PMP Part 2 Flashcards
Project manager Mary was informed by the team that the constant conflicts in the project have slowed down the team so that they are now behind in the work. Mary is not sure what she did wrong while planning the project. She used a RACI chart to assign roles to each team member. She has assigned each activity to at least two people who will be held accountable for the work. What best explains the conflicts in the project?
Only one person should be held accountable for an activity when using a RACI chart
When using a RACI chart, only one person should be held accountable per task on the chart, which applies to using a kind of tool to assign resources. When more than one person is held accountable, the team members will blame each other for work that was done incorrectly or not at all.
A project manager decided to ensure that all team members on the project do not work on more than one activity at a time. This way, the team doesn’t get burned out and can work at a steady pace. The schedule may increase due to this policy, which is okay with the sponsor. What technique best describes this action?
Resource leveling
Resource leveling is done when resources on a project are over-allocated; it removes resources that are working on two activities at the same time.
A project manager has completed the project status report. The report states the CPI is 1.1 and the SPI is 1.14. The report was given to the project sponsor, who has become very upset about the project’s progress and has requested an immediate meeting with the project manager. What should the project manager report in the meeting?
The project is progressing on schedule and on budget
A SPI and CPI of 1 and greater tell us that the project is actually under budget and ahead of schedule. All other choices are reporting wrong information.
The datacenter redesign project is currently 30% complete. The project manager is not happy with the way processes are being followed by the team in ensuring that the network wiring will meet its quality requirements. What process should the project manager do to improve the processes so as to meet the quality requirements with the network wiring?
Manage quality
Manage quality is an executing process where you will improve processes by conducting audits and process analysis. All other choices are monitoring and controlling processes that will be used to measure the work against the project management plan.
Which of the following is an XP practice that helps to create a shared vision between the developers and the customers?
Metaphors
A metaphor is using XP to explain designs and create a shared vision between customers and the development team.
What is the difference between the product backlog and the iteration backlog?
Product backlog contains all work needed to be completed on the project and the iteration backlog willl contain all work that will get done in the next iteration
The product backlog will contain all the work needed to complete the project, while the iteration backlog will contain the work that will get done in the next iteration.
When using different prioritization technique what is the most important aspect that the agile project manager should communicate to the customers?
Don’t worry too much about the specifics, it’s more important to get the relative prioritization correct
When using any prioritization technique is important to ensure the customer understands not to worry too much about the specifics of the technique but to understand that it is done prioritize the features based on relative value.
The project team is working with the customers to write the user stories. The customers have refused as they claim this would add no value to the project. What would be the best step to resolve this?
Educate the user why the user stories are valuable
When managing an agile project user stories will produce a lot of value to both the team members and the customers, as such it would be best to educate them on the value of the user stories.
The project manager has met with the project team and has informed them that his team performance assessments are done, and he would like to speak with each of them individually about the results. What process group is this?
Executing
During the executing process group, the project manager will assess the team’s performance and try to improve it through the executing process of developing and managing the team.
Your company has decided to roll out a new Wi-Fi network for the staff. The sponsor has informed you that encryption on the network is mandatory. Where will the project manager document that the encryption was mandated by the sponsor?
Requirements traceability matrix
The requirements traceability matrix will trace the requirements back to their origins. The project scope statement, scope baseline, and requirements documentation will not include where requirements came from.
While working on the network upgrade project, the project manager receives many ideas about what to include in the project. The ideas seem to be very scattered and not logically grouped. What tool can best help the project manager group these ideas?
Affinity diagrams
An affinity diagram is used to group large number of ideas to review and analyze. A histogram is used to show frequencies over time. A flowchart is used to visually view a process for improvements. An ideas matrix is a made-up term.
The agile project team has determined that many of its processes has a lot of waiting and would like to remove all of the waste in the processes. What would be the best tool the agile team can use to improve their processes?
Value stream map
A value stream map is a visual representation of the flow of information through a process in which you can identify waste such as waiting time and optimize the process.
The project manager and the project team are reviewing the completed deliverables to see if they meet the performance requirements outlined in the requirements documentation. This is done so that when the customers are invited to inspect the deliverable, there will be no issues. What is the best output of this process?
