PMP Prep Flashcards

1
Q

Budget at Completion (BAC)

A

Original budget of project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

PV

A

Planned Value
Amount of money worth of work that should have been done on the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

EV

A

Earned Value
Amount of money worth of work actually done

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

AC

A

Actual Cost
Amount of money already spent on the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CV

A

Cost Variance
Difference between work done and money spent. Negative values = bad

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

CPI

A

Cost Performance Index
Rate of how we are spending to actually earning. 1 and over is good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

SV

A

Schedule Variance
Difference between amount of work you should have done vs actually done. Negative value = bad

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

SPI

A

Schedule Performance Index
Rate of how we are meeting project schedule. 1 and over is good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

EAC

A

Estimate at Completion
Forecasting total cost of the project at the end based on current spending rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

ETC

A

Estimate to Completion
Forecasting the amount of money that will be needed to complete the project based on current performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

VAC

A

Variance at Completion
Difference between original budget and new forecasted budget. Negative = bad

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

TCPI

A

To-Complete Performance Index
Performance needed to finish the project within budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Process Groups

A

Initiating
Planning
Executing
Monitoring and Controlling
Closing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Knowledge Areas

A

Project Integration Management
Project Scope Management
Project Schedule Management
Project Cost Management
Project Quality Management
Project Resource Management
Project Communications Management
Project Risk Management
Project Procurement Management
Project Stakeholder Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Project Integration Management Processes

A

7
Develop Project Charter (i)
Develop Project Management Plan (p)
Direct and Manage Project Work (e)
Manage Project Knowledge (e)
Monitor and Control Project Work (mc)
Perform Integrated Change Control (mc)
Close project or Phase (c)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Project Scope Management Processes

A

6
Plan Scope Management (p)
Collect Requirements (p)
Define Scope (p)
Create WBS (p)
Validate Scope (mc)
Control Scope (mc)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Project Schedule Management Processes

A

6
Plan Schedule Management (p)
Define activities (p)
Sequence activities (p)
Estimate activity duration (p)
Develop schedule (p)
Control schedule (mc)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Project Cost Management Processes

A

4
Plan cost management (p)
Estimate costs (p)
Determine budget (p)
Control costs (mc)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Project Quality Management Processes

A

3
Plan quality management (p)
Manage Quality (e)
Control Quality (mc)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Project Resource Management Processes

A

6
Plan resource management (p)
Estimate activity resources (p)
Acquire resources (e)
Develop team (e)
Manage team (e)
Control resources (mc)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Project Communications Management Processes

A

3
Plan communications management (p)
Manage communications (e)
Monitor communications (mc)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Project Risk Management Processes

A

7
Plan risk management (p)
Identify risks (p)
Perform qualitative risk analysis (p)
Perform quantitative risk analysis (p)
Plan risk response (p)
Implement risk responses (e)
Monitor risks (mc)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Project Procurement Management Processes

A

3
Plan Procurement management (p)
Conduct procurements (e)
Control Procurements (mc)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Project Stakeholder Management Processes

A

Identify stakeholders (i)
Plan Stakeholder engagement (e)
Manage stakeholder engagement (e)
Monitor stakeholder engagement (mc)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Communication Channel Formula

A

N(N-1) / 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

PERT

A

Project evaluation and review technique - uses optimistic, pessimistic, and realistic values to get an estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

PERT Beta Formula (Regular PERT Formula)

A

(O + 4R + P) / 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Pert Standard Deviation Range Formula

A

(P - O) / 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Pert Triangle Distribution Formula

A

(O + R + P) / 3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Initiating Major Outputs

A

Project Charter
Assumption Log
Stakeholder Register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Major Components of Project Management Plan

A
  • Knowledge Areas management plans
  • Scope baseline
  • Schedule baseline
  • Cost baseline
  • Perf management baseline
  • Project life cycle description
  • Development approach
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Executing Major Outputs

