PMP Exam Review Flashcards

1
Q

What is a project?

A

temporary endeavor undertaken to create a unique product

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

3 types of deliverables

A

product, service, result

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a project manager?

A

person assigned by the organization to lead the team that is responsible for achieving project objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the agile team roles?

A

product owner - prioritizes the product backlog (in collaboration with stakeholders)
scrum master / team facilitator - promotes the team as a servant leader who works to removed impediments
team - 3-9 people

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

List the Scrum Events and the Agile Ceremonies

A

scrum events: sprint, sprint planning, daily scrum, sprint review, retrospective

agile ceremonies: same list w/o sprint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Describe Kanban

A

flow-based scheduling (on a board)
# columns and labels change with each project
limits for # items in each column
‘swarm’ to unclog bottlenecks
does not use sprints

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Describe Crystal

A

agile method
complexity increases as # people involved increases
uses color scheme to denote complexity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a RACI chart?

A

type of RAM (responsibility assignment matrix)
defines involvement of stakeholders in different parts of the project
RACI = responsible, accountable, consulted, informed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is in the resource management plan?

A

organization chart
resource management guidance
training strategies
resource calendar
recognition plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Compare agile vs. traditional project assignments

A

agile: team self organizes and assesses requirements
traditional: PM assigns work via a work breakdown structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What values support PMI’s code of ethics?

A

responsibility, respect, fairness, honesty

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the techniques for prioritizing?

A

review project backlog
Kano model - identifies needs as basic, performance, or excitement
MoSCoW analysis - must/should/could/won’t have (lists of items)
Paired comparisons - compares two features, take the winner and repeat with another feature
100 points - assign different combinations of point values to different items, sum = 100

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a report? How is it created?

A

something designed to inspire decision or action
raw data is organized into facts, facts are put in context to create a report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

List some team decision making tools

A

Brainstorming - quantity over quality
3-point estimating - average of optimistic, pessimistic, most likely values
absolute estimating - predicting via a value
relative estimating - predicting via comparisons (t-shirt sizing)
story points w/fibonacci values

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is velocity?

A

number of story points team produced in a sprint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Describe a retrospective

A

checks on process effectiveness
looks for root causes of issues
evaluate trial process for continued use, adjusting or eliminating
steps: set stage, gather data, generate insights, make decisions, close

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

List components of a communications plan

A

meeting times
tools to track work status
frequency of work status updates
shared team hours
preferred communication approaches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is project vision?

A

includes what the project is, where it is going to be used, who it will serve
explains desired objectives
explains alignment with company’s strategic goals

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Who issues the project charter? what is it?

A

issued by the project sponsor

it authorizes the project
used with traditional projects
empowers PM
high level requirements
milestones
stakeholder register
exit criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

List methods to reach a consensus

A

fists of 5 (closed fist = complete disagreement; 5 fingers = complete agreement)
roman voting (gladiator)
Polling (hear all opinions, then vote)
dot voting - same approach as 100 points method of estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is an example of an XP Metaphor?

A

amazon using a shopping cart to ‘check out’
(xp metaphor is analogy for how something will work)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is an EEF?

A

Enterprise environmental factor
-conditions (not under control of the project team) that affect the project
internal: organizational culture, infrastructure
external: market conditions, government standards/policies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is an OPA?

A

Organizational process asset
-plans, processes, procedures specific to the organization
lessons learned, knowledge base, templates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What is a business case?
How is this different from a business needs document?

A

economic feasibility study (financial analysis)
provides basis for authorization of the project

different b/c a needs document is done first and focuses on more than just financial reasons to do a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What is a project implementation plan?

A

built to ensure minimal disruption is caused by implementing your project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Describe ‘rolling wave planning’

A

REFERS TO WORK

iterative planning technique in which the near-term work is planned in detail and future work is planned at a higher level, form of progressive elaboration that focuses on scope planning

can be used in either predictive or agile

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What is a predictive life cycle?

A

approach in which scope, time and cost are determined early and are fixed

aka: ‘waterfall’ or ‘traditional’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

What are the adaptive life cycles?

A

iterative - producing several versions of the finished product

incremental - continuously adding to parts of the product that are already finished

agile - project constantly evolves via continuous collaboration, iterative repetition with incremental deliverables

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

List the typical use cases

A

Agile, predictive, hybrid, iterative, incremental

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

What is a ‘blah blah blah’ management plan used for?

