PMP Prep Deck- SW 2022 Flashcards
What is the term for an individual who is involved with and or impacted by a project?
Stakeholder
INITIATING PHASE
Project success measures define in clear terms the criteria by which project success will be evaluated. What 3 questions do detailed and well-constructed project success measures answer?
- what does success look like?
- how will success be measured?
- what factors may impact my success?
What is the definition of a project?
a. permanent endeavor that produces repetitive outputs??
b. temporary endeavor undertaken to create a unique product, service or result
c. temporary endeavor that produces repetitive outputs
d. temporary endeavor undertaken to create a temporary business or product
b. temporary endeavor undertaken to create a unique product, service or result
Name the two processes in the initiating process group
Develop project charter and ID stakeholders
Which doc describes the necessary info to determine if a project is worth the required investment?
a. service level agreement
b. cost baseline
c. memorandum of understanding
d. business case
d. business case
Who is the person assigned by the performing org to be responsible for achieving the project’s objective?
a. program mgr
b. project mgr
c. functional mgr
d. portfolio mgr
b. project mgr
Power, urgency, and legitimacy are attributes of which stakeholder classification model?
a. salience
b. influence-impact
c. power-interest
d. power-influence
a. salience
Without approval from the project sponsor, there is no project? True or false?
True
The business case is used to record all assumptions and constraints known at any point during the project, True or false?
False
- the assumption log is used to record all assumptions
It is critical to identify all stakeholders as early as possible. True or false?
True
The stakeholder register is rarely updated throughout the life of a project. True or false?
False
- updated as often as new stakeholder info is discovered
What is the definition of the project charter?
Formally documents the high level details of a project as well as several key elements that structure and organize the formation of a project
What is the assumption log and in which process is it created?
Used to record all assumptions and constraints known at any point during the project. It is one of the major outputs of the develop project charter process
What is the project stakeholder register and in which process is it created?
A document used to record pertinent info on every stakeholder, including each stakeholder’s function, title, level of interest in the project, and level of influence. It is created during the identify stakeholders process
What is the difference between a project charter and business case?
Project charter formally documents the high level details of a project and after approval by the sponsor, formally authorizes the project
The business case help define the objectives, purpose, and assumptions of a project. It is used prior to starting a project to determine if the benefits of achieving the objectives are worth the investment
Which of the following is not a goal of the initiating process group?
a. define the project
b. obtain project approval
c. define the scope
d. identify and start to understand the stakeholders
c. define the scope
- scope is defined in the planning process group
What is the main goal of the develop project charter (4.1) process?
Focuses on developing and gaining sponsor approval of the project charter
What is the main goal of the identify stakeholders (13.1) process?
The identify stakeholders process identifies, analyzes, and classifies all stakeholders that could impact, or be impacted by, the project
Which of the following is not an input to the deliver project charter process?
a. business case
b. project mgmt plan
c. agreements
d. EEFs and OPAs
b. project mgmt plan
Early in the project, what are two important inputs to identify stakeholders?
Project charter and business case
Stakeholder_______ and _______ helps the team design ways to appropriately engage each stakeholder
Identification and analysis
Which of the following is a method of eliciting info from groups or individuals, such as team members or subject matter experts?
a. brainstorming
b. data analysis
c. bidder conference
d. EEF
a. brainstorming
Which of the following is a method of eliciting info from groups or individuals, such as team members or subject matter experts?
a. brainstorming
b. data analysis
c. bidder conference
d. EEF
a. brainstorming
What is a mapping technique used to identify where stakeholders are perceived to be relative to their power and interest in the project?
Power-interest grid
How should stakeholders with high power and high interest be classified and managed?
Closely
PLANNING PHASE
List the following processes in the order in which they should be completed:
- create WBS
- collect requirements
- plan scope mgmt
- define scope
Although iterative, general order is
- plan scope mgmt
- collect requirements
- define scope
- create WBS
A project ____ meeting is a common practice to clearly communicate project objectives and build team and stakeholders buy in
kick off
What is the major output created by the four scope mgmt processes in the planning process group?
Scope baseline
_____ defines all the necessary work that is required t complete the project
Project scope
A ____ is a condition or capability that must be present in the finished product to satisfy a business need
Requirement
Why is the collect requirements (5.2) process completed before the define the scope process?
The collect requirements process transforms high level requirements into clear objectives required to define the scope if the project
What is the difference between requirements documentation and requirements traceability matrix?
The requirements doc serves to clearly define all potential project requirements needed for creating the scope baseline
The requirements traceability matrix organizes and presents the requirements in visual manner that links each requirements to the individual deliverables that satisfy it
A trained facilitator is often used in the _____ process to obtain requirements from stakeholders and others with expert judgment
collect requirements
What is the definition of an affinity diagram?
Classifies requirements into distinct groups for review and analysis
____ a model of the potential products and providing it for review can ne a fast and inexpensive method for obtaining feedback on requirements
Prototyping
A well defined scope statement creates clear boundaries, reducing ____
Scope creep
What is the project scope statement?
Detailed definition of the project and product scope, major deliverables, assumptions and constraints. The statement clearly defines what is and is not in the project scope
The documents compromise the scope baseline:
Scope statement
Work breakdown structure (WBS)
WBS dictionary
List the following processes in the order in which they should be completed:
- define activities
- plan schedule mgmt
- sequence activities
- develop schedule
- estimate activity durations
- plan schedule mgmt
- -define activities
- sequence activities
- estimate activity durations
- develop schedule
The _____ process describes the actions that deliver the deliverables created by the create WBS (5.4) process
Define activities
An ____ is a distance, scheduled portion of work to be performed
Activity
______ moves a successor LEFT (earlier); _____ moves a successor RIGHT (later)
Lead, Lag
______ are calculated in terms of the number of work periods to complete an activity
Duration estimates
Which of the following estimating techniques is less costly and time consuming, but also the least accurate ?