A

Work performance data
Change request
Team performance assessments
Selected seller
Agreements
Issue log
Lessons learned register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Monitoring & Controlling Major Outputs

A

Accepted deliverables
Work performance information
Work performance reports
Approved change request

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Closing Major Outputs

A

Final product, service, or result transition
Final report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Schedule Management - Key Documents

A

Activity attributes
Activity list
Duration estimates
Milestone list
Project calendars
Project schedule
Project schedule network diagram
Schedule data
Schedule forecast

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

Integration Management - Key Documents

A

Assumption log
Change log
Issue log
Lessons learned register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Cost Management - Key Documents

A

Basis of Estimates
Cost estimates
Cost forecast

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

Resource Management - Key Documents

A

Physical resource assignemnts
Project team assignments
Resource breakdown structure
Resource calendars
Resource requirements
Team charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

Communications Management - Key Documents

A

Project communications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

Scope Management - Key Documents

A

Project scope statement
Requirements documentation
Requirements traceability matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

Quality Management - Key Documents

A

Quality control measurements
Quality metrics
Quality report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

Risk Management - Key Documents

A

Risk register
Risk report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

Stakeholder Management - Key Documents

A

Stakeholder register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

PMO Organizational Structures

A

From lax to strict
Supporting
Controlling
Directive

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

Supporting PMO Org Structure

A

Supports PjM
Provides templates, training, lessons

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

Controlling PMO Org Structure

A

Determines framework/methodology & use of forms

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

Directive PMO Org Structure

A

Controls project and assignments, project managers report to the PMO

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

Organizational Structures

A

Functional
Matrix (weak, balanced, strong) - applies to PjM and PMO as a whole
Project Oriented Organizations (Projectized)
Hybrid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

Functional Organizational Structure

A

Team members report to their dept managers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

Matrix Organizational Structure

A

Weak: Functional > PjM
Balanced: Functional = PjM - likely scenario on exam
Strong: Functional < PjM - likely scenario on exam

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

Project Oriented Organizations Organizational Structure

A

Project manager has ultimate power

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

Hybrid Organizational Structure

A

A combination of multiple individuals having the power

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

Types of Project Managers

A

From strongest to weakest:
Project Manager
Project Coordinator
Project Expeditor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

Organization Process Assets (OPAs)

A

Process documents policies, tools, knowledge base

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

Enterprise Environmental Factors (EEFs)

A

Impacts projects or organization positively or negatively, and can be internal or external

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

Leadership Styles

A

Laissez-Faire
Transactional - focused on goals
Servant Leader
Transformational - empowering
Charismatic
Interactional - combination

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

Forms of Power

A

Reward
Expert
Legitimate - given power/position
Referent - Respected/charisma
Punishment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

Project Selection Methods

A

Benefit / Cost Ratio
Economic Value Add
Internal Rate of Return
Opportunity Cost
Payback period
Present value
Net Present Value
Return on Investment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

Perform Integrated Change Control

A

Integration management and Monitoring & Controlling process that consists of reviewing, approving, managing changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

When are control processes executed vs validating?

A

Control: Throughout the process
Validating: At the end

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

Critical Path Method

A

Visual way to show how multiple, dependent, parts of a project will impact each other. The critical path is always the project that will take the longest

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

Float/Slack/Total Float

A

Amount of time you can delay an activity without delaying project
Float = late start - early start OR late finish - early finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

How to move through the forward pass on CPM

A

Look at the early starts and finishes
Calculated: early start + duration - 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

How to move through backward pass on CPM

A

Look at late finishes and late starts
Calculated: Late finish - duration +1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

Free Float

A

Amount you can delay one task without delaying the next task
Calculated: Early start of next activity - Early Finish of current activity - 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

Precedence Diagramming Method

A

Used to construct a schedule in which the activities are represented graphically using nodes and are linked based on their relationship

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

Analogous (Top Down) Estimating

A

Based on prior projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

Parametric Estimating

A

Uses statistical relationship between historical data and other variables

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

Three Point Estimating

A

Weighted average of 3 possibilities (optimistic, realistic, pessimistic)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
70
Q