Verified deliverables
The process of quality control is when the deliverables are inspected to see if they meet the quality requirements. The output of this process is verified deliverables. Control quality is generally done before the process of validate scope, where the deliverables will be inspected by the customers for a formal acceptance. The project management plan, accepted deliverables, and requirements documentation are not outputs of the control quality process.
Define a project
Projects are temporary endeavors to create a unique product, service, or result.
Per the PMBOK definition, a project is a temporary endeavor to create a unique product, service, or result. Projects are not ongoing and are not only done to improve a business.
The project manager has been informed that the company’s senior management would like a meeting about the status of the project. What should the project manager take to display the current schedule of the project?
Milestone chart
A milestone chart is a high-level view of major accomplishments on a project. These are best used when presenting a quick view of data and the project schedule to management personnel. All other choices would give you a detailed view of the project schedule and work.
When an organization is considering a project, what are some of the factors that can influence why a project should get done?
Meeting regulatory, legal, or social requirements
Reasons a project should get done include meeting regulatory, legal, or social requirements, satisfying stakeholders’ needs, and implementing business changes. The other choices pertain to operational work, which is more day-to-day and ongoing.
You are having an issue with the software crashing consistently on the project. What should you use to identify the cause of this issue and the effect it may have on your project?
Isikawa Diagram
Ishikawa diagrams, or cause-and-effect diagrams, are used to identify probable causes and sub-causes of a particular problem. A histogram is a bar chart and a flowchart is used to represent a process graphically. Continuous improvement is a theory that is used to continuously improve a product over its life cycle.
You’re currently working on a large new building development project. The project team is currently breaking down the deliverables listed in the project scope statement into work that is more manageable. What process best describes this scenario?
Create WBS
During the create WBS process the project team will use the tool of decomposition to break down the project deliverables into work packages. These work packages will then be used to help estimate the time and cost of the project. Define activities is a process of decomposing the work packages into activities, not the deliverables. Define scope is used to create the scope statement which will have a list of the deliverables. Define WBS is not a process.
You are currently working on a large building demolition project. There are many requirements for the potential vendors on the project, and you would like to ensure that they all receive the same information. What is the best tool or technique to ensure all vendors receive the same information about the project?
Bidder conference
A bidder conference is held by inviting all the potential sellers and reviewing the requirements for the project with them. This will ensure that no vendor receives more or less information than the others. The scope statement, requirements traceability matrix, and requirements documentation are generally written before vendors are invited to learn about the project.
The product owner has added three new changes to the product backlog. The agile project manager has met with the team and they have decided immediately how to implement these new changes, although these changes will be implemented in three iterations from now. The product owner informs the agile project manager that he is not happy about this. What should the agile project manager do?
Tell the team they should not have committed to doing these changes until they were ready to implement them
One of the core principles of agile is to defer decisions. What this means is to make decisions about potential changes or features until the very last minute.
The project manager is currently working on a large building renovation project. The project team is almost done with planning when the project sponsor informs the project manager that due to new regulations, the project will need to be completed within 6 months; if not, they will not be able to open the building to the public. What best represents this?
Constraints
A constraint is something that limits a project, which can include time or cost. In this question, the constraint is a limitation on the time needed to get the project done. Deliverables, assumptions, and work packages are not constraints on a project.
What is considered the single most important skill a project manager should have?
Communication
Communication skills are the most important skills a project manager should have. Projects are done by people, not technology.
The project team has completed the server deployment project. They have tested the server to ensure that it works according to the requirements given to them, and it seems to be functioning correctly. What process group has the team just completed?
Executing
The outputs of all the executed processes combined, including directly executing the process and managing project work, are the project deliverables. The output for planning would be the project management plan. The output for closing would be the final product service or result transition and the final report. The output for monitoring and controlling would be the accepted deliverables and the work performance reports.
The project manager has been informed that the cost of building a new room in the office will be $15,000, +/- 65%. The project manager wants to know why there is such a large variance in the estimate. The builder said they have not seen the space and it’s just a high-level estimate. What kind of estimate does this best represent?
Rough order of magnitude estimate
A rough order of magnitude estimate has a variance of -25% to +75%. It is usually done in the early phases of the project. Definitive estimates are between -5% to +10%. Detail estimate and materials estimate are made-up terms.