PMP Test Flashcards

1
Q

What is a System of Value Delivery?

A

Portfolios, Programs, Projects, Products, etc. that aim to build, sustain, and/or advance an organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the Information Flow? (5)

A

Senior Leadership (Strategy) to Portfolios (Outcomes) to Programs/Projects (Deliverables) to Operations and they all report back accordingly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Adaptive and hybrid projects may require

A

Ongoing feedback and business direction. Predictive projects can set feedback checkpoints

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the Product Life Cycle phases (4)

A

Introduction, Growth, Maturity, Decline/Retirement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the three main types of product management.

A

Program within a product life cycle, Project within a product life cycle , Product within a Program

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the 5 System of Value Delivery components?

A

External, Internal, Portfolio, Program, Project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the PM values?

A

Responsibility, Respect, Fairness, Honesty

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the 12 PM Principles?

A

stewardship
teamwork
stakeholder engagement
value creation
systems thinking
leadership
tailored approaches
quality focus
managing project complexity
risk management
building adaptability and resiliency
change management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the 8 PM project performance domains?

A

Stakeholders
Team
Development, Approach and Life Cycle
Planning
Project Work
Delivery
Measurement
Uncertainty

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a stakeholder?

A

Any individual, group, or organization that may affect or be affected or perceived to be affected by the project. Including 3rd party, internal, and external customers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Example of stakeholders

A

Suppliers, Org governance bodies, PM Team, End users

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the 6 steps to stakeholder engagement?

A

Identify, Understand (mind), Analyze (position), Prioritize, Engage, Monitor (changes)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the 4 elements of Emotional Intelligence?

A

Self-Awerness, Self-Management, Social Awareness, Social Skill

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a predictive approach?

A

AKA Waterfall. Used for projects with high level of risk and investment that may require replanning between dev phases but the scope, schedule, cost, resources, and risk are well defined early and are stable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is adaptive approach?

A

Requirements are highly uncertain/volatile and likely to change during the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Example of Life Cycle Phase? (6)

A

Feasibilty, Design, Build, Test, Deploy, Close

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is crashing?

A

Shortening by adding more resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is fast tracking?

A

Compressing the schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is deterministic vs probabilistic estimating?

A

Probabilistic provides a range through creating an average or simulation. Deterministic on number is given aka point estimate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What is a Flow Based Estimate?

A

Cycle time and throughput

1 wall takes 5 mins so 5 walls will take 25mins

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What are the 4 types of activity dependency?

A

Mandatory - cannot be modified
Discretionary - can be modified for best practices
External - depends on non project activity and cannot be modified
Internal - involves one or more project activities and can be modified

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Adaptive Schedule Example (7)

A

Product Vision
Product Roadmap
Release Plan
Iterations
(Epics)
Feature - per user Story
Tasks - delivers user story

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is the Cost Baseline

A

Developed from the cost estimate, it show when costs will be incurred.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is included in the project budget?