Bottom Up Estimating

A

Most comprehensive approach. Break down work at lowest level then aggregate work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
71
Q

Reserve Analysis

A

Building in ‘non-work’ time

72
Q

Definitive Estimates

A

Closest to truth
-5% to +10% accuracy

73
Q

Budget Estimates

A

Second most accurate
-10% to 25% accuracy

74
Q

Rough Order of Magnitude Estimates

A

Least accurate
-25% to 75% accuracy

75
Q

Cost of Quality

A

Money spent achieving quality

76
Q

Fast Tracking

A

Compression technique that attempts to work activities in parallel

77
Q

Crashing

A

Compression technique that adds additional resources

78
Q

Tuckman’s Ladder

A

Forming
Storming
Norming
Performing
Adjouring

79
Q

Marlow’s Hierarchy of Needs

A

Pyramid describing what is needed to get to highly motivated (from bottom to top)
Physiological
Safety
Social
Esteem
Self Actualization

80
Q

Herzberg Motivational Theory

A

Hygiene agents contribute to motivation for EEs, these are expected and hurt when not present

81
Q

McGregor’s Theory of X

A

People are not trustworthy and need to be micromanaged

82
Q

McGregor’s Theory of Y

A

People are self led and can motivate and accomplish things themselves

83
Q

Theory of Z

A

Providing benefits and loyalty to increase productivity and loyalty in return

84
Q

Expectancy Theory of Motivation

A

People behave based on what they expect to receive out of their work

85
Q

McClelland 3 Need Theory

A

Achievement
Power
Affiliation

86
Q

Fixed Price (Lump Sum) Contracts

A

Set scope including all labor/materials
Worse for seller, better for buyer

87
Q

Firm Fixed Price Contract

A

Cannot be changed

88
Q

Fixed Price Incentive Fee Contract

A

Includes bonus for meeting targets

89
Q

Fixed Price Economic Price Adjustment

A

Adjusting based on inflation/price changes

90
Q

Cost Reimbursable Contracts

A

Pay for expenses then fee for profit
Better for sellers, worse for buyers

91
Q

Cost Plus Fixed Fee Contract

A

Pays for costs and fixed fee

92
Q

Cost Plus Incentive Fee Contract

A

Pays for costs plus a fee if a target is met

93
Q

Cost Plus Award Fee Contract

A

Pays for costs plus an award fee based on satisfaction of work

94
Q

Time and Materials Contracts

A

Pays for all materials and labor, buyer takes on risks as they will pay for any overages and should only be used when scope is high level

95
Q

Total Quality Management

A

All members of organization are responsible for quality

96
Q

Continuous Improvement (Kaizen)

A

Japanese philosophy where all parties are responsible for improvement

97
Q

Affinity Diagrams

A

Used to group ideas together

98
Q

Matrix Diagrams

A

Used to show relationships amongst processes

99
Q

Cause and Effect/Ishikawa/Fishbone Diagrams

A

Will tell you the cause of defects

100
Q

Flowcharts

A

Show you a graphical representation of the process and any room for improvements, can also help you pinpoint where issues are in the process

101
Q

Histogram

A

Bar charts that show the distribution of numerical data

102
Q

Pareto Chart

A

A combination bar and line chart that uses a technique to identify the few factors that have the greatest impact on an outcome, result, or on measures of quality, satisfaction or performance.

