PMP Terminology Flashcards
Bottom-up Estimating
A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS)
Sponsor
A person or group who provides resources and support for the project, program, or portfolio, and is accountable for enabling success
Secondary Risk
A risk that arises as a direct result of implementing a risk response
Actual Cost
The realized cost incurred for the work performed on an activity during a specific time period
Project Scope Statement
The description of the project scope, major deliverables, assumptions, and constraints
Project Management
The application of knowledge, skills, tools, and techniques to project activities to meet the project requirements
Product Life Cycle
The series of phases that represent the evolution of a product, from concept through delivery, growth, maturity, and to retirement
Critical Path Activity
Any activity on the critical path in a project schedule
Work Package
The work defined at the lowest level of the work breakdown structure for which cost and duration can be estimated
Change Control
A process whereby modifications to documents, deliverables, or baselines associated with the project are identified, documented, approved, or rejected
Late Finish Date
In the critical path method, the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, the project completion date, and any schedule constraints
Defect Repair
An intentional activity to modify a nonconforming product or product component
Precedence Diagramming Method
A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed
Change Control System
A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled
Critical Path Method
A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model
Data Date
A point in time when the status of the project is recorded
Project
A temporary endeavor undertaken to create a unique product, service, or result
Finish-to-Finish
A logical relationship in which a successor activity cannot finish until a predecessor activity has finished
Change Request
A formal proposal to modify any document, deliverable, or baseline
Optimistic Duration
An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance
Scope Baseline
The approved version of a scope statement, work breakdown structure (WBS) and its associated WBS dictionary, which can be changed only through formal change control procedures and is used as a basis for comparison
Early Start Date
In the critical path method, the earliest point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic, the data date, and any schedule constraints
Free Float
The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint
S-Curve Analysis
An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period
Earned Value Management
A methodology that combines scope, schedule, and resource measurements to assess project performance and progress
Schedule Variance
A measure of schedule performance expressed as the difference between the earned value and planned value
To-Complete Performance Index
A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the remaining budget
Workaround
A response to a threat that has occurred, for which a prior response had not been planned or was not effective
Forward Pass
A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time
Risk Avoidance
A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact
Resource Leveling
A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply
Trigger Condition
An event or situation that indicates that a risk is about to occur
Predecessor Activity
An activity that logically comes before a dependent activity in a schedule
Critical Path
The sequence of activities that represent the longest path through a project, which determines the shortest possible duration
Critical Chain Method
A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties
Schedule Compression
A technique used to shorten the schedule duration without reducing the project scope
Crashing
A technique used to shorten the schedule duration for the least incremental cost by adding resources
What-If Scenario Analysis
The process of evaluating scenarios in order to predict their effect on project objectives
Stakeholder
An individual, group, or organization who may affect, be affected by, or perceive itself to be affected by a decision, activity, or outcome of a project, program, or portfolio
Estimate to Complete
The expected cost to finish all the remaining project work
Finish-to-Start
A logical relationship in which a successor activity cannot start until a predecessor activity has finished
Planned Value
The authorized budget assigned to schedule work
Fast Tracking
A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration
Start-to-Start
A logical relationship in which a successor activity cannot start until a predecessor activity has started
Risk Acceptance
A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs
Parametric Estimating
An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters
Schedule Performance Index
A measure of schedule efficiency expressed as the ratio of earned value to planned value
Pessimistic Duration
An estimate of the longest activity duration, which takes into account all the known variables that could affect performance
Project Charter
A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities
Opportunity
A risk that would have a positive effect on one or more project objectives
Work Breakdown Structure
A hierarchical decomposition of the total scope of work to be carried out by the project team accomplish the project objectives and create the required deliverables
Scope Management Plan
A component of the project or program management plan that describes how the scope will be defined, developed, monitored, controlled, and verified
Risk Category
A group of potential causes of risk
Successor Activity
A dependent activity that logically comes after another activity in a schedule
Cost Management Plan
A component of a project or program management plan that describes how costs will be planned, structured, and controlled
Lessons Learned
The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Deliverable
Any unique and verifiable product, result, or capability to perform a service that is required to be produced to complete a process, phase, or project
Project Management Office
A management structure that standardizes the project-related governance processes and facilitates the sharing of resources, methodologies, tools, and techniques
Organizational Process Assets
Plans, processes, policies, procedures, and knowledge bases specific to and used by the performing organization
Variance Analysis
A technique for determining the cause and degree of difference between the baseline and actual performance
Risk Management Plan
A component of the project, program, or portfolio management plan that describes how risk management activities will be structured and performed
Project Life Cycle
The series of phases that project passes through from its initiation to its closure