A

The estimate and contingency reserve. The Management reserve is not included.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
What are the 3 bid documents?
Request for Information Request for proposal Request for quote
25
What are the 2 types of Key Performance Indicators?
Leading predicts changes or trends in the project and Lagging provides information on the deliverables
26
What are the characteristics of a effective metric?
SMART Specific Meaningful Achievable Relevant Timely
27
What is Little's Law?
The more work you have in progress, the slower all the work gets.
28
What is estimate to complete?
Forecasting the amount that will be needed to complete the current project based on the current performance. (ETC) ETC = EAC - AC
29
What is estimate at completion?
Forecasting the total cost of the project at the end based on the current spending rate of the project. (EAC) EAC = BAC / CPI
30
What are the 3 elements in the Theory of Need?
Achievement, Power, Affiliation
31
What are the 3 Theories?
Theory X - people are only motivated by money (micromanager) Theory Y - people want to do good work (Coaching) Theory Z - people are motivated by a high calling (insight & meaning)
32
What is Ouchi's theory?
Based off Z, focus on creating a job for life where the focus is on the employee's well being and family
33
What is the ADKAR?
The five step of adapting change: Awareness - why Desire - support Knowledge - learn the new process Ability - start changing Reinforcement - incentives
34
What are the 5 steps of implementing change in an organization.
Formulate change Plan Change Implement Change Manage Change Sustain Change
35
What are the 8 steps to leading change?
Create urgency Form Powerful Coalition Create a vision Communicate vision Remove obstacles Create short term wins Build on the change Anchor change in corp culture
36
What is the Tuckman Ladder?
The stages of forming a high performance team aka a team performance model. Forming Storming Norming Performing Adjourning
37
What is the Drexler/Sibbet team performance model?(7)
1. Orientation - why 2. Trust Building - who 3. Goal Setting - what 4. Commitment - how 5. Implementation - details/work starts 6. High Performance - smooth 7. Renewal - changes
38
What are the elements of a Salience indentification?
Created by the stakeholders: power, influence, urgency
39
What are the three types of project reports?
Quality, Risk, Status
40
Define total float
The maximum number of days the activity can be delayed without delaying the project completion date.
41
What is schedule variance (SV)?
The difference between the amount of work we should have done vs. the amount actually done. This value should be positive for ahead of schedule. Negative values indicate behind schedule Earned value - planned value
42
What is schedule performance index (SPI)?
The rate of how we are meeting the project schedule. This value should be 1 and over for a project to be ahead of the schedule. EV/PV
43
What is Feature Completion rate?
The feature acceptance rate
44
What is Cost Variance (CV)?
The difference between the work done and money spent. This value should be positive for under budget. Negative values indicate over budget CV = Earned value - actual cost
45
What is Cost Performance Index (CPI)?
The rate of how we are spending to actually earning on the project. This value should be 1 and over for projects under budget. EV / AC
46
What is Variance at completion (VAC)?
The difference between the original budget and new forecasted budget. This value should be positive for projects that may end at or under budget BAC - EAC
47
What is To-Complete performance index (TCPI)
The performance that needs to be met to finish the project within the budget. TCPI = (BAC – EV) / (BAC – AC)
48
What is the Hawthorne Effect?
individuals modify an aspect of their behavior in response to their awareness of being observed
49
What is vanity metric?
none useful information
50
What is OSCAR?
A coaching model Outcome - goals & desired results Situation - figure things out Choices/Consequences - choose a path Actions - go Review - regular meetings
51
What are Herzberg's 2 motivation factors?
Hygiene - related to work like location, salary, policies Motivation - recognition & achievement
52
What are intrinsic motivations?
autonomy, mastery, purpose
53
What is Virginia Satir's Change Model (6)?
Late Status Quo Foreign Element Chaos Transforming Idea Practice & Integration New Status Quo
54
What is a single-point estimate?
A point estimate is a single value estimate of a parameter. For instance, a sample mean is a point estimate of a population mean.
55
What is a story point estimate?
Story points are units of measure for expressing an estimate of the overall effort required to fully implement a product backlog item or any other piece of work
56
What is Wideband Delphi?
a process used to arrive at a group opinion or decision by surveying a panel of experts.
57
What is Earned Value analysis?
a method that allows the project manager to measure the amount of work actually performed on a project beyond the basic review of cost and schedule reports. Earned Value (EV): % complete x BAC
58
What is Expected Monetary Value (EMV)?
a statistical technique used in risk management. It's a way of quantifying the expected loss or gain Positive EMV = % X Net Negative EMV = % x cost Overall EMV= PEMV - NEMV
59
What is SWOT?
evaluate a company's competitive position Strengths Weaknesses Opportunities Threats
60
List the types of meetings? (7)
Backlog Refinement Bidder Conference Change Control Board Daily Standup Iteration Planning Iteration Review Kickoff
61
List of artifacts? (6)
Business Case Business Model Canvas Project Brief Project Charter Project Vision Statement Roadmap
62
List the logs & registers? (8)
Assumption Log Backlog Change Log Issue Log Lessons Learned Register Risk-Adjusted Backlog - addresses risk Risk Register Stakeholder Register
63
List of Plans? (15)
Change Control Plan Communication Management Plan Cost Management Plan Iteration Plan Procurement Management Plan Project Management Plan Quality Management Plan Release Plan Requirements Management Plan Resource Management Plan Risk Management Plan Scope Management Plan Schedule Management Plan Stakeholder Management Plan Test Plan
64
List of Charts? (5)
