PMP ITTOs Flashcards

Learn the ITTOS to all 49 Project Management Processes

1
Q

Inputs for a new project

A

Needs assessment and business case or customer contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Inputs to 4.1 Develop the Project Charter

A
.1 Project statement of work
.2 Business case
.3 Agreements
.4 Enterprise Environmental
Factors
.5 Organizational process assets
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Tools and Techniques to 4.1 Develop the Project Charter

A

.1 Expert Judgement
.2 Data Gathering
.3 Interpersonal & Team Skills
.4 Meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Outputs to 4.1 Develop the Project Charter

A

.1 Project Charter

.2 Assumption Log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Inputs to 4.2 Develop Project Management Plan

A
.1 Project Charter
.2 Outputs from Other Processes
.3 Enterprise Environmental
Factors
.4 Organizational Process Assets
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Tools and Techniques to 4.2 Develop Project Management Plan

A

.1 Expert Judgement
.2 Data Gathering
.3 Interpersonal & Team Skills
.4 Meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Outputs to 4.2 Develop Project Management Plan

A

.1 Project Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Inputs to 4.3 Direct and Manage Project Work

A
.1 Project Management Plan
.2 Project Documents
.3 Approved Change Requests
.4 Enterprise Environmental
Factors
.5 Operational Process Assets
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Tools and Techniques to 4.3 Direct and Manage Project Work

A

.1 Expert Judgement
.2 Project Management Information System
.3 Meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Outputs to 4.3 Direct and Manage Project Work

A
.1 Deliverables
.2 Work Performance Data
.3 Issue Log
.4 Change Requests
.5 Project Management Plan Updates
.6 Project Documents Updates
.7 Organizational Process Assets Updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Inputs to 4.4 Manage Project Knowledge

A
.1 Project Management Plan
.2 Project Documents
.3 Deliverables
.4 Enterprise Environmental
Factors
.5 Organizational Process Assets
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Tools and Techniques to 4.4 Manage Project Knowledge

A

.1 Expert Judgement
.2 Knowledge Management
.3 Information Management
.4 Interpersonal & Team Skills

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Outputs to 4.4 Manage Project Knowledge

A

.1 Lessons Learned Register
.2 Project Management Plan Updates
.3 Organizational Process Assets Updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Inputs to 4.5 Monitor and Control Project Work

A
.1 Project Management Plan
.2 Project Documents
.3 Work Performance Information
.4 Agreements
.5 Enterprise Environmental
Factors
.6 Organizational Process Assets
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Tools and Techniques to 4.5 Monitor and Control Project Work

A

.1 Expert Judgement
.2 Data Analysis
.3 Decision Making
.4 Meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Outputs to 4.5 Monitor and Control Project Work

A

.1 Work Performance Reports
.2 Change Requests
.3 Project Management Plan Updates
.4 Project Documents Updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Inputs to 4.6 Perform Integrated Change Control

A
.1 Project Management Plan
.2 Project Documents
.3 Work Performance Reports
.4 Change Requests
.5 Enterprise Environmental Factors
.6 Organizational Process Assets
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Tools and Techniques to 4.6 Perform Integrated Change Control

A
.1 Expert Judgement
.2 Change Control Tools
.3 Data Analysis
.4 Decision Making
.5 Meetings
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Outputs to 4.6 Perform Integrated Change Control

A

.1 Approved Change Requests
.2 Project Management Plan Updates
.3 Project Documents Updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Inputs to 4.7 Close Project or Phase

A
.1 Project Charter
.2 Project Management Plan
.3 Project Documents
.4 Accepted Deliverables
.5 Business Documents
.6 Agreements
.7 Procurement Documentation
.8 Organizational Process Assets
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Tools and Techniques to 4.7 Close Project or Phase

A

.1 Expert Judgement
.2 Data Analysis
.3 Meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Outputs to 4.7 Close Project or Phase

A

.1 Project Documents Updates
.2 Final Product, Service, or Result Transition
.3 Final Report
.4 Organizational Process Assets Updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Inputs to 5.1 Plan Scope Management

A

.1 Project Charter
.2 Project Management Plan
.3 Enterprise Environmental Factors
.4 Organizational Process Assets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Tools and Techniques to 5.1 Plan Scope Management