Separating these “vital few” from the “trivial many” is generally known as the “80/20” rule

103
Q

Scatter Diagram

A

Show trends in relation to different variables

104
Q

Agile Manifesto

A

Individuals and interactions over processes and tools
Working software over comprehensive documentation
Customer collaboration over contract negotiation
Responding to change over following a plan

105
Q

Delphi Technique

A

Process of gathering a panel of experts and engaging in several rounds of questions about how to make certain business decisions or solve an organizational problem

106
Q

Escalate Risk Response

A

Escalate outside the team for help

107
Q

Avoid Risk Response

A

Eliminate risk entirely

108
Q

Transfer Risk Response

A

Transfer to 3rd Party

109
Q

Mitigate Risk Response

A

Reduce the possibility

110
Q

Accept Risk Response

A

Deal with it, take advantage but don’t seek if its positive

111
Q

Exploit Risk Response

A

Usually for positive risk (opportunity) and seeking to make it happen

112
Q

Enhance Risk Response

A

Increase probability

113
Q

Share Risk Response

A

Cooperating with other party to reduce negative risk or increase positive

114
Q

Resource Breakdown Structure

A

Grouping of resources into certain categories and breaking down sub-categories underneath

115
Q

Quantitative Risk Analysis

A

Using information from qualitative risk analysis and analyzing and determining risk impact on project as a whole to determine the best course of action for the project with risks considered
Actually coming up with the schedule/cost numbers

116
Q

Management Reserve

A

Additional reserves set by functional managers to account for any additional unaccounted risk or unforeseen delays, mostly for unknown unknowns

117
Q

What process is vendor payment a part of?

A

Control procurements

118
Q

Attribute Sampling

A

Measures whether the results conform to the established specifications

119
Q

Qualitative Risk Analysis

A

Prioritizing individual project risks by assessing their probability of occurrence and impact as well as other characteristics

120
Q

When is customer scope validation done?

A

Monitoring and controlling

121
Q

Configuration Management Plan

A

Establish policies around naming conventions and versioning control

122
Q

When can stakeholders NOT be identified?

123
Q

What should you do if a contract is taking a while to be signed but work is urgent?

A

Utilize letter of intent

124
Q

Project performance appraisal

A

Feedback is gathered from team members’ supervisors that may point out a need for additional training

125
Q

Individual assessment

A

Used to determine information about an individual about their decision-making process, interactions with others, and how they prefer to be led.

126
Q

Compliance counsel

A

Individuals who represent compliance-related groups like legal, environmental, or security, assess project compliance as a member of a compliance counsel.

127
Q

Data vs information vs reports

A

Data is raw and hasn’t been analyzed
Information has been analyzed but is not ready for consumption
Reports take information and packages/distributes them so they can be acted on

128
Q

Stakeholder engagement assessment matrix

A

Graph that shows how stakeholders should be engaged vs how they are actually being engaged

129
Q

What do you need to consider project closed?

A

Phase complete, project complete, project cancelled
Invoices paid
Procurements fulfilled
Deliverables accepted by customer
Final performance reporting completed

130
Q

Impediment vs Blocker

A

An impediment slows down the progress of the team. A blocker completely stalls the team from delivering on time.

131
Q

Immediate action after Change Control Board makes a decision

A

Update change log

132
Q

Stakeholder Cube

A

A three-dimensional model showing aspects of a stakeholder or stakeholder group that measures power, interest, and influence

133
Q

Lead and Lag

A

A task that must wait for its predecessor to complete before it can be started has lag
A task that does not need to wait for its predecessor to complete before it can be started has lead

134
Q

Indirect Cost

A

Costs that are incurred for more than one project or an organization’s overhead (ie internet to allow team to work properly)

135
Q

Iterative vs Incremental

A

Incremental delivery yields a useable piece of the project in each iteration.
Iterative development means that the project is built in successive levels, but it is not always useable in the first few iterations.

136
Q

Secondary Risks

A

Risks that are created by the implementation of enacted risk responses

137
Q

Why should a project manager be present for contract negotiations?

A

To protect the relationship with the seller

138
Q

Who can change the team charter and when?

A

Anyone, anytime

139
Q

Who can validate scope?