Analogous estimating
- analogous estimating uses historical data from similar projects to produce a grossvalue of estimate for a projects activity duration
Which of the following estimating techniques uses statistical or numerical relationship to calculate activity durations?
Parametric estimating
_______ estimating requires significant resources and time, but can be very accurate.
Bottoms-up analysis
- This technique aggregates estimates of individual lower-level activities
Which of the following estimating techniques uses the triangular distribution mathematical equation to incorporate risk and uncertainty into the estimate?
- bottom-up estimating
- parametric estimating
- three-point estimating
- analogous estimating
- three-point estimating
What’s the difference between contingency reserves and mgmt reserves?
Contingency reserves address know-unknowns ( ex: the PM expects rework but the exact amount is unknown
Mgmt reserve address unknown-unknowns (unforeseen work
When creating the cost baseline in the determine budget process, _____ reserves are included in the baseline, but ___ reserves are not included
Contingency reserves (included) Mgmt reserves (not icluded)
After the time, scope and cost baselines are defined within the project mgmt plan, all future changes can be made only through the ____ process
Perform integrated change control process (included in the monitoring and controlling process group)
List the following processes in the order in which they should be completed:
- identify risks
- plan risk mgmt
- perform qualitative risk analysis
- plan risk responses
- perform quantitative risk analysis
- plan risk mgmt
- identify risks
- perform qualitative risk analysis
- perform quantitative risk analysis
- plan risk responses
Which document visually translates the project deliverables into small manageable components?
Work breakdown structure (WBS)
What is the definition of a requirement?
A condition/capability that must be present in the finished product to satisfy a need
What is scope creep?
The expansion of project work beyond the project boundaries
What is the key output of the define the scope process?
Project scope statement
- Provides a detailed definition of the project and product scope, major deliverable, assumptions, and constraints
“work” refers to the deliverable produced, not the activities that produce the deliverables
True
- to dig a ditch, the work would be defined as the complete ditch, not the activities required to dig the ditch
Name the technique used to create the WBS by dividing the scope into progressively smaller, more manageable parts
Decomposition
Define a work package
the lowest level of the WBS. It is the smallest amount of work for which cost and duration can be estimated and managed
The schedule management processes in the planning process group progressively translate the ____ of the scope baseline into logically sequenced work schedule
Deliverables
What are 3 key outputs produced by the define the activities process
Activity list, activity attributes and milestone list
What is the definition of an activity?
A distinct schedule portion of work to be perfromed
_____ extend the description of activities in the activity list, providing details on the effort type and work location
Activity attributes
- evolve and deepen in description as the project progresses
The _____ document frames the schedule constraints impacting the project
Milestone list
- created as an output of the define the activities process. The defined milestones identify significant points/events that are used in creating the detailed schedule
The ____ process aims to organize the activities into a schedule network diagram that graphically shows the order in which work will be completed
Sequence activities
What is the key output produced by the sequence activities process?
Project schedule network diagram
- shows the logical relationships of all activities start to finish
The ____ process brings depth and perspective to the network diagram by defining the amount of effort and resources each activity demands
Estimate activity durations
The ____ is the approved version of the schedule model used to evaluate actual vs planned progress throughout the project
Schedule baseline
All project baselines must be approved by the project sponsor
True
What is the difference between crashing activities and fast tracking activities?
Crashing: refers to the addition of resources to reduce the time required to complete an activity
Fast tracking: refers to the reorganization of sequential activates into parallel activities to reduce the time required to complete the activities
What is the largest negative impact of crashing that must be evaluated and accounted for?
Additional cost (more resources)
The ____ explains the logic behind each cost estimate, allowing the team to understand how the costs were derived
Basis of estimates
The determine budget process creates the project’s budget and baseline by ____ the cost estimates into time-phased view
Aggregating
The project budget and cost baseline are different
True
- project budget includes the mgmt reserve; the cost baseline doesn’t
Which type of reserve accounts for identified risks?
Contingency reserve accounts for identified risks. In comparison, the mgmt reserve accounts for unplanned work
The cost of preventing mistakes is _____ than the cost of correcting mistakes found by inspection or use
Less
The ____ describes the activities and resources necessary for the project team to achieve the project’s quality objectives
Quality mgmt plan
- also defines procedures for addressing nonconformance, corrective actions and continuous improvement
What two components comprise the cost of quality?
Cost of conformance and nonconformance
The cost of conformance includes what two types of costs?
Prevention and appraisal costs
- prevention are those associated with building quality into a products (training, equipment)
- appraisal are those associated with assessing the quality (testing, destructive testing loss, inspection)
The cost of quality (COQ) only considers the cost incurred while completing the project’s physical work
False
- includes all quality-related costs over the entire life of the project
What is the difference between project charter and team charter
The project charter is the foundational doc that authorizes the existence of the project
the team charter defines the team’s agreed upon operating guidelines
The ____ organizes the resource estimates into hierarchical chart that can be used to help acquire and monitor resources
Resource breakdown structure
Throughout the resource estimating process, various options must be evaluated to determine the optimal resource solution given the project’s constraints. Which data analysis technique does this describe?
Alternative analysis
Define the steps in a basic sender-receiver communications model
Encode, transmit, decode
Name the 3 most common communication methods
Interactive: multidirectional communication
Push: sent to specific recipients, but no confirmation that the info is understood
Pull: allows content access at the user’s own discretion
____ is anything compromising the understanding of a communicated message
Noise
- caused by a receiver being distracted or lacking adequate perception and/or knowledge
What is the equation for calculating communication channels?