A

.1 Expert Judgement
.2 Data Analysis
.3 Meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Ouputs to 5.1 Plan Scope Management
.1 Scope Management Plan | .2 Requirements Management Plan
26
Inputs to 5.2 Collect Requirements
``` .1 Project Charter .2 Project Management Plan .3 Project Documents .4 Business Documents .5 Agreements .6 Enterprise Environmental Factors .7 Organizational Process Assets ```
27
Tools and Techniques to 5.2 Collect Requirements
``` .1 Expert Judgement .2 Data Gathering .3 Data Analysis .4 Decision Making .5 Data Representation .6 Interpersonal & Team Skills .7 Context Diagram .8 Prototypes ```
28
Outputs to 5.2 Collect Requirements
.1 Requirements Documentation | .2 Requirements Traceability Matrix
29
Inputs to 5.3 Define Scope
``` .1 Project Charter .2 Project Management Plan .3 Project Documents .4 Enterprise Environmental Factors .5 Organizational Process Assets ```
30
Tools and Techniques to 5.3 Define Scope
``` .1 Expert Judgement .2 Data Analysis .3 Decision Making .4 Interpersonal & Team Skills .5 Product Analysis ```
31
Outputs to 5.3 Define Scope
.1 Scope Statement | .2 Project Documents Updates
32
Inputs to 5.4 Create WBS
.1 Project Management Plan .2 Project Documents .3 Enterprise Environmental Factors .4 Organizational Process Assets
33
Tools and Techniques to 5.4 Create WBS
.1 Expert Judgment | .2 Decomposition
34
Outputs to 5.4 Create WBS
.1 Scope Baseline | .2 Project Documents Updates
35
Inputs to 5.5 Validate Scope
.1 Project Management Plan .2 Project Documents .3 Verified Deliverables .4 Work Performance Data
36
Tools and Techniques to 5.5 Validate Scope
.1 Inspection | .2 Decision Making
37
Outputs to 5.5 Validate Scope
.1 Accepted Deliverables .2 Work Performance Information .3 Change Requests .4 Project Documents Updates
38
Inputs to 5.6 Control Scope
.1 Project Management Plan .2 Project Documents .3 Work Performance Data .4 Organizational Process Assets
39
Tools and Techniques to 5.6 Control Scope
.1 Data Analysis
40
Outputs to 5.6 Control Scope
.1 Work Performance Information .2 Change Requests .3 Project Management Plan Updates .4 Project Documents Updates
41
Inputs to 6.1 Plan Schedule Management
.1 Project Charter .2 Project Management Plan .3 Enterprise Environmental Factors .4 Organizational Process Assets
42
Tools and Techniques to 6.1 Plan Schedule Management
.1 Expert Judgement .2 Data Analysis .3 Meetings
43
Outputs to 6.1 Plan Schedule Management
.1 Schedule Management Plan
44
Inputs to 6.2 Define Activities
.1 Project Management Plan .2 Enterprise Environmental Factors .3 Organizational Process Assets
45
Tools and Techniques to 6.2 Define Activities
.1 Expert Judgement .2 Decomposition .3 Rolling Wave Planning .4 Meetings
46
Outputs to 6.2 Define Activities
``` .1 Activity List .2 Activity Attributes .3 Milestone List .4 Change Requests .5 Project Management Plan Updates ```
47
Inputs to 6.3 Sequence Activities
.1 Project Management Plan .2 Project Documents .3 Enterprise Environmental Factors .4 Organizational Process Assets
48
Tools and Techniques to 6.3 Sequence Activities
.1 Precedence Diagramming Method .2 Dependency Determination and Integration .3 Leads and Lags .4 Project Management Information Systems
49
Outputs to 6.3 Sequence Activities
.1 Project Schedule Network Diagrams | .5 Project Documents Updates
50
Inputs to 6.4 Estimate Activity Durations
.1 Project Management Plan .2 Project Documents .3 Enterprise Environmental Factors .4 Organizational Process Assets
51
Tools and Techniques to 6.4 Estimate Activity Durations
``` .1 Expert Judgment .2 Analogous Estimating .3 Parametric Estimating .4 Three-point Estimating .5 Bottom-up Estimating .6 Data Analysis .7 Decision Making .8 Meetings ```
52
Outputs to 6.4 Estimate Activity Durations
.1 Duration Estimates .2 Basis of Estimates .3 Project Documents Updates
53
Inputs to 6.5 Develop Schedule
``` .1 Project Management Plan .2 Project Documents .3 Agreements .4 Enterprise Environmental Factors .5 Organizational Process Assets ```
54
Tools and Techniques to 6.5 Develop Schedule
