Inputs for a new project
Needs assessment and business case or customer contract
Inputs to 4.1 Develop the Project Charter
.1 Project statement of work .2 Business case .3 Agreements .4 Enterprise Environmental Factors .5 Organizational process assets
Tools and Techniques to 4.1 Develop the Project Charter
.1 Expert Judgement
.2 Data Gathering
.3 Interpersonal & Team Skills
.4 Meetings
Outputs to 4.1 Develop the Project Charter
.1 Project Charter
.2 Assumption Log
Inputs to 4.2 Develop Project Management Plan
.1 Project Charter .2 Outputs from Other Processes .3 Enterprise Environmental Factors .4 Organizational Process Assets
Tools and Techniques to 4.2 Develop Project Management Plan
.1 Expert Judgement
.2 Data Gathering
.3 Interpersonal & Team Skills
.4 Meetings
Outputs to 4.2 Develop Project Management Plan
.1 Project Management Plan
Inputs to 4.3 Direct and Manage Project Work
.1 Project Management Plan .2 Project Documents .3 Approved Change Requests .4 Enterprise Environmental Factors .5 Operational Process Assets
Tools and Techniques to 4.3 Direct and Manage Project Work
.1 Expert Judgement
.2 Project Management Information System
.3 Meetings
Outputs to 4.3 Direct and Manage Project Work
.1 Deliverables .2 Work Performance Data .3 Issue Log .4 Change Requests .5 Project Management Plan Updates .6 Project Documents Updates .7 Organizational Process Assets Updates
Inputs to 4.4 Manage Project Knowledge
.1 Project Management Plan .2 Project Documents .3 Deliverables .4 Enterprise Environmental Factors .5 Organizational Process Assets
Tools and Techniques to 4.4 Manage Project Knowledge
.1 Expert Judgement
.2 Knowledge Management
.3 Information Management
.4 Interpersonal & Team Skills
Outputs to 4.4 Manage Project Knowledge
.1 Lessons Learned Register
.2 Project Management Plan Updates
.3 Organizational Process Assets Updates
Inputs to 4.5 Monitor and Control Project Work
.1 Project Management Plan .2 Project Documents .3 Work Performance Information .4 Agreements .5 Enterprise Environmental Factors .6 Organizational Process Assets
Tools and Techniques to 4.5 Monitor and Control Project Work
.1 Expert Judgement
.2 Data Analysis
.3 Decision Making
.4 Meetings
Outputs to 4.5 Monitor and Control Project Work
.1 Work Performance Reports
.2 Change Requests
.3 Project Management Plan Updates
.4 Project Documents Updates
Inputs to 4.6 Perform Integrated Change Control
.1 Project Management Plan .2 Project Documents .3 Work Performance Reports .4 Change Requests .5 Enterprise Environmental Factors .6 Organizational Process Assets
Tools and Techniques to 4.6 Perform Integrated Change Control
.1 Expert Judgement .2 Change Control Tools .3 Data Analysis .4 Decision Making .5 Meetings
Outputs to 4.6 Perform Integrated Change Control
.1 Approved Change Requests
.2 Project Management Plan Updates
.3 Project Documents Updates
Inputs to 4.7 Close Project or Phase
.1 Project Charter .2 Project Management Plan .3 Project Documents .4 Accepted Deliverables .5 Business Documents .6 Agreements .7 Procurement Documentation .8 Organizational Process Assets
Tools and Techniques to 4.7 Close Project or Phase
.1 Expert Judgement
.2 Data Analysis
.3 Meetings
Outputs to 4.7 Close Project or Phase
.1 Project Documents Updates
.2 Final Product, Service, or Result Transition
.3 Final Report
.4 Organizational Process Assets Updates
Inputs to 5.1 Plan Scope Management
.1 Project Charter
.2 Project Management Plan
.3 Enterprise Environmental Factors
.4 Organizational Process Assets
Tools and Techniques to 5.1 Plan Scope Management
.1 Expert Judgement
.2 Data Analysis
.3 Meetings