Communication channels = N x (N - 1) / 2
N= # of stakeholders
List the following processes in the order in which they should be completed:
- plan risk mgmt
- plan risk responses
- perform qualitative risk analysis
- identify risks
- perform quantitative risk analysis
- plan risk mgmt
- identify risks
- perform qualitative risk analysis
- perform quantitative risk analysis
- plan risk responses
Which document is created during the identify risks process to record specific details on every individual project risk
Risk register
- a key output of the identify risk process
What are the two key outputs of the identify risk process?
Risk register and risk report
Once created, the risk register and risk report are not adjusted. True or false?
False
- continually adjusted to deepen the understanding of the current risk profile and to include addl risks identified
What factors are used to evaluate each risk on the risk register during the qualitative risk analysis process?
Perception of probability of occurrence and impact
- qual risk analysis is subjective, as it based on perception of each risk’s probability of occurrence and impact
An S-curve is produced by which type of risk analysis
Monte carlo analysis
- the S-curve from a monte carlo risk analysis visually shows the probability of achieving any project outcome
What is the purpose of a tornado diagram?
Used in quantitative risk analysis determines which individual risk has the greatest potential impact by correlating variation in project outcomes
Which analysis method is used to select the best of several alternative course of action?
Decision tree analysis
- a mathematical method in which alternate decision paths are shown and evaluated for their overall expected monetary value. The net path value is calculated for each and the decision path with the best value is selected
Which of the following is not a desired characteristic of a proper risk response plan?
- appropriate
- cost effective
- timely
- realistic
Timely
What are the five alternative risk strategies that must be considered when planning for threats?
- escalate, avoid, transfer, mitigate, accept
Which output produced in the plan procurements mgmt process defies the procurement need in detail sufficient to allow the sellers to assess if they are capable of providing the work?
Procurement statement of work
Which type of contract is used when the scope of work is expected to change significantly during the proect?
Cost-reimbursable contract
- seller is reimbursed for all allowable costs (per contract)
Which docs produced as outputs of the plan procurement mgmt. process must not be provided to the potential sellers?
Source selection criteria: objective to eval each proposal
independent cost estimates: frame of reference for eval bids
The stakeholder engagement matrix is used to compare which two levels of stakeholder engagement
Current vs desired enagagement
EXCUTING SECTION
The direct and manage project work process ensures both the planned project and ____ are executed
Approved change requests
- both planned project work and approved change requests are inputs to the direct and manage project work process
The deliverables produced by the direct and manage project work process are evaluated to conform they meet quality standards during which process?
Control quality
The direct and manage project work process is where the “rubber meets the road” as the team executes ____ defined in the project plans
planned project activites
What are the raw observations/measurements produced as an output of the direct and manage work process??
Work performance data
- passed onto the processes in the monitor and control process group for analysis. Through analysis, the data are converted into work performance info
When a change request is approved in the perform integrated change control process, it flows back to the ____ process as an output
direct and manage project work
Which output doc should the project team use to record problems, gaps, inconsistencies, and conflicts that occur during the direct and manage project work process?
Issue log
Throughout the entire project, both best practices and problems must be codified and recorded on the ____
Lessons learned register
The ____ process translates the quality mgmt plan into executable activates that integrate quality policies into the project
Manage quality process
What data representation technique used in the manage quality process breaks down the causes of a problem and organizes them into discrete branches, allowing root cause identification?
- flow chart
- cause and effect diagram
- affinity chart
- scatter diagram
cause and effect diagram
- also known as the fishbone or ishikawa diagram
The scatter diagram graphically shows the relationship between two variables. True or false?
True
- tool and technique used in the manage quality process that graphically shows the relationship between two variables
What is the term used to describe a set of structured observation techniques used to determine if project activities comply with policies, processes and procedures?
Quality audit
What is the key objective of the 3 resource mgmt processes in the executing process group?
Obtain, develop and manage a team. resources and procurements to complete all the project work
Explain what the resource calendar does?
Defines the exact time frames when each project resource is available to the project
Does a weak-matrix or strong-matrix organizational structure offer project managers less access/control of resources?
Weak-matrix
- closer to the projectized structure. Therefore the project mgr has less authority to control resources
Which mgmt plan instructs the way in which external resources are obtained?
Procurement mgmt plan
- instructs the way in which internal resources are obtained and the procurement mgmt plan instructs how to obtain external resources
____ decision tools allow the project team to evaluate resource options and select the optimal mix to meet the project’s needs
Multicriteria
In order, name the five stakes of the Tuckman ladder, which is used to evaluate the team development
Forming, storming, norming, performing, adjourning
Which key output produced by the develop team process allows the current status of team development to be addressed and tracked?
Team performance assessments
The team’s overall performance can be improved through which 4 actions?
Training, coaching, mentoring, change requests
The ___ defines in clear terms the team’s value and operating guidelines
Team charter
- input to the 9.4 develop team process
___ is the ability to identify, assess and manage emotions of oneself, others and groups
Emotional intelligence
Name the 5 conflict resolution techniques identified in the manage team process
Withdraw/avoid smooth/accommodate compromise/reconcile force/direct collaborate/problem solve
In which conflict resolution technique does the project manager retreat from the conflict?
Withdraw/avoid
- may cause an issue to worsen if the issue is not rectified
By leveraging which conflict resolution technique would you push your viewpoint through power, often creating a win-lose situation?
Force/direct
Name the conflict resolution technique aimed at creating a win-win situation where both parties viewpoints are shared and incorporated
Collaborate/problem solve
What is the potential downside of using the smooth/accommodate conflict resolution technique?
Risk of the issues not being adequately addressed
- smooth/accommodate involves emphasizing agreement while ignoring/conceding differences in hopes of maintaining harmony
The manage communication process is conducted only once. True or false?
False
- is an iterative process that is constantly collecting, evaluating, storing and distributing info from updates, issues, and changes of other processes
The ____ is the software by which project information is distributed
Project mgmt information system (PMIS)
What are the key objectives of the implement risk responses process?
