PMP Questions Scardo Review Flashcards
A project manager scheduled a review at the end of a phase, with the objective of obtaining authorization to close the current project phase and initiate the next phase. Which of the following is an incorrect way of describing this review? Phase gate Phase planning Kill point Stage gate
B - Stage Gates, Phase Gates and Kill Points refer to the same term and refer to a phase end review with the objective of obtaining authorization to close the current phase and starting the next one. This is a retrospective review of the current phase. The phase planning, on the other hand, is carried out early during the planning phase of the project.[PMBOK 5th edition, Page 41] [Project Framework]
If you are measuring the quality of items in a sample on a pass/fail basis, what is that called? Attribute sampling Biased sampling Variable sampling Stratified sampling
A - The attribute sampling measures the quality characteristic of items in a sample on a pass/fail basis; on the other hand, the variable sampling measures the quality characteristic on a continuous scale. [PMBOK 5th edition, Page 250] [Project Quality Management]
Which of the following should you NOT use as an input into creating the WBS structure? Bill of Material (BOM) Project scope statement Organizational process assets Requirements documentation
A - The Bill of Material (BOM) is not used as an input in the Create WBS process. The other three are valid inputs. [PMBOK 5th edition, Page 125] [Project Scope Management]
In an ongoing project, the project sponsor and a manager of the performing organization are having conflicts. What would be your comment on this situation?
The project manager needs to step in and handle the stakeholders’ expectations. The stakeholders may have different objectives and interests in the project.
The project manager needs to step in and handle the stakeholders’ expectations. All stakeholders are supposed to have the same objectives and interests in a project.
The project manager should resolve in favor of the project sponsor since he is providing the funds for the project.
The project manager should resolve in favor of the manager of the performing organization since they are executing the project and need to be kept in good books.
A - The project manager needs to recognize that the stakeholders could have conflicting interests and objectives. It is the responsibility of the project manager to successfully manage the stakeholders’ expectations. [PMBOK 5th edition, Page 404] [Project Stakeholder Management]
The transition from one phase to another within a project's life cycle (e.g. design to manufacturing) is typically marked by: Kill point Monte Carlo Constraint Decision tree
A - The transition from one phase to another within a project’s lifecycle generally involves, and is usually defined by, some form of technical transfer or handoff. These are also called as kill points. [PMBOK 5th edition, Page 41] [Project Framework]
1.) You are managing a multi-million dollar project, and discover several critical pieces of data in the project information repository have been modified without authorization. What should you do?
A. Determine the extent of the data breach, and implement security procedures to prevent a recurrence.
Determine the extent of the data breach and notify the appropriate project and company staff of the incident.
Determine the extent of the data breach, and restore the modified data from a backup.
Determine the extent of the data breach, and setup auditing to track further unauthorized access.
B - Notification of the appropriate staff of an information security breach, and providing detail to assist with an investigation is the appropriate response. The project manager is responsible for maintaining an accurate project information base and protecting the intellectual property of others, per the code of ethics. Failing to notify project or corporate staff that there has been unauthorized access to critical information violates the PMI code. [Reference: PMI Code of Ethics and Professional Conduct, Page 2,3] [Prof. Responsibility]
As a project manager, you are performing various project performance measurements to assess the magnitude of variation. You then attempt to determine the cause and decide whether corrective action is required. This would be known as: Scope Analysis Variance Analysis Performance Reporting Configuration Management
B - This is known as Variance Analysis. As project manager, you would then attempt to determine the cause of the Variance, relative to the scope baseline and then decide on whether corrective action is required. [PMBOK 5th edition, Page 139] [Project Scope Management]
Quantitative risk analysis should be performed:
only on risks identified by the project manager
only in extreme cases
only on prioritized risks
on all risks
C - Since the quantitative risk analysis is a more in-depth process, it should only be performed on prioritized risks to minimize impact to the overall project schedule. [PMBOK 5th edition, Page 334] [Project Risk Management]
In a cause and effect diagram, which of these is not a potential cause? Personnel Problem statement Time Material
B - A cause-and-effect diagram helps determining the root cause behind a problem statement. The potential causes of a specific effect fall into these categories: time, machine, method, material, energy, measurement, personnel, and environment. [PMBOK 5th edition, Page 236] [Project Quality Management]
Which document describes the project's deliverables and the work required to create those deliverables? Project authorization document Project scope statement Project scope management plan Project charter
B - The project scope statement is the correct response. This document describes the project’s deliverables in detail and the work that is required to create those deliverables. It also forms the baseline for evaluating whether requests for changes are within or outside the project’s boundaries. [PMBOK 5th edition, Page 123] [Project Scope Management]
During a presentation to management, you want to display the project schedule with only the key deliverables displayed. What is the correct tool for this purpose? Project schedule network diagram Critical path network Milestone chart Critical chain diagram
C - A milestone chart displays only the key deliverables and is simple and easy to understand. [PMBOK 5th edition, Page 182] [Project Time Management]
The date through which the project has provided actual status and accomplishments is called: Data Date (DD) Due Date (DD) Project Date (PD) Reporting Date (RD)
A - The date through which the project has provided actual status and accomplishments is called the data date. It is also known as the as-of date or the status date [PMBOK 5th edition, Page 184] [Project Communications Management]
Which of these is NOT a risk diagramming technique? System or process flow charts Cause and effect diagram RACI chart Influence diagrams
C - Risk diagramming techniques can include: cause-and-effect diagrams (also known as the fishbone diagrams), flowcharts, and influence diagrams. [PMBOK 5th edition, Page 325] [Project Risk Management]
A Project Manager's primary professional responsibility is towards: The performing organization The project sponsor All stakeholders Customers
C - A project manager’s professional responsibilities are not limited to any one of the stakeholders. The other choices are correct but not complete by themselves. Expectations of every project stakeholder need to be managed. [PMBOK 5th edition, Page 391] [Prof. Responsibility]
Which process is concerned with providing forecasts to update current cost information? Monitor and Control Project Work Project Management Information System Close Project or Phase Direct and Manage Project Work
A - The Monitor and Control Project Work process is responsible for keeping track of the project’s measures, including cost. [PMBOK 5th edition, Page 86] [Project Integration Management]
Which of these tools and techniques are common to all six Project Integration Management processes? Project management Information System Analytical techniques Facilitation techniques Expert Judgment
D - All six processes of Project. Integration Management use Expert judgment as a tool and technique. [PMBOK 5th edition, Page 65] [Project Integration Management]
What is the difference between a histogram and a Pareto chart?
A histogram is a less accurate version of a Pareto chart.
A histogram is a type of Pareto chart.
A Pareto chart is a type of histogram.
A histogram and a Pareto chart simply different terms for the same technique.
C - A Pareto chart is a type of histogram where the causes are ordered by frequency. [PMBOK 5th edition, Page 237] [Project Quality Management]
As a project manager, you are responsible for determining and delivering the required levels of both grade and quality. Select which of the following statements you disagree with.
Grade relates to the product’s characteristics
Grade relates to the customer requirements
Quality relates to the customer requirements
Quality and grade of a product must be carefully managed
B - The grade of a product relates to the technical characteristics of the product. [PMBOK 5th edition, Page 228] [Project Quality Management]