A

Sponsor OR customer
Testers can verify but not validate

140
Q

Net Present Value Formula

A

Deciding I don’t need to memorize this, but:
Positive = good
Formula = Revenue / (1+ interest rate) ^ time frame

141
Q

Internal Rate of Return

A

The rate at which cash inflows equal cash outflows without consideration of external factors

142
Q

Net Future Value

A

Shows an investments future value
Positive = good

143
Q

Residual risk

A

A risk that remains after a team has planned risk responses

144
Q

Emotional intelligence impact on productivity

A

Does not DIRECTLY impact, impacts things like reduced tension, better relationships, communication, trust, etc that then directly impact productivity

145
Q

Value analysis

A

Refers to trying to get the most scope for the least financial spend

146
Q

360-degree assessment

A

Allows members to assess their own strengths and weaknesses for project manager to react to

147
Q

Stakeholder register vs Stakeholder Engagement Plan

A

Register lists stakeholders and information about their knowledge/impact
Engagement plan lists how they want to be involved/communicated to and how often

148
Q

Planning Major Output

A

Project management plan and all of its components

149
Q

Salience Model

A

Assesses stakeholders by power, urgency (immediate attention), and legitimacy (how appropriate is their involvement)

150
Q

Stakeholder Prioritization Method

A

Ranks stakeholders on their influence based on multiple factors

151
Q

Lean Principles

A

Eliminating waste
Amplifying learning
Deciding late
Delivering fast
Empowering the team
Building quality in
Optimizing the whole.

152
Q

Product Analysis

A

Translates project objectives into tangible deliverables and requirements by improving the project team’s understanding of the product

153
Q

Funding limit reconciliation

A

A technique of reconciling the expenditure of funds with the funding limits set for the project

154
Q

What process is claims administration done in?

A

Control procurements

155
Q

What to do when discovering risk

A

Add it to risk register, then analyze impacts

156
Q

What process is most associated with process improvement?

A

Manage quality

157
Q

What to do first when a project is cancelled?

A

Do a scope verification to determine what has been completed

158
Q

Upward Influence

A

Higher ups in company telling subordinates what to do

158
Q

Downward Influence

A

Individual contributors/SMEs influencing project

159
Q

Single source contract

A

Company chooses to do business with one vendor despite there being other options

160
Q

Stakeholder Analysis

A

Talking with the stakeholders to gain their perspective and thoughts/expectations for a project

161
Q

Tacit knowledge

A

Knowledge that is difficult to communicate. This kind of knowledge is typically related to experience, ability, or emotion
Typically deals with team dynamics and how people get along

162
Q

Change driven project

A

A project that has a fixed cost and schedule but flexible scope

163
Q

Risk triggers

A

Will alert the team when a risk is about to become an issue.

164
Q

Sole source contract

A

Company does business with one vendor because they are the only vendor availabe

165
Q

Knowledge Areas Acronym

A

ISSCQRCRPS

I sold silly crepes quickly regardless of crying ranchers playing soccer

166
Q

Matrix Organizational Structure

A

Weak: PjM has a little more power than functional, authority is low and PJM is part time
Strong: PM has most of the power over resources, full time position
Balanced: PMs power is almost equal to functional managers

167
Q

Functional Organizational Structure

A

Funtional manager has most of the power, project manager is likely part time and reports to that manager

168
Q

Project Oriented Organizational Structure

A

Project manager has ultimate power, control of all resources, full time

169
Q

WBS dictionary

A

Has all the detail information about each work package, such as who is doing it, where it’s getting done, and cost of it

170
Q

Purpose of stakeholder engagement plan

A

Express why information needs to be communicated and how it will manage expectations and engagement

171
Q

Contingency Reserve

A

Time or money assigned in the schedule or cost baseline for known risks with response strategies

172
Q

Purpose of managing stakeholder activity

A

Keep stakeholders expectations in check

173
Q

What tool do you use for resource leveling?

A

Resource histogram

174
Q

Project perf appraisal vs team performance assessment

A

Appraisal: meet with team and solution
Assessment: observe

175
Q

What does the scope baseline consist of?

A

Scope statement
WBS
WBS Dictionary