address the issue of preventing unauthorized changes. Updating the communications management plan does not effectively address the issue. If the project manager had adhered to the change control process, they would have obtained approval for the change from the appropriate stakeholders, including the stakeholder who is concerned about the cost. Sharing the results of a risk analysis is good practice, but does not address the stakeholder's concerns or replace the need for an integrated change control procedure. Performing regular equipment quality assessments is part of ongoing project execution, but doesn't replace the need for integrated change control when there's a change that impacts project parameters.
147
As a project manager of a technology firm, a change in the scope is required to implement a change in the project. What tools can be utilized to better understand the impact of the change? A.Pareto chart B.Fishbone diagram C.Deming's PDCA cycle D.Cause and effect diagram
Solution: C. Deming's PDCA cycle Deming's PDCA cycle is the correct option. The other options are not used to understand change impact.
148
What is the reason for relationship network change? A.Roles and titles are formally assigned B.Evolves over time as people gain and lose influence C.Built-in advance by corporate management D.Visible to everyone in the organization
Solution: B. Evolves over time as people gain and lose influence Relationship network changes over time as the project progresses people lose or gain influence. Other options are incorrect as they are true in essence but are not the reason the Relationship network changes over time
149
A project manager is working on an IT project. During an iteration review meeting, a couple of key stakeholders enter into a heated discussion about the prototype's capabilities. What should the project manager do next? A.Plan a brainstorming session with the project team to find a resolution to the problem. B.Identify the source of the conflict between the stakeholders and address the issue. C.List the positives and negatives of the situation to determine the impact of this conflict. D.Invite the project sponsor to intervene and act as a negotiator for the key stakeholders.
Solution: B. Identify the source of the conflict between the stakeholders and address the issue. Projects operate in dynamic environments and face many mutually exclusive constraints including budget, scope, schedule, and quality, which can lead to conflicts. There are many potential sources of conflict regarding the prototype's capabilities, and without understanding the source of the conflict, the project manager cannot effectively resolve it. The project manager should seek to identify the source of the conflict, address the issue, and work to resolve it. Addressing conflict before it escalates beyond useful debate leads to better outcomes. The other answer choices are incorrect because without knowing the source of the conflict, it can't be known whether inviting the project sponsor to intervene or planning a brainstorming session will resolve the conflict. Generating a list of positives and negatives is not an effective way to address the situation. While understanding the impact of the conflict may be helpful, it is not as important as identifying the source of the conflict and working to resolve it. If it is not resolved, the impact will grow.
150
Within the fourth iteration of product development, the project manager realizes that the software used for the project management plan is not permitting planned updates. Which action should the project manager take? A.Select a team resource who can update the project management plan template. B.Based on business value for the upcoming iterations, choose a priority for the activities. C.Resolve the issue independently so that team members do not become distracted. D.Add the problem as a new project risk in the risk register and suggest corrective actions.
Solution: C. Resolve the issue independently so that team members do not become distracted A project manager's job is to remove impediments to team performance, therefore software deficiencies must be addressed at an administrative level and not at the team level. The other answer choices are incorrect. They are not valid because administrative resources, rather than team resources, will be used to address the issue.
151
A goal has been set at four months for a project team to distribute a product. Unfortunately, it will be difficult to adhere to that time frame due to team members having individual tasks to complete. How should the project manager handle this situation? A.Encourage members of the team to alter their tasks in order to not impede with meeting the project deadline. B.Aid team members in prioritizing their personal tasks against the project's goals. C.Postpone the delivery date of the project to a later time so the team can complete their personal tasks. D.Request a delay to the teams’ individual tasks and offer assistance finding alternative times to complete tasks outside of work hours.
Solution: B. Aid team members in prioritizing their personal tasks against the project's goals In the case that there is limited time, the team must prioritize the delivery-related tasks to get the product distributed on time. The project manager should handle this situation by aiding team members in prioritizing their personal tasks against the project's goals. The other answer choices do not lead to the desired outcome.
152
A project manager is working on an complex project with multiple stakeholders and competing priorities. Each stakeholder wants to maximize its share of the allocated resources for the requested functionality. What should the project manager focus on? A.Meeting the personal interests of stakeholders. B.Meeting the mutual interests of all stakeholders. C.Preserving the relationships and rapport with stakeholders. D.Pushing stakeholders to accept the project manager's viewpoint.
Solution: B. Meeting the mutual interests of all stakeholders. The project manager should focus on finding a solution that meets the needs of all stakeholders, even if it means making some compromises. This will help ensure the project's success and maintain good relationships with stakeholders. The other answer choices are incorrect. Meeting the personal interests of stakeholders is not always possible, and it may not be in the project's best interests. Preserving the relationships and rapport with stakeholders is important but not the most important thing. The project manager should focus on meeting the needs of stakeholders, even if it means some relationships are impacted. Pushing stakeholders to accept the project manager's viewpoint is not a good strategy. This will only alienate stakeholders and make it more difficult to reach a consensus.
153
A project manager is leading a key flagship solution initiative prioritizing agility, market adaptation, and rapid response to market trends. Which activity should the project manager prioritize first to ensure success? A.Conduct periodic reviews of project plans, objectives, and deliverables to ensure all data is captured. B.Request more funding from the sponsor to hire additional skilled resources and improve quality. C. Collaboratively review project objectives with the sponsor to agree on achievable plans and deliverables. D.Create a business case after a market review to adjust project deliverables based on new objectives.
Solution: C. Collaboratively review project objectives with the sponsor to agree on achievable plans and deliverables. Given the project's focus on agility, adaptability, and responsiveness to market trends, the project manager should establish clear and achievable goals. Collaboration with the sponsor ensures a shared understanding of priorities and market realities, alignment between project plans and expectations, and flexibility to adapt plans based on evolving market trends. The other answer choices are incorrect. Conducting periodic reviews might delay adaptation. Requesting more funding might be reactive rather than proactive and doesn't address the core need for flexibility. Creating a new business case implies starting over, potentially delaying the project, and neglecting existing plans.