``` .1 Schedule Network Analysis .2 Critical Path Method .3 Resource Optimization .4 Data Analysis .5 Leads and Lags .6 Schedule Compression .7 Project Managment Information System .8 Agile Release Planning ```
55
Outputs to 6.5 Develop Schedule
``` .1 Schedule Baseline .2 Project Schedule .3 Schedule Data .4 Project Calendars .5 Change Requests .6 Project Management Plan Updates .7 Project Documents Updates ```
56
Inputs to 6.6 Control Schedule
.1 Project Management Plan .2 Project Documents .3 Work Performance Data .4 Organizational Process Assets
57
Tools and Techniques to 6.6 Control Schedule
``` .1 Data Analysis .2 Critical Path Method .3 Project Management Information System .4 Resource Optimization .5 Leads and Lags .6 Schedule Compression ```
58
Outputs to 6.6 Control Schedule
``` .1 Work Performance Information .2 Schedule Forecasts .3 Change Requests .4 Project Management Plan Updates .5 Project Documents Updates ```
59
Inputs to 7.1 Plan Cost Management
.1 Project Charter .2 Project Management Plan .3 Enterprise Environmental Factors .4 Organizational Process Assets
60
Tools and Techniques to 7.1 Plan Cost Management
.1 Expert Judgment .2 Data Analysis .3 Meetings
61
Outputs to 7.1 Plan Cost Management
.1 Cost Management Plan
62
Inputs to 7.2 Estimate Costs
.1 Project Management Plan .2 Project Documents .3 Enterprise Environmental Factors .4 Organizational Process Assets
63
Tools and Techniques to 7.2 Estimate Costs
``` .1 Expert Judgment .2 Analogous Estimating .3 Parametric Estimating .4 Bottom-up Estimating .5 Three-point Estimating .6 Data Analysis .7 Project Management Information System .8 Decision Making ```
64
Outputs to 7.2 Estimate Costs
.1 Cost Estimates .2 Basis of Estimates .3 Project Documents Updates
65
Inputs to 7.3 Determine Budget
``` .1 Project Management Plan .2 Project Documents .3 Business Documents .4 Agreements .5 Enterprise Environmental Factors .6 Organizational Process Assets ```
66
Tools and Techniques to 7.3 Determine Budget
``` .1 Expert Judgment .2 Cost Aggregation .3 Data Analysis .4 Historical Information Review .5 Funding Limit Reconciliation .6 Financing ```
67
Outputs to 7.3 Determine Budget
.1 Cost Baseline .2 Project Funding Requirements .3 Project Documents Updates
68
Inputs to 7.4 Control Costs
``` .1 Project Management Plan .2 Project Documents .3 Project Funding Requirements .4 Work Performance Data .5 Organizational Process Assets ```
69
Tools and Techniques to 7.4 Control Costs
.1 Expert Judgment .2 Data Analysis .3 To-complete Performance Index .4 Project Management Information System
70
Outputs to 7.4 Control Costs
``` .1 Work Performance Information .2 Cost Forecasts .3 Change Requests .4 Project Management Plan Updates .5 Project Documents Updates ```
71
Inputs to 8.1 Plan Quality Management
``` .1 Project Charter .2 Project Management Plan .3 Project Documents .4 Enterprise Environmental Factors .5 Organizational Process Assets ```
72
Tools and Techniques to 8.1 Plan Quality Management
``` .1 Expert Judgment .2 Data Gathering .3 Data Analysis .4 Decision Making .5 Data Representation .6 Test & Inspection Planning .7 Meetings ```
73
Outputs to 8.1 Plan Quality Management
.1 Quality Management Plan .2 Quality Metrics .3 Project Management Plan Updates .4 Project Documents Updates
74
Inputs to 8.2 Manage Quality
.1 Project Management Plan .2 Project Documents .3 Organizational Process Assets
75
Tools and Techniques to 8.2 Manage Quality
``` .1 Data Gathering .2 Data Analysis .3 Decision Making .4 Data Representation .5 Audits .6 Design for X .7 Problem Solving .8 Quality Improvement Methods ```
76
Outputs to 8.2 Manage Quality
``` .1 Quality Reports .2 Test & Evaluation Documents .3 Change Requests .4 Project Management Plan Updates .5 Project Documents Updates ```
77
Inputs to 8.3 Manage Quality
``` .1 Project Management Plan .2 Project Documents .3 Approved Change Requests .4 Deliverables .5 Work Performance Data .6 Enterprise Environmental Factors .7 Organizational Process Assets ```
78
Tools and Techniques to 8.3 Manage Quality