A

it explains how the ‘blah blah blah’ will work, but does not contain the ‘blah blah blah’

example: the scope management plan does not explain the actual scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

What is project scope?

A

the work done to deliver a product or service

project scope INCLUDES product scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

What is product scope?

A

features and functions of the product or service

product scope IS INCLUDED IN project scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

List the data gathering techniques

A

document analysis
focus groups
questionnaires
benchmarking - comparing your product to the market
interviews

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

What is the ‘Delphi Technique’?

A

a decision making technique that involves consulting experts, having a moderator summarize and deliver all of their opinions, then the experts submit another answer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Compare affinity diagram to mind mapping

A

Affinity: takes a large collection of ideas and organizes them into similar groups

Mind: consolidates many ideas

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

Describe a context diagram

A

a scope model that shows how your product will interact with the rest of the business

product = order system; rest of the business = customer, warehouse, bank

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

What is the purpose of a requirements traceability matrix?

A

links requirements to the deliverable that satisfies them

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

What is included in the project scope statement?

A

scope, major deliverables, assumptions, constraints

developed after requirements have been established

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

What does product analysis help to define?

A

scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

Describe a work package and the 100% rule

A

work package - lowest level of any branch in the WBS

THERE ARE NO LIMITS TO THE NUMBER OF DECOMPOSITIONS WITHIN A WBS

100% rule - if something is not included in the WBS, that item will not get done without a change request

41
Q

What is a control account?

A

control point where scope/budget/actual cost/schedule are compared to earned value for performance measurement

42
Q

What is a planning package?

A

a placeholder on the WBS for future work that has not been fully planned

43
Q

What are the parts of the scope baseline?

A

scope statement, WBS, WBS dictionary

44
Q

What is the ranking system in the product backlog?

A

Epic -> features -> user stories -> tasks

45
Q

Describe a milestone

A

significant event in a project/program/portfolio
no duration
not an activity (it is a moment in time)

46
Q

What are the types of precedence relationships?

A

finish to start (most common)
start to start
finish to finish
start to finish (least common)

47
Q

Explain effort vs. duration

A

effort: working hours
duration: elapsed time

example: worked on a fence for 5 hours over the weekend (Sat and Sun), duration was 48 hours while effort was 5 hours

48
Q

What is project float? What are the formulas?

A

difference between the critical path and another project path

(critical path has zero float)

late start minus early start
late finish minus early finish

49
Q

Describe smoothing and leveling

A

smoothing: adjust activities to keep resource requirements within original limits, does not change critical path

leveling: adjusts start and finish dates based on resource constraints, CAN change critical path

50
Q

What are the schedule compression techniques?

A

Crashing - adding resources to shorten items on the critical path

Fast-tracking - perform activities in parallel to reduce time

51
Q

Cost estimate vs budget

A

cost estimate = single activity
budget = project

52
Q

Direct cost vs indirect cost

A

direct - anything that can be directly tied to a WBS item

indirect - cannot directly tie to WBS (items shared by multiple teams, ex: furniture in a meeting room)

53
Q

What is life cycle costing?

A

costs associated with ongoing operations resulting from the completion of a project (buying a dog = project cost; taking care of the puppies = life cycle cost)

54
Q

What is cost of quality? What are the components?

A

total cost associated with preventing defects and correcting observed defects

cost of conformance = preventing defects

cost of nonconformance = correcting defects

55
Q

List and describe estimating techniques

A

Bottom-up: estimating at most granular level
Analogous: uses historically similar projects
Parametric: uses statistical cost relationships (pipe cost is $x/ft)
3-point: triangular (O+M+P)/3 or PERT/beta (O+4M+P)/6

56
Q

What are the types of reserves?

A

Contingency: included in cost baseline
Management: money for unknown risks, not controlled by the PM, not in cost baseline

both are included in the project budget

57
Q

Define ‘quality’

A

degree to which characteristics fulfill requirements

58
Q

what is the difference between quality control and quality assurance?

A

control: ensuring the finished product meets expectations

assurance: ensuring the correct processes are followed (not checking the thing that is being worked on)

59
Q

What does it mean if a regulation is ‘de facto’

A

it is widely accepted but not required by law

60
Q

What is a control chart?