Organizational Breakdown Structure Product Breakdown Structure Resource Breakdown Structure Risk Breakdown Structure Work Breakdown Structure
65
List of Baselines? (5)
Budget Milestone Schedule Performance Measurement Baseline Project Schedule Scope Baseline
66
List of Visual Data? (23)
Affinity Diagram Burndown/burnup chart Cause & Effect Diagram Cumulative Flow Diagram Cycle Time Chart Dashboards Flowchart Gnatt Chart Histogram Information Radiator Lead Time Chart Prioritization Matrix Project Schedule Network Diagram Requirement Traceability Matrix Responsibility Assignment Matrix (RAM) Scatter Diagram S-Curve Stakeholder Engagement Assessment Matrix Story Map Throughput Chart Use Case Value Stream Map Velocity Chart
67
List the contracts? (4)
Fixed-price contracts Cost-reimbursable contracts Time & Materials Indefinite Delivery Indefinite Quantity (IDIQ)
68
Budget at Completion (BAC)
Original budget of the project
69
Planned Value (PV)
Amount of money worth of work we that should have been done on the project. PV = % Complete (Planned) x Task budget
70
Earned Value (EV)
Amount of money worth of work you actually did on the project. EV= % Complete x BAC
71
Actual Cost (AC)
Amount of money you already spent on the project
72
What is the critical path of a project?
The longest sequence of tasks that must be completed to execute a project
73
What is Domain?
Defined as the high-level knowledge area that is essential to the practice of project management.
74
What is an Enabler?
Illustrative examples of the work associated with the task. Please note that enablers are not meant to be an exhaustive list but rather offer a few examples to help demonstrate what the task encompasses.
75
What is a Task?
The underlying responsibilities of the project manager within each domain area.
76
What is servant leadership?
Flexibility, empathy, stewardship, and listening
77
List the Domain 1 People tasks? (14)
Manage conflict Lead a team Support team performance Empower team members and stakeholders Ensure team members/stakeholders are adequately trained Build a team Address and remove impediments, obstacles, and blockers for the team Negotiate project agreements Collaborate with stakeholders Build shared understanding Engage and support virtual teams Define team ground rules Mentor relevant stakeholders Promote team performance through the application of emotional intelligence
78
Manage conflict (3)
- Interpret the source and stage of the conflict - Analyze the context for the conflict - Evaluate/recommend/reconcile the appropriate conflict resolution solution
79
Lead a team (7)
- Set a clear vision and mission - Support diversity and inclusion (e.g., behavior types, thought process) - Value servant leadership (e.g., relate the tenets of servant leadership to the team) - Determine an appropriate leadership style (e.g., directive, collaborative) - Inspire, motivate, and influence team members/stakeholders (e.g., team contract, social contract, reward system) - Analyze team members and stakeholders’ influence - Distinguish various options to lead various team members and stakeholders
80
Support team performance (4)
- Appraise team member performance against key performance indicators - Support and recognize team member growth and development - Determine appropriate feedback approach - Verify performance improvements
81
Empower team members and stakeholders (4)
- Organize around team strengths - Support team task accountability - Evaluate demonstration of task accountability - Determine and bestow level(s) of decision-making authority
82
Ensure team members/stakeholders are adequately trained (4)
- Determine required competencies and elements of training - Determine training options based on training needs - Allocate resources for training - Measure training outcomes
83
Build a team (4)
- Appraise stakeholder skills - Deduce project resource requirements - Continuously assess and refresh team skills to meet project needs - Maintain team and knowledge transfer
84
Address and remove impediments, obstacles, and blockers for the team (4)
- Determine critical impediments, obstacles, and blockers for the team - Prioritize critical impediments, obstacles, and blockers for the team - Use network to implement solutions to remove impediments, obstacles, and blockers for the team - Re-assess continually to ensure impediments, obstacles, and blockers for the team are being addressed
85
Negotiate project agreements (5)
- Analyze the bounds of the negotiations for agreement - Assess priorities and determine ultimate objective(s) - Verify objective(s) of the project agreement is met - Participate in agreement negotiations - Determine a negotiation strategy
86
Collaborate with stakeholders (3)
- Evaluate engagement needs for stakeholders - Optimize alignment between stakeholder needs, expectations, and project objectives - Build trust and influence stakeholders to accomplish project objectives
87
Build shared understanding (4)
- Break down situation to identify the root cause of a misunderstanding - Survey all necessary parties to reach consensus - Support outcome of parties' agreement - Investigate potential misunderstandings
88
Engage and support virtual teams (4)
- Examine virtual team member needs (e.g., environment, geography, culture, global, etc.) - Investigate alternatives (e.g., communication tools, colocation) for virtual team member engagement - Implement options for virtual team member engagement - Continually evaluate effectiveness of virtual team member engagement
89
Define team ground rules (3)
- Communicate organizational principles with team and external stakeholders - Establish an environment that fosters adherence to the ground rules - Manage and rectify ground rule violations
90
Mentor relevant stakeholders (2)
- Allocate the time to mentoring - Recognize and act on mentoring opportunities
91
Promote team performance through the application of emotional intelligence (2)
- Assess behavior through the use of personality indicators - Analyze personality indicators and adjust to the emotional needs of key project stakeholders
92
List the Domain 2 Process tasks? (17)