``` .1 Data Gathering .2 Data Analysis .3 Inspection .4 Testing/Product Evaluations .5 Data Representation .6 Meetings ```
79
Outputs to 8.3 Manage Quality
``` .1 Quality Control Measurements .2 Verified Deliverables .3 Work Performance Information .4 Change Requests .5 Project Management Plan Updates .6 Project Documents Updates ```
80
Inputs to 9.1 Plan Resource Management
``` .1 Project Charter .2 Project Management Plan .3 Project Documents .4 Environmental Factors .5 Organizational Process Assets ```
81
Tools and Techniques to 9.1 Plan Resource Management
.1 Expert Judgment .2 Data Representation .3 Organizational Theory .4 Meetings
82
Outputs to 9.1 Plan Resource Management
.1 Resource Management Plan .2 Team Charter .3 Project Documents Updates
83
Inputs to 9.2 Estimate Activity Resources
.1 Project Management Plan .2 Project Documents .3 Environmental Factors .4 Organizational Process Assets
84
Tools and Techniques to 9.2 Estimate Activity Resources
``` .1 Expert Judgment .2 Bottom-up Estimating .3 Analogous Estimating .4 Parametric Estimating .5 Data Analysis .6 Project Management Information System .7 Meetings ```
85
Outputs to 9.2 Estimate Activity Resources
.1 Resource Requirements .2 Basis of Estimates .3 Resource Breakdown Structure .4 Project Documents Updates
86
Inputs to 9.3 Acquire Resources
.1 Project Management Plan .2 Project Documents .3 Environmental Factors .4 Organizational Process Assets
87
Tools and Techniques to 9.3 Acquire Resources
.1 Decision Making .2 Interpersonal and Team Skills .3 Pre-assignment .4 Virtual Teams
88
Outputs to 9.3 Acquire Resources
``` .1 Physical Resource Assignments .2 Project Team Assignments .3 Resource Calendars .4 Change Requests .5 Project Managment Plan Updates .6 Project Documents Updates .7 Enterprise Environmental Factors Updates .8 Organizational Process Assets Updates ```
89
Inputs to 9.4 Develop Team
.1 Project Management Plan .2 Project Documents .3 Environmental Factors .4 Organizational Process Assets
90
Tools and Techniques to 9.4 Develop Team
``` .1 Colocation .2 Virtual Teams .3 Communication Technology .4 Interpersonal and Team Skills .5 Recognition and Rewards .6 Training .7 Individual and Team Assessments .8 Meetings ```
91
Outputs to 9.4 Develop Team
``` .1 Team Performance Assessments .2 Change Requests .3 Project Management Plan Updates .4 Project Documents Updates .5 Enterprise Environmental Factors Updates .6 Organizational Process Assets Updates ```
92
Inputs to 9.5 Manage Team
``` .1 Project Management Plan .2 Project Documents .3 Work Performance Reports .4 Team Performance Assessments .5 Environmental Factors .6 Organizational Process Assets ```
93
Tools and Techniques to 9.5 Manage Team
.1 Interpersonal and Team Skills | .2 Project Management Information System
94
Outputs to 9.5 Manage Team
.1 Change Requests .2 Project Management Plan Updates .3 Project Documents Updates .4 Enterprise Environmental Factors Updates
95
Inputs to 9.6 Control Resources
``` .1 Project Management Plan .2 Project Documents .3 Work Performance Reports .4 Agreements .5 Organizational Process Assets ```
96
Tools and Techniques to 9.6 Control Resources
.1 Data Analysis .2 Problem Solving .3 Interpersonal and Team Skills .4 Project Management Information System
97
Outputs to 9.6 Control Resources
.1 Work Performance Information .2 Change Requests .3 Project Management Plan Updates .4 Project Documents Updates
98
Inputs to 10.1 Plan Communications Management
``` .1 Project Charter .2 Project Management Plan .3 Project Documents .4 Enterprise Environmental Factors .5 Organizational Process Assets ```
99
Tools and Techniques to 10.1 Plan Communications Management
``` .1 Expert Judgment .2 Communication Requirements Analysis .3 Communication Technology .4 Communication Models .5 Communication Methods .6 Interpersonal and Team Skills .7 Data Representation .8 Meetings ```
100
Outputs to 10.1 Plan Communications Management
.1 Communications Management Plan .2 Project Management Plan Updates .3 Project Documents Updates
101
Inputs to 10.2 Manage Communications