To minimize a project’s risk exposure and maximize opps by implementing agreed-upon risk response plans
What is the name of the individual responsible for ensuring the risk response plans for a specific risk are fully implemented?
Risk owner
During which process is the final agreement and contract with a seller completed?
Conduct procurements
What types of meeting is used to provide prospective contractors the oppty to gain a deeper understanding of the procurement statement of work?
Bidder conference
Which of the following is not a characteristic of a bidder conference?
- defined meeting to provide detailed info
- allows all sellers the oppty to ask questions
- each seller can only hear the responses to their questions
- NDAs are often required
- each seller can only hear the responses to their questions
What is the term for a potential list of sellers within a competitive range?
Select sellers
The person authorized to sign legal agreements is often a purchasing or legal rep, not the project mgr
True
Which of the following docs are not provided to potential contractors?
- source selection criteria
- RFP
- procurement SOW
- source selection criteria
The manage stakeholder engagement and ____ processes work in concert, each focuses effort on aligning stakeholders and assisting in better decision making
Manage communications
- these two work together to achieve a similar goal of ensuring constant and appropriate flow of info to and from stakeholders
Which doc is most likely used to record problems and concerns with project communications effort?
- issue log
- assumptions log
- stakeholder register
- communications mgmt plan
issue log
- both an input and output of the manage stakeholder engagement process
MONITORING AND CONTROLLING SECTION
Which of the following is not an objective of the monitoring and controlling process group?
- track, review and regulate project progress and performance
- identify areas in which changes to the plans are required and initiate change requests where needed
- objectively evaluate and formally accept project deliverables
- deliver project deliverable, once completed, to the customer
deliver project deliverable, once completed, to the customer
- this is in the close project or phase process
Which of the following is not produced during the monitoring and controlling process group?
- work performance data
- work performance info
- work performance reports
- schedule and costs forecasts
work performance data
- performed during the executing process group by direct and mamage project work process
The monitor and control project work process provides insight into the health of a project by tracking, reviewing and reporting on actual vs expected progress. True or false?
True
- to maintain a clear understanding of how the project is progressing against the project baseline and project plans
Which doc, produced as a key output of the monitor and control project work process, summarizes project performance and forecasts?
Work performance reports
- summarize work perf info concisely and are critical to keep stakeholders aware of the project’s progress and to generate decisions or actions
____ are submitted to correct current and potential project performance issues
Change requests
How are work performance date translated into work performance info?
Data analysis
- one of the primary activities that occur in the monitor/control process group
What is the desired impact of the work performance reports generated as an output of the monitor and control project work process?
Maintain stakeholder awareness and generate decision or actions
Which type of analysis identifies the difference between planned and performance and actual performance?
Variance analysis
- key tool and technique used during the M/C project work process to determine the condition of the project
Any change request that potentially impacts a project baseline must be evaluated using the formal ____ process
Perform integrated change control
Change requests can only be implemented after they are transformed into ___
Approved change requests
____ is the process of obtaining the customer’s formal acceptance of completed project deliverables
Validate scope
- to obtain the customer’s formal acceptance of the completed project deliverables
The verified deliverables that are produced as outputs by the ____ process are the main inputs leverage by the validate the scope process
Control quality
- are what ar evaluated for formal customer acceptance in the validate scope progress
____ is the formal document signifying that the customer has accepted a deliverable as complete and satisfactory
Accepted deliverable
Which document produced in the planning process group links the project requirements to the deliverables that satisfy them?
Requirements traceability matrix
is produced in the collect requirements process visually displays the deliverables that must be satisfied
Which analysis technique used during the control scope process determines if project performance is improving or deteriorating by examining historical results?
Trend analysis
How does the variance analysis work and what type of actions could it facilitate?
Compares the baseline to the actual results . If the variance exceeds a threshold, then corrective or preventative action may be developed. If the actions impact the baseline, then a change request will be generated
The control scope process is conducted throughout the lie of the project? True or false?
True
- after scope baseline is defined, the control scope process must be conducted throughout the entire project. Essential as it helps monitor the success of the project and prevention of scope creep
How do schedule variance (SV) and schedule performance (SPI) differ when analyzing a project’s performance?
SV defines the amount a project is ahead/behind the schedule baseline
SPI defines hw efficiently the team is completing the work
By which standard is the actual schedule performance evaluated during the control schedule process?
Schedule baseline
- is the standard by which schedule progress is evaled during the control schedule process
The control costs process centers on understanding both the total amount spent and the ___ of the money spent to complete project activities
Effectiveness
- analysis conducted during the control cost process determines the effectiveness of the money spent on a project by analyzing the total amount spent and value generated from the spend
Which variable defines the total budget amount allocated for the project?
Budget at completion (BAC)
Planned value (PV) defines the value of work that_____ done
should be
- PV defines the vale of the work that should be done and is the standard by which progress will be measured
Earned value (EV) defines the value of the work that ____ done
Is
- EV defines the value that is done. This is often used toc calculate the projects completion %
Scheduled variance (SV) determines the amount a project is ahead/behind the schedule baseline. What does a negative schedule baseline indicate?
Project is behind schedule
- a negative SV behind, positive is ahead
At the completion of a project, what will the SV be?
Zero
- SV will always be 0 at end because all of the work planned is complete
Your project team has been more efficient that originally projected in completing project work. what would you expect the SPI value to be?
Above 1
- SPI values above 1 indicate that more work has been completed than planned at the period of time (indicating that the team has been more efficient than expected)
The ____ variable determines if the project is ahead or behind the budget defined in the cost baseline
Cost variance (CV) - determines the amount of a budget deficit or surplus at a given time
Which EVM variable calculates the expected total cost of the project at the completion of all project work?
Estimate at completion (EAC)
- determines the expected total cost at the completion of all project work
The estimate to complete (ETC) calculates the expected cost to finish all the remaining project work. True or false?