A

measures the stability of a process over time

plots the outcome against specification limits to see if the outcome is within the limits and is ‘in control’

61
Q

What are the visual aides uses to measure quality?

A

fishbone diagram, scatter diagram, control chart, pareto chart

62
Q

What is a ‘turnkey’ project?

A

entire project is sub-contracted but is ran by the buyer’s project manager

63
Q

What are the traditional types of contracts?

A

Fixed price - can include incentives or provisions for economic adjustments (inflation)

Time and materials - buyer pays on a per-hour or per-unit basis, can includes reimbursement for expenses

Cost reimbursable - buyer pays for service plus all costs incurred by the seller, can include an additional fee paid to the seller

64
Q

What are the agile types of contracts

A

capped time - work is stopped after a certain amount of time

Target cost - work until you run out of money

incremental delivery - example: 1st release = capped, 2nd = target

65
Q

Explain the types of PMOs

A

PMO = project management office

supporting - consults, offers templates and best practices

controlling - mid-level control, guides and enforces compliance

directive - high-level control, directive PMO manages project

66
Q

List methods of handling conflict

A

Problem-solving - proactive, direct, common answer on exam

collaboration - second-favorite answer

compromise
forcing
smoothing
withdrawal

67
Q

How are contingency reserves and management reserves different?

A

contingency reserves - part of the cost baseline, for ‘known unknowns’

management reserves - outside of the cost baseline, for ‘unknown unknowns’

68
Q

What is the Deming cycle?

A

plan-do-check-act cycle

takes an incremental and iterative approach to quality management that can reduce variations in a process and reduces waste

69
Q

Is multitasking a favorable approach in project management?

A

No

multitasking = ‘switch tasking’, results in inefficiency and waste

70
Q

What are some reasons for a project to close?

A

met all objectives
no longer feasible due to requirements changes
funding no longer available
risks render the project impossible
organization no longer needs the project
external factors make the project obsolete (new law fixes the problem that the project would have fixed)

71
Q

At what point should procurements be closed?

A

anytime the terms of the procurement have been satisfied by both the buyer and seller AND the bill has been paid- CAN OCCUR AT ANY POINT IN THE LIFE OF THE PROJECT

72
Q

What types of risks could be encountered?

How are risks identified?

A

positive risk = opportunity

negative risk = threat

risks are written as if/then statements

when identifying, focus on the risk itself, NOT THE IMPACT (the impact is not the risk)

individual risk = affects certain objectives

overall risk = affects the project as a whole

variability risk - uncertainty about a key characteristic (team member’s productivity)

ambiguity risk - uncertainty about future events (weather, inflation)

secondary risk - unintended consequence of a risk response (I’m hiding from something, but I don’t have any food in here)

73
Q

How can a risk register be organized?

A

in a decomposed, risk breakdown structure

74
Q

What are the risk identification frameworks?

A

PESTLE - political, legal

TECOP - technical, operational

VUCA - volatility

75
Q

What are the risk classification approaches?

A

effect-based: think of potential project impacts, then think of risks that could cause those impacts

source-based: think of trigger events that lead to risks, then identify those risks that come from the trigger event

in both cases you are starting with something that is not the risk, and then working either forwards or backwards to figure out the risk

76
Q

What is a product roadmap?

A

a document that paints a picture of what value will be delivered and when

77
Q

How do you calculate total communication channels on a team?

A

N(N-1)/2

N = total number of team members, INCLUDING YOURSELF!!!!!!

“you are leading a team of seven”, then you have a team of 8!

78
Q

What are the parts of a communication model?

A

encoding –> transmitting –> decoding

79
Q

What does a lack of feedback imply?

A

acceptance

80
Q

What is a functional manager?

A

a manager who’s subordinates are added to a project team, resulting in the functional manager becoming a stakeholder in the project

81
Q

What are the 5 levels of engagement?

A

unaware, resistant, neutral, supportive, leading

commonly used in a stakeholder engagement matrix

82
Q

What is the difference between an artifact and a project document

A

a project document defines and supports the project

an artifact is created during the project (ex. lessons learned register, sprint backlog, product roadmap, product backlog)

83
Q

What are the steps in the change control system?

A

change identification, document the change, analyze the impact of the change, approve or reject the change, implement the change

84
Q

What are the types of change requests?

A

corrective, preventative, repair (ex: budget), update

85
Q

What are the common leadership styles?

A

Laissez