``` .1 Project Management Plan .2 Project Documents .3 Work Performance Reports .4 Enterprise Environmental Factors .5 Organizational Process Assets ```
102
Tools and Techniques to 10.2 Manage Communications
``` .1 Communication Technology .2 Communication Methods .3 Communication Skills .4 Project Management Information System .5 Project Reporting .6 Interpersonal and Team Skills .7 Meetings ```
103
Outputs to 10.2 Manage Communications
.1 Project Communications .2 Project Management Plan Updates .3 Project Documents Updates .4 Organizational Process Assets Updates
104
Inputs to 10.3 Monitor Communications
``` .1 Project Management Plan .2 Project Documents .3 Work Performance Reports .4 Enterprise Environmental Factors .5 Organizational Process Assets ```
105
Tools and Techniques to 10.3 Monitor Communications
``` .1 Expert Judgment .2 Project Management Information System .3 Data Representation .4 Interpersonal and Team Skills .5 Meetings ```
106
Outputs to 10.3 Monitor Communications
.1 Work Performance Information .2 Change Requests .3 Project Management Plan Updates .4 Project Documents Updates
107
Inputs to 11.1 Plan Risk Management
``` .1 Project Charter .2 Project Management Plan .2 Project Documents .4 Enterprise Environmental Factors .5 Organizational Process Assets ```
108
Tools and Techniques to 11.1 Plan Risk Management
.1 Expert Judgment .2 Data Analysis .3 Meetings
109
Outputs to 11.1 Plan Risk Management
.1 Risk Management Plan
110
Inputs to 11.2 Identify Risks
``` .1 Project Management Plan .2 Project Documents .3 Agreements .4 Procurement Documentation .5 Enterprise Environmental Factors .6 Organizational Process Assets ```
111
Tools and Techniques to 11.2 Identify Risks
``` .1 Expert Judgment .2 Data Gathering .3 Data Analysis .4 Interpersonal and Team Skills .5 Prompt Lists .6 Meetings ```
112
Outputs to 11.2 Identify Risks
.1 Risk Register .2 Risk Report .3 Project Documents Updates
113
Inputs to 11.3 Perform Qualitative Risk Analysis
.1 Project Management Plan .2 Project Documents .3 Enterprise Environmental Factors .4 Organizational Process Assets
114
Tools and Techniques to 11.3 Perform Qualitative Risk Analysis
``` .1 Expert Judgment .2 Data Gathering .3 Data Analysis .4 Interpersonal and Team Skills .5 Risk Categorization .6 Data Representation .7 Meetings ```
115
Outputs to 11.3 Perform Qualitative Risk Analysis
.1 Project Documents Updates
116
Inputs to 11.4 Perform Quantitative Risk Analysis
.1 Project Management Plan .2 Project Documents .3 Enterprise Environmental Factors .4 Organizational Process Assets
117
Tools and Techniques to 11.4 Perform Quantitative Risk Analysis
``` .1 Expert Judgment .2 Data Gathering .3 Interpersonal and Team Skills .4 Representations of Uncertainty .5 Data Analysis ```
118
Outputs to 11.4 Perform Quantitative Risk Analysis
.1 Project Documents Updates
119
Inputs to 11.5 Plan Risk Responses
.1 Project Management Plan .2 Project Documents .3 Enterprise Environmental Factors .4 Organizational Process Assets
120
Tools and Techniques to 11.5 Plan Risk Responses
``` .1 Expert Judgment .2 Data Gathering .3 Interpersonal and Team Skills .4 Strategies for Threats .5 Strategies for Opportunities .6 Contingent Response Strategies .7 Strategies for Overall Project Risk .8 Data Analysis .9 Decision Making ```
121
Outputs to 11.5 Plan Risk Responses
.1 Change Requests .2 Project Management Plan Updates .3 Project Documents Updates
122
Inputs to 11.6 Implement Risk Responses
.1 Project Management Plan .2 Project Documents .3 Organizational Process Assets
123
Tools and Techniques to 11.6 Implement Risk Responses
.1 Expert Judgment .2 Interpersonal and Team Skills .3 Project Management Information System
124
Outputs to 11.6 Implement Risk Responses
.1 Change Requests | .2 Project Documents Updates
125
Inputs to 11.7 Monitor Risks
.1 Project Management Plan .2 Project Documents .3 Work Performance Data .4 Work Performance Reports
126
Tools and Techniques to 11.7 Monitor Risks
.1 Data Analysis .2 Audits .3 Meetings
127
Outputs to 11.7 Monitor Risks