True
ETC = EAC - AC
The ____ variable determines the CPI that must be achieved with the remaining resources to meet a specific mgmt goal
To-complete performance index (TCPI)
- evals the current performance and determines the CPI rate that must be maintained to hit a defined mgmt goal. Two equations exist to calculate the TCPI to meet the mgmt goals of BAC or EAC
Is a TCPI above or below 1 more difficult to complete?
Above 1
- values above 1 are more difficult to meet because the team must perform at a level more efficient than originally planned in the project cost baseline
Deos earned value mgmt (EVM) confuse or scare you?
Check out course EVM Made Easy
What is the purpose of the control quality process?
to ensure project outputs are complete, correct, and satisfactory to customers by monitoring and recording quality results
Control quality determines if the project outputs do what they were intended to do. True or false?
True
Which data gathering technique uses a smaller sample to measure quality and infer the total quality of a larger population?
Statistical sampling
Name the simple, yet powerful, date gathering technique used to gather attribute date while performing inspections
Check sheets
When a quality issue is identified, which type of data analysis technique is often leveraged to investigate the case?
Root cause analysis
- aims to ID the core problem driving an issue so that it can be eliminated
The team has used a chart to determine whether or not a process is stable. Which chart have they leveraged?
Control chart
What is the goal of the control resources process?
Right resources, right place, right time
Which project document shows when resources are available to the project?
Resources calendar
Define the purpose of the monitor communications process
Provides a realistic eval of the success of actual communication and quickly initiates changes to improve results when needed
What are 4 ways in which the team achieves the goal of ensuring each stakeholders communications needs are met?
- monitoring the actual comms
- evaluating the effectiveness
- understanding changes on stakeholders needs
- triggering changes to the comms plan
The ____ matrix provides the desired stakeholders engagement level that the communications mgmt plan was designed to achieve
Stakeholder engagement matrix
Which of the following is not one of the key objectives of monitor risk response?
- monitor the implementations of risk response plans
- track identified risks
- identify and analyze new risks
- assign individuals to implement new corrective actions to eliminate new risks identified
- assign individuals to implement new corrective actions to eliminate new risks
___ is the term that describes the approaches and contingencies that project mgmrs build into their risk processes
Project resilience
The control procurements process focuses on all of the following except:
- establishing contracts with buyers
- ensuring that both parties meet contractual obligations
- confirming that the appropriate buyer [arties approve deliverables
- resolving all conflicts in a positive manner
establishing contracts with buyers
- control procurements process evals contract progress and results and manages the procurement relationship to improve the likelihood of project success
When conflicts/issues occur on the fulfillment of a contract, what is the most optimal method of action?
Negotiations
If negotiations are unable to rectify contractual issues, what method should be leveraged?
Alternative dispute resolution (ADR)
What are the key outputs of the control procurement process?
close procurements, work performance information, change requests, document updates
As a project evolves, it is often necessary to modify the methods used to engage stakeholders. True or false?
True
The monitor stakeholder engagement process aims to ___ and ___ engagement activities as the project evolves
adapt and improve
____ involves listening and then using your words to clarify and confirm the message that was heard
Active listening
CLOSING SECTION
Define the key objectives of the Close Project or Phase process
- finalize all activities of the project phases or contract
- archive all project or phase info
- formally close the project, phase or contract
- release all or team resources
In executing te close project process, you have created a final project report, transferred the final product to the ownership of the customer, and dismissed your project team. You believe that you can now formally close the project. What activity have you forgotten to complete?
- obtain approval from the project sponsor
- formally acknowledge the success of the team
- complete and archive the lessons learned register and all project docs
- close the charter document
complete and archive the lessons learned register and all project docs
In closing the project, the project mgr reviews the ____ to ensure that all project work is complete and the project has met its objectives
Project mgmt plans
While developing the final report for formal project closure. you utilize which project doc to demonstrate compliance with the project scope?
Requirements documentation
- created during the collect requirements process describes how individual requirements meet the business need for the project
Due to a company reorg, the project sponsor was recently terminated and the project was canceled. What action should the project mgr take first upon being informed this?
Conduct Lessons learned
- regardless of whether a project is completed fully or terminated before completion. lessons learned must be ca[tured and recorded. These lessons learned help to inform future projects
The Close Project or phase process is the ____ finalization of all process and process groups
Forma finalization
Which 3 outputs must be completed before a project is properly closed?
- final product, service, or results transferred to customer
- project docs updates and marked as final
- final report created
Of the 4 data analysis techniques used in the close project or phase process, which technique is focused on identifying learned and knowledge sharing opps to help improve future projects? - document analysis - regression analysis trend analysis - variance analysis
Document analysis
- technique that helps identify lessons learned for future projects
When using ____ ; the interrelationships between project variables are analyzed to identify opps to improve the performance of future projects
Regression analysis
You inform your team that a critical output of the close project process is the completion and archival of the lessons learned register. What is the main reason why ensuring that the register is updated and archived?
To identify and make easily available improvement ideas that can be used on comparable projects
After all project work is complete, it is proper to release all team members
False
- not unit project closure is over
What is the purpose of the final report and what does it contain?
Summarizes the project performance elements such as benefit, cost, quality, schedule. Should follow communication plan to ensure proper dissemination is achieved. Delivered to project sponsor and stakeholders
AGILE PROJECT MGMT SECTION
Who is responsible for the business decisions and maximizing the value of the product?
Product owner
What are the characteristics of those who make up the team in agile?
- self organized
- cross functional
- build or maintain the product
What are the roles of the facilitator in an agile environment?
- facilitator of processes
- coach
- conscience
- defender
The scrum master (facilitator) tells the team how to do the work. True or false?
False
Who owns the product backlog?
Product owner
What is the difference between sprint backlog and product backlog?
