PMP Student Manual Vocab Flashcards

1
Q

A general guideline with many applications, it contends that a relatively large number of problems or defects, typically 80%, are commonly due to a relatively small number of causes, typically 20%.

A

80/20 Rule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A marketing approach used to determine user preferences by showing different sets of users similar services with one independent variable.

A

AB Testing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The realized cost incurred for the work performed on an activity during a specific time.

A

AC (Actual Cost)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A strategy for managing negative risks or opportunities that involves acknowledging a risk and not taking any action until the risk occurs.

A

Accept

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A set of conditions that is required to be met before deliverables are accepted.

A

Acceptance Criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A communication technique that involves acknowledging what you hear and clarifying the message to confirm hat what you heard matches the message that the sender intended.

A

Active Listening

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Multiple attributes associated with each schedule activity that can be included within the activity list.

A

Activity Attributes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A logical relationship that exists between two project activities. The relationship indicates whether the start of an activity is contingent upon an event or input from outside the activity.

A

Activity Dependency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The quantitative assessments of the likely number of time periods that are required to complete an activity.

A

Activity Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A documented tabulation of schedule activities that shows the activity description, activity identifier, and a sufficiently detailed scope-of-work description so project team members understand what work is to be performed.

A

Activity List

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A distinct, scheduled portion of work performed during the course of a project.

A

Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Involves verifying and documenting project results to formalize project or phase completion.

A

Administrative Closure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A technique that allows large numbers of ideas to be classified into groups for review and analysis.

A

Affinity Diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

A project lifecycle that is iterative or incremental. Also referred to as change-driven or adaptive, they work well in environments with high levels of change and ongoing stakeholder involvement in a project.

A

Agile Lifecycles

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A project management methodology that uses an iterative and incremental approach that focuses on customer value and team empowerment. In agile project management, the product is developed in iterations by small and integrated teams.

A

Agile Project Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A process in which you determine the number of iterations or Sprints that are needed to complete each release, the features that each iteration will contain, and the target dates of each release.

A

Agile Release Planning

17
Q

Any documents or communication that defines the initial intentions of a project. Examples include contracts, memorandums or understanding (MOUs), service level agreements (SLAs), letters of agreement, letters of intent, verbal agreements, email, or other written agreements.

A

Agreements

18
Q

A technique for estimating the duration or cost of an activity on a project using historical data from a similar activity or project.

A

Analogous Estimating

19
Q

Change requests that have been reviewed and approved by the change control board (CCB) and are ready to be scheduled for implementation.

A

Approved Change Requests

20
Q

A process that explores the validity of the project assumptions within the constraints and identifies risks from any incompleteness or inaccuracy of these project assumptions.

A

Assumption and Constraint Analysis

21
Q

Data that is counted such as the number of product defects or customer complaints.

A

Attribute Sampling Data

22
Q

An examination of a project’s goals and achievements, including adequacy, accuracy, efficiency, effectiveness, and the project’s compliance with the applicable methodologies and regulations. It tends to be a formal, one-sided process that can be extremely demoralizing to team members.

A

Auditing

23
Q

Using this group decision-making method, one member of the group makes the decision. In most cases, this person will consider the larger group’s ideas and decisions and will then make a decision based on that input.

A

Autocratic

24
Q

A strategy for managing negative risks or threats that involves changing the project management plan to remove the risk entirely by extending schedule, changing the strategy, increasing the funding, or reducing the scope.

A

Avoid