``` .1 Work Performance Information .2Change Requests .3 Project Management Plan Updates .4 Project Documents Updates .5 Organizational Process Assets Updates ```
128
Inputs to 12.1 Plan Procurement Management
``` .1 Project Charter .2 Business Documentation .3 Project Management Plan .4 Project Documents .5 Enterprise Environmental Factors .6 Organizational Process Assets ```
129
Tools and Techniques to 12.1 Plan Procurement Management
``` .1 Expert Judgment .2 Data Gathering .3 Data Analysis .4 Source Selection Analysis .5 Meetings ```
130
Outputs to 12.1 Plan Procurement Management
``` .1 Procurement Management Plan .2 Procurement Strategy .3 Bid Documents .4 Procurement Statement of Work .5 Source Selection Criteria .6 Make-or-buy Decisions .7 Independent Cost Estimates .8Change Requests .9 Project Documents Updates .10 Organizational Process Assets Updates ```
131
Inputs to 12.2 Conduct Procurements
``` .1 Project Management Plan .2 Project Documents .3 Procurement Documentation .4 Seller Proposals .5 Enterprise Environmental Factors .6 Organizational Process Assets ```
132
Tools and Techniques to 12.2 Conduct Procurements
``` .1 Expert Judgment .2 Advertising .3 Bidder Conferences .4 Data Analysis .5 Interpersonal and Team Skills ```
133
Outputs to 12.2 Conduct Procurements
``` .1 Selected Sellers .2 Agreements .3 Change Requests .4 Project Management Plan Updates .5 Project Documents Updates .6 Organizational Process Assets Updates ```
134
Inputs to 12.3 Control Procurements
``` .1 Project Management Plan .2 Project Documents .3 Agreements .4 Procurement Documentation .5 Approved Change Requests .6 Work Performance Data .7 Enterprise Environmental Factors .8 Organizational Process Assets ```
135
Tools and Techniques to 12.3 Control Procurements
``` .1 Expert Judgment .2 Claims Administration .3 Data Analysis .4 Inspection .5 Audits ```
136
Outputs to 12.3 Control Procurements
``` .1 Closed Procurements .2 Work Performance Information .3 Procurement Documentation Updates .4 Change Requests .5 Project Management Plan Updates .6 Project Documents Updates .7 Organizational Process Assets Updates ```
137
Inputs to 13.1 Identify Stakeholders
``` .1 Project Charter .2 Business Documents .3 Project Management Plan .4 Project Documents .5 Agreements .6 Enterprise Environmental Factors .7 Organizational Process Assets ```
138
Tools and Techniques to 13.1 Identify Stakeholders
``` .1 Expert Judgment .2 Data Gathering .3 Data Analysis .4 Data Representation .5 Meetings ```
139
Outputs to 13.1 Identify Stakeholders
.1 Stakeholder Register .2 Change Requests .3 Project Management Plan Updates .4 Project Documents Updates
140
Inputs to 13.2 Plan Stakeholder Engagement
``` .1 Project Charter .2 Project Management Plan .3 Project Documents .4 Agreements .5 Enterprise Environmental Factors .6 Organizational Process Assets ```
141
Tools and Techniques to 13.2 Plan Stakeholder Engagement
``` .1 Expert Judgment .2 Data Gathering .3 Data Analysis .4 Decision Making .5 Data Representation .6 Meetings ```
142
Outputs to 13.2 Plan Stakeholder Engagement
.1 Stakeholder Engagement Plan
143
Inputs to 13.3 Manage Stakeholder Engagement
.1 Project Management Plan .2 Project Documents .3 Enterprise Environmental Factors .4 Organizational Process Assets
144
Tools and Techniques to 13.3 Manage Stakeholder Engagement
``` .1 Expert Judgment .2 Communication Skills .3 Interpersonal and Team Skills .4 Ground Rules .5 Meetings ```
145
Outputs to 13.3 Manage Stakeholder Engagement
.1 Change Requests .2 Project Management Plan Updates .3 Project Documents Updates
146
Inputs to 13.4 Monitor Stakeholder Engagement
``` .1 Project Management Plan .2 Project Documents .3 Work Performance Data .4 Enterprise Environmental Factors .5 Organizational Process Assets ```
147
Tools and Techniques to 13.4 Monitor Stakeholder Engagement
``` .1 Data Analysis .2 Decision Making .3 Data Representation .4 Communication Skills .5 Interpersonal and Team Skills .6 Meetings ```
148
Outputs to 13.4 Monitor Stakeholder Engagement
.1 Work Performance Information .2 Change Requests .3 Project Management Plan Updates .4 Project Documents Updates