Sprint: what the team will work to complete in the current sprint
Product: the queue of work to be completed for the overall project
Something that provides customer value, functionality, and is tested and accepted while only being a smaller subset of the total project outcome is defined as:
An increment
What are artifacts of agile?
- product backlog
- sprint backlog
- increment
Define the “time boxed” and advise what is the most common time box for a sprint
- time boxed: there is a predetermined and defined length
- most common length of a sprint is 2 weeks
When does the sprint planning take place?
At the beginning of the sprint
Who determines what is put onto the sprint backlog during sprint planning?
Product owner and the team collaborate to determine what items to pull into the sprint to maximize value creation
How long is the daily stand up?
15 min
What is another term for sprint review?
Demo
What is the difference between a sprint review and a sprint retrospective?
Sprint review: focuses on inspection of the product, getting customer feedback, and gaining a better understanding of what the customer needs
Sprint retrospective: focuses on processes and product devt to look at what went well, what did not, and how it can be improved in the next sprint
Sprint planning is used on the ____. All sprint planning should start with a _____
Product backlog, blank slate
During sprint planning the product owner asks them to “consider” items and then the team comes up with how to complete them
True
The purpose of collaborative sprint planning is to produce _____
optimal value creation
What should be communicated during a daily scrum/stand up?
- what works was communicated yesterday
- what issues were experienced
- what will be completed today
What is the purpose of the daily scrum/stand up?
- achieve fast cycles of learning
get a better plan to deliver the value
What is the purpose of a sprint review (demo)?
- determine is the product meets the customer needs
- determine if the product is for for purpose
- give the team learning feedback and update the product backlog
What is the purpose of a sprint retrospective?
- for the team to determine what they can do better next time
- not about blame but about finding root causes and planning action items
Describe the planning process in an agile life cycle
Team plans and replans as more info becomes available from the review from frequent deliveries
What are the two types of agile life cycles?
- iteration based agile
- flow based agile
A team works in timeboxes of equal duration. Is this iteration base agile or flow based agile?
iteration based
A team pulls from the backlog based on its capacity to start work. Is this iteration base agile or flow based agile?
Flow based
A team works on features in order of importance. Is this iteration base agile or flow based agile?
iteration bases
The team and business stakeholders determine the most appropriate schedule for planning, product reviews and retrospectives. If this iteration base agile or flow based agile?
Flow based
A project that uses some agile approaches like short iterations, daily stand ups, and retrospectives but also uses upfront estimation work assignment, and progress tracking is considered:
- agile
- hybrid
- predictive
- none
hybrid
Agile is about ____ delivery on a frequent basis. That delivery creates ____ for the team
- customer bases
- feedback
A ____ helps teams to visualize the flow of work, make impediments easily visible, and allow flow to be managed by adjustingwork in process limits
kanban board
AGILE MANIFESTO SECTION
What are the 4 values of the agile manifesto?
- individuals and interactions over processes and tools
- working software over comprehensive documentation
- customer collaboration over contract negotiation
- responding to change over following a plan
What is the highest priority in agile?
Satisfy the customer through early and continuous delivery of valuable software
What do agile processes harness for the customer’s competitive advantage?
Change
Agile prefers delivering software in a couple months vs a couple weeks
False
- deliver SW frequently, from a couple weeks to a couple months, with a preference for shorter timescale
Based on the principles of agile, who must work together daily throughout the project?
Business professionals and developers
In agile, we build projects around motivated individuals and give them the environment, support and trust they need to get the job done
True
- 5th principle of agile manifesto
What is the most efficient method of conveying info to/within a devt team?
Face to face
What is the primary measure of progress based on agile principles?
Working software
In agile principles what do they mean by sustainable devt?
Sponsor, developers and users should be able to maintain a consistent pace indefinitely
You are in the process of collecting and disseminating performance information to the stakeholders in the project. You want to predict the future performance of the project based on the current information. This performance information includes status reports, current status of risks, and summary of changes approved in the period. Which of the following methods will help you in predicting the future performance of the project?
- forecasts
- run chart
- WBS
- pareto chart
Forecasts
Forecasts are estimates or predictions of conditions and events in the project’s future based on information and knowledge available at the time of the forecast. [PMBOK® Guide 7th edition, Page 104] (Domain: Process, Task 5)
Based on agile principles, what enhances agility?
Continuous attention to technical excellence and good design
In agile, simplicity, the art of maximizing the work left to do is essential
False
- simplicity is the art of maximizing the amount of work to be done
Where do the best architecture reqs and designs come from in agile?
self-organizing teams
Based on agile principles, at regular intervals the team reflects on how to become more effective. The team then tunes and adjusts behaviors. True or false?
True
According to the 12 principles of the agile manifesto, a team should value ____ and ____ delivery to satisfy the customer
Early and continuous
Why, according to the 12 principles of the agile manifesto, should a team welcome change?
Agile processes harness change for the customer’s competitive advantage
According to the 12 principles of the agile manifesto, describe the desired timescales
Deliver working products frequently, from a couple of weeks to a couple of months, with a preference to the shorter timescale
Business people and developers must work together daily throughout the project
True
Those on agile team should possess what characteristics?
Build projects around motivated individuals while providing an environment, support system, and trust system they need to complete the job
What is the most efficient and effective method of communicating info to/within a team?
Fact to fce
What is the primary measure of progress?
A working product
Describe the type of devy that an agile environment should promote
Sustainable devt.
SERVANT LEADERSHIP SECTION
What do servant leaders promote?
- Self awareness
- environment of safety, respect and trust
- service to others
What do servant leaders have to do day-to-day?
Facilitate and collaborate, facilitating collaboration
How do servant leaders help streamline efforts?
By identifying and removing obstacles for the team
Servant leaders_____ an environment for team’s success
Create
What characteristics should servant leaders value?
