PMP Test Flashcards
What is a System of Value Delivery?
Portfolios, Programs, Projects, Products, etc. that aim to build, sustain, and/or advance an organization.
What is the Information Flow? (5)
Senior Leadership (Strategy) to Portfolios (Outcomes) to Programs/Projects (Deliverables) to Operations and they all report back accordingly
Adaptive and hybrid projects may require
Ongoing feedback and business direction. Predictive projects can set feedback checkpoints
What are the Product Life Cycle phases (4)
Introduction, Growth, Maturity, Decline/Retirement
What are the three main types of product management.
Program within a product life cycle, Project within a product life cycle , Product within a Program
What are the 5 System of Value Delivery components?
External, Internal, Portfolio, Program, Project
What are the PM values?
Responsibility, Respect, Fairness, Honesty
What are the 12 PM Principles?
stewardship
teamwork
stakeholder engagement
value creation
systems thinking
leadership
tailored approaches
quality focus
managing project complexity
risk management
building adaptability and resiliency
change management
What are the 8 PM project performance domains?
Stakeholders
Team
Development, Approach and Life Cycle
Planning
Project Work
Delivery
Measurement
Uncertainty
What is a stakeholder?
Any individual, group, or organization that may affect or be affected or perceived to be affected by the project. Including 3rd party, internal, and external customers.
Example of stakeholders
Suppliers, Org governance bodies, PM Team, End users
What are the 6 steps to stakeholder engagement?
Identify, Understand (mind), Analyze (position), Prioritize, Engage, Monitor (changes)
What are the 4 elements of Emotional Intelligence?
Self-Awerness, Self-Management, Social Awareness, Social Skill
What is a predictive approach?
AKA Waterfall. Used for projects with high level of risk and investment that may require replanning between dev phases but the scope, schedule, cost, resources, and risk are well defined early and are stable.
What is adaptive approach?
Requirements are highly uncertain/volatile and likely to change during the project
Example of Life Cycle Phase? (6)
Feasibilty, Design, Build, Test, Deploy, Close
What is crashing?
Shortening by adding more resources
What is fast tracking?
Compressing the schedule
What is deterministic vs probabilistic estimating?
Probabilistic provides a range through creating an average or simulation. Deterministic on number is given aka point estimate.
What is a Flow Based Estimate?
Cycle time and throughput
1 wall takes 5 mins so 5 walls will take 25mins
What are the 4 types of activity dependency?
Mandatory - cannot be modified
Discretionary - can be modified for best practices
External - depends on non project activity and cannot be modified
Internal - involves one or more project activities and can be modified
Adaptive Schedule Example (7)
Product Vision
Product Roadmap
Release Plan
Iterations
(Epics)
Feature - per user Story
Tasks - delivers user story
What is the Cost Baseline
Developed from the cost estimate, it show when costs will be incurred.
What is included in the project budget?
The estimate and contingency reserve. The Management reserve is not included.
What are the 3 bid documents?
Request for Information
Request for proposal
Request for quote
What are the 2 types of Key Performance Indicators?
Leading predicts changes or trends in the project and Lagging provides information on the deliverables
What are the characteristics of a effective metric?
SMART
Specific
Meaningful
Achievable
Relevant
Timely
What is Little’s Law?
The more work you have in progress, the slower all the work gets.
What is estimate to complete?
Forecasting the amount that will be needed to complete the current project based on the current performance. (ETC)
ETC = EAC - AC
What is estimate at completion?
Forecasting the total cost of the project at the end based on the current spending rate of the project. (EAC)
EAC = BAC / CPI
What are the 3 elements in the Theory of Need?
Achievement, Power, Affiliation
What are the 3 Theories?
Theory X - people are only motivated by money (micromanager)
Theory Y - people want to do good work (Coaching)
Theory Z - people are motivated by a high calling (insight & meaning)
What is Ouchi’s theory?
Based off Z, focus on creating a job for life where the focus is on the employee’s well being and family
What is the ADKAR?
The five step of adapting change:
Awareness - why
Desire - support
Knowledge - learn the new process
Ability - start changing
Reinforcement - incentives
What are the 5 steps of implementing change in an organization.
Formulate change
Plan Change
Implement Change
Manage Change
Sustain Change
What are the 8 steps to leading change?
Create urgency
Form Powerful Coalition
Create a vision
Communicate vision
Remove obstacles
Create short term wins
Build on the change
Anchor change in corp culture
What is the Tuckman Ladder?
The stages of forming a high performance team aka a team performance model.
Forming
Storming
Norming
Performing
Adjourning
What is the Drexler/Sibbet team performance model?(7)
- Orientation - why
- Trust Building - who
- Goal Setting - what
- Commitment - how
- Implementation - details/work starts
- High Performance - smooth
- Renewal - changes
What are the elements of a Salience indentification?
Created by the stakeholders: power, influence, urgency
What are the three types of project reports?
Quality, Risk, Status
Define total float
The maximum number of days the activity can be delayed without delaying the project completion date.
What is schedule variance (SV)?
The difference between the amount of work we should have done vs. the amount actually done. This value should be positive for ahead of schedule. Negative values indicate behind schedule
Earned value - planned value
What is schedule performance index (SPI)?
The rate of how we are meeting the project schedule. This value should be 1 and over for a project to be ahead of the schedule.
EV/PV
What is Feature Completion rate?
The feature acceptance rate
What is Cost Variance (CV)?
The difference between the work done and money spent. This value should be positive for under budget. Negative values indicate over budget
CV = Earned value - actual cost
What is Cost Performance Index (CPI)?
The rate of how we are spending to actually earning on the project. This value should be 1 and over for projects under budget.
EV / AC