Execute project with the urgency required to deliver business value Manage communications Assess and manage risks Engage stakeholders Plan and manage budget and resources Plan and manage schedule Plan and manage quality of products/deliverables Plan and manage scope Integrate project planning activities Manage project changes Plan and manage procurement Manage project artifacts Determine appropriate project methodology/methods and practices Establish project governance structure Manage project issues Ensure knowledge transfer for project continuity Plan and manage project/phase closure or transitions
93
Execute project with the urgency required to deliver business value (3)
- Assess opportunities to deliver value incrementally - Examine the business value throughout the project - Support the team to subdivide project tasks as necessary to find the minimum viable product
94
Manage communications (4)
- Analyze communication needs of all stakeholders - Determine communication methods, channels, frequency, and level of detail for all stakeholders - Communicate project information and updates effectively - Confirm communication is understood and feedback is received
95
Assess and manage risks (2)
- Determine risk management options - Iteratively assess and prioritize risks
96
Engage stakeholders (4)
- Analyze stakeholders (e.g., power interest grid, influence, impact) - Categorize stakeholders - Engage stakeholders by category - Develop, execute, and validate a strategy for stakeholder engagement
97
Plan and manage budget and resources (4)
- Estimate budgetary needs based on the scope of the project and lessons learned from past projects - Anticipate future budget challenges - Monitor budget variations and work with governance process to adjust as necessary - Plan and manage resources
98
Plan and manage schedule (6)
- Estimate project tasks (milestones, dependencies, story points) - Utilize benchmarks and historical data - Prepare schedule based on methodology - Measure ongoing progress based on methodology - Modify schedule, as needed, based on methodology - Coordinate with other projects and other operations
99
Plan and manage quality of products/deliverables (3)
- Determine quality standard required for project deliverables - Recommend options for improvement based on quality gaps - Continually survey project deliverable quality
100
Plan and manage scope (3)
- Determine and prioritize requirements - Break down scope (e.g., WBS, backlog) - Monitor and validate scope
101
Integrate project planning activities (5)
- Consolidate the project/phase plans - Assess consolidated project plans for dependencies, gaps, and continued business value - Analyze the data collected - Collect and analyze data to make informed project decisions - Determine critical information requirements
102
Manage project changes (4)
- Anticipate and embrace the need for change (e.g., follow change management practices) - Determine strategy to handle change - Execute change management strategy according to the methodology - Determine a change response to move the project forward
103
Plan and manage procurement (5)
- Define resource requirements and needs - Communicate resource requirements - Manage suppliers/contracts - Plan and manage procurement strategy - Develop a delivery solution
104
Manage project artifacts (3)
- Determine the requirements (what, when, where, who, etc.) for managing the project artifacts - Validate that the project information is kept up to date (i.e., version control) and accessible to all stakeholders - Continually assess the effectiveness of the management of the project artifacts
105
Determine appropriate project methodology/methods and practices (4)
- Assess project needs, complexity, and magnitude - Recommend project execution strategy (e.g., contracting, finance) - Recommend a project methodology/approach (i.e., predictive, agile, hybrid) - Use iterative, incremental practices throughout the project life cycle (e.g., lessons learned, stakeholder engagement, risk)
106
Establish project governance structure (2)
- Determine appropriate governance for a project (e.g., replicate organizational governance) - Define escalation paths and thresholds
107
Manage project issues (3)
- Recognize when a risk becomes an issue - Attack the issue with the optimal action to achieve project success - Collaborate with relevant stakeholders on the approach to resolve the issues
108
Ensure knowledge transfer for project continuity (3)
- Discuss project responsibilities within team - Outline expectations for working environment - Confirm approach for knowledge transfers
109
Plan and manage project/phase closure or transitions (3)
- Determine criteria to successfully close the project or phase - Validate readiness for transition (e.g., to operations team or next phase) - Conclude activities to close out project or phase (e.g., final lessons learned, retrospective, procurement, financials, resources)
110
List the Domain 3 Business Environment tasks? (4)
Plan and manage project compliance Evaluate and deliver project benefits and value Evaluate and address external business environment changes for impact on scope Support organizational change
111
Support organizational change (3)
- Assess organizational culture - Evaluate impact of organizational change to project and determine required actions - Evaluate impact of the project to the organization and determine required actions
112
Evaluate and address external business environment changes for impact on scope (4)
- Survey changes to external business environment (e.g., regulations, technology, geopolitical, market) - Assess and prioritize impact on project scope/backlog based on changes in external business environment - Recommend options for scope/backlog changes (e.g., schedule, cost changes) - Continually review external business environment for impacts on project scope/backlog
113
Evaluate and deliver project benefits and value (5)
- Investigate that benefits are identified - Document agreement on ownership for ongoing benefit realization - Verify measurement system is in place to track benefits - Evaluate delivery options to demonstrate value - Appraise stakeholders of value gain progress
114
Plan and manage project compliance (7)
- Confirm project compliance requirements (e.g., security, health and safety, regulatory compliance) - Classify compliance categories - Determine potential threats to compliance - Use methods to support compliance - Analyze the consequences of noncompliance - Determine necessary approach and action to address compliance needs (e.g., risk, legal) - Measure the extent to which the project is in compliance