Self-awareness, safety, respect, trust, and service to others
Servant leader should help the people on their team grow by: ____, _____, and _____.
Listening, coaching and facilitating
As a servant leader you want to approach project work in a specific order; purpose, _____ and then process
People
Servant leaders manage _____ to build communication and coordination with the team
Relationships
When project managers act as servant leaders, the emphasis shifts from ____ to ____
Managing coordination to facilitating collaboration
As a servant leader of an agile team, you are responsible for helping to streamline processes that are impeding a team’s ability to do work. True or false?
True
THE AGILE UMBRELLA SECTION
Name the agile framework for developing and sustaining complex products, with specific rules, events and artifacts
Scrum
Describe the difference between behavior driven devt (BBD) and eXtreme programming (XP)
BBD: a system of design and validation that uses test first principles and English like scripts
XP: A SW build technique based on frequent cycles. XP is most known for popularizing a comprehensive set of practices intended to improve the results of SW projects
What are crystal methods?
A family of methodologies that are designed to scale and provide a selection of methodology rigor based on project size and criticality
Scrumban is an agile approach originally designed to go from _____ to _____
Scrum to kanban (evolved into a hybrid framework)
Feature driven devt (FDD) was developed to meet what size of SW devt project?
Large
What are the 6 primary roles in FDD?
- PM
- chief architect
- devt mgr
- chief programmer
- class owner
- domain expert
Dynamic systems devt method is designed to add more ____ to existing iterative methods
Rigor
This agile process features more accelerated cycles and less heavyweight processes
Agile unified process
When would you need to uses scrum of scrums?
When two or more scrum teams consisting of three to nine member need to coordinate their work
What does the scaled agile framework do?
Focuses on providing a knowledge base of patterns for scaling devt work across all levels of the enterprise
What does large scale scrum (LeSS) accomplish?
Organizes multiple devt teams toward a common goal
Why would it make sense that a whole org, not a singular product team, use enterprise scrum?
A method that is used at the org level because it advises organizational leaders to extend the use of scrom across all aspects of the org
What are the principles of disciplined agile (DA)?
- people first
- learning oriented
- full delivery life cycle
- goal driven
- enterprise awareness
- scalable
What concepts exist under the agile umbrella?
- scrum and BDD
- XP and FDD
- crystal and XP
- kanban and DSDM
- all
All
UNDERSTANDING AGILE TEAM ROLES SECTION
In agile, 3 common roles are:
- cross functional team member
- product owner
- team facilitator
Describe a cross functional team member
Team member with the necessary skills to produce a working product. They produce a potentially releasable product consistently and in the shortest amount of time with high quality
Describe a product owner
Responsible for guiding the directiona product goes- rank the work based off the business value
Describe a team facilitator
Servent leader of the team. Also called the product mgr, srum master, team lead, coach, etc.
Describe a T-shaped person
One area of deep expertise and a broad ability in the remaining skills required by the team
A product owner is a committee responsible for maximizing the value of a product
False
How long is the product owner responsible for the product?
Entire life cycle
What is the product owner’s ability ultimate responsibility?
Guiding the direction of the product to deliver max value
The product owner ______ the work based on its _____
Ranks, business value
The product owner owns, maintains, and organizes the ____ to help the team see how to deliver the highest value without creating waste
Product backlog
AGILE TEAM EXPLAINED SECTION
What are two key features of agile teams?
Cross-functional and self-managing
Team members may change as the project progresses
True
What is the definition of colocation?
An organizational placement strategy where the project team members are physically located close to one another in order to improve communication, working, relationship nd productivity
What does it mean when team are self-managing?
Team decides what work they are pulling into the print and decides on the right team members at the right time to complete it
Agile teams focus on ____ product development so they can obtain ____
rapid, feedback
What are the 5 attributes of successful agile teams?
- dedicated people
- cross functional
- colocation or ability to manage location challenges
- mixed team of generalists and specialists
- stable work env
A servant leader’s role is to do whatever the team asks them
False
SCRUM MASTER EXPLAINED SECTION
How does the scrum master serve the team?
- improv team mgmt
- encourage cross-functionality
- keep team focused on increments that meet the definition of done
- facilitate impediment removal
- ensure agile/scrum events take place and are proper
How does the scrum master serve the product owner?
- help find techniques for product goal and backlog mgmt
- help team understand the need for clear concise product backlog
- help improve the product planning process
- encourage stakeholder collaboration
How does the scrum master serve the org?
- lead, train, coach in agile principles
- plan and advise on agile implementation
- help employees understand and apply empirical approach to work
- remove barriers between stakeholders and the scrum team
A scrum master should ensure agile/scrum events take place and are proper. True or false?
True
A scrum master facilitates betweenwhat 3 entities?
- team
- prodcut owner
- org
AGILE ROLES 3 PERSPECTIVES SECTION
What is the difference between an I shaped persona nd a T shaped person in terms of skills?
I: has depth of skill but not a lot of breadth
T: defined specialization but has the skills, versatility and aptitude to help other people when necessary
A person who multitasks between 2 projects equally will give 50% effort on each project. True or false?
False
- due to the cost of task switching, they will end up giving 20%-40% on each project
In an agile environment, the team is focused on the ___
Work
In an agile environment, the product owner is focused on the overall ___ lifecycke
Product
AGILE PROJECT CHARTER SECTION
What is the purpose of an agile project charter?
To align the team to a common understanding
What are the two types of charters in agiile?
Project charter and team charter
In an agile project charter where does it answer the question of “why” we are doing this project?
Project vision
What is the social contract of how the team will work together in accomplishment of the overall team goals?
Team charter
What are the 4 components of a team charter?
- team values
- working agreements
- ground rules
- grou norms
Meeting times and standards are an example of what component of the team charter?
group norms
What are some examples of working agreements in a team charter?
What “ready” means
WIP standards
Sustainable pace and core hours are examples of what component of a team charter?
Team values
What is the project release criteria?
What being “done” looks like
At minimum, an agile project charter answers the following 4 questions:
- Why we are doing this project? )vision)
- Who benefits and how? (vision / purpose)
- What does done mean for the project? (release criteria)
- How are we going to work together? (intended flow of work)
PRODUCT BACKLOG PREP SECTION
The product backlog is a static fully detailed list of all the high-level features that will be included in the product. True or false?
False
- list is how the owner sees it today
User stories on the backlog need to be detailed enough for the team do do what?
Understand, estimate and complete them (through further convos)
What is the product backlog?
An ordered list of high level features as the product owner sees it today in user story format
It is detailed enough for the team to understand, estimate and complete
What is a product roadmap and who typically produces it?
The anticipated sequence of deliverable and is typically created by product owner
What is the purpose of backlog refinement meetings?
To refine enough stories so that the team understand them and how they relate to each other
From a high-level, explain how the scope is developed differently in an agile environment than in predictive
Agile: spends less time definitively defining the complete scope at the beginning of the project. It instead focuses on the plan and process for its ongoing discovery and refinement
TEST PREP / RESEARCH
USER STORIES SECTION
What are the 3 C’s of a user story?
- card, conversation, confirmation
What is a user story?
A brief description of deliverable value for a specific user. It is a promise for a convo to clarify details
What is the “conversation” in regards to user stories?
The second C of user stories is the details that come out via discussion with the product owner, it helps to get a deeper understanding. It is used for the cards at the top of the product log
When we are talking about acceptance criteria in user stories, which C are we talking about?
Confirmation
- expectations of “done” from product owner
How are user stories structured?
As a ______ (user(who)), I want to be _____ (value(what)), so that I can _____ (reason(why))
We take every user story as soon its created and we immediately add in depth details to fully understand and plan fo all the product requirements. True or false?
False
- we only get details with follow up questions when needed. Don’t want to waste time so focus on the user stories of highest value
PRODUCT BACKLOG REFINEMENT SECTION
Why do we rank and refine user stories during backlog refinement?
So that the most important work is visible and ready to work in the next iteration
How do we evaluate each card in the backlog refinement?
Having focused discussion between the Product owner, team and SMEs to understand what the intention is, the potential challenges, the dependencies, and create an estimate in relation to the other cards
Backlog refinement is continual. True or false?
True
- looking for of most value. ones with higher priority have more refinement
What is the length of a backlog refinement meeting in and iteration based agile project?
2-3 hrs
What do refinement discussion drive?
Understanding
Where do we use the acceptance criteria in the refinement discussion?
Becomes the product owner’s script for the product demo/review
SPRINT PLANNING AND BACKLOG SECTION
What initiates the sprint?
Sprint planning, where we select the work to be performed in the sprint
The product owner decides what work will be performed in the print. True or false?
False
- team and product owner
How long is a sprint planning meeting for a two week sprint?
2 week iteration it would be a focused four hour time boxed meeting
What is the key thing to discuss in a sprint planning meeting?
The most important backlog items and how they map to product goals
What are the 3 main topics discussed in a sprint planning?
- why is this print valuable?
- what can be done in this sprint?
- how will chosen work get done?
In iteration-based agile, when teams gave reduced capacity they only plan for work that meets that capacity. True or false?
True
- teams estimate what they can complete. They cannot be 100% sure what they can deliver since they don’t know the unexpected. Smaller stories allows team to see progress in the form of a finished product and they learn what they will be able to accomplish in the future
DAILY STAND UPS SECTION
A daily stand up is just a daily status meeting
False
-a synchronization meeting that helps work through flow and get our print goal
What is the purpose of a daily stand up?
To commit to each other, uncover problems, and ensure work flows smoothly through the team
A daily stand should be no longer than ___ minutes
15 min
In an iteration-based agile daily stand up, what 3 questions does everyone answer in the round robin fashion?
- What did I complete since the last stand up?
- what am I planning to complete between now and the next stand up?
- What are my impediments (risks/problems)?
Flow based agile has a different approach to stand up. Explain the difference between a daily stand up in flow vs iteration based agile
Flow: focuses on the team’s throughput. the team assesses the board from left to right
- what do we need to do to advance this piece of work?
- is anyone working on something that is not on the board?
- what do we need to finish as a team?
- are there any bottlenecks or blockers to the flow of work?
KANBAN BOARD SECTION
What is a Kanban board?
A visual board that helps make flow work
Why would we use a Kanban board in agile projects?
To limit WIP (work in progress) to align processes and to highlight bottlenecks
What are the 5 key elements of a kanban board?
Visual signals (user story cards), columns (make a workflow), commitment point, delivery point and WIP limits
How is the kanban board used?
Visualization tool that enables improvements to the flow of work by making bottlenecks and work quantitatives visible
DEMO/REVIEW SECTION
When are demos/reviews held?
At the end of every sprint (or when needed if you are in flow based agile)
Who attends the demo/review?
Scrum master, product owner, other stakeholders as needed
The demo/review is really a chance for the team and stakeholders to inspect and adapt the product. True or false?
True
As the team completes the features, usually in the form of user stories, the team periodically demonstrates the working product. The ____ sees the demonstration and accepts or declines the features/stories.
Product owner
When does a demonstration happen in flow-based agile?
When time to do so and when enough features have been completed to give an understanding of the product
As a general rule, demos should occur at least once every ____ weeks
2
RETROSPECTIVE SECTION
During which part of the sprint do we do the retrospective?
At the end of every sprint
How long is the max time allowed for a retrospective in a two week sprint?
One and a half hours
What is the goal of the retrospective?
Reflect on progress and improve- one-two improvements
A retrospective is about figuring who is to blame for issues that occurred during the sprint. True or false?
False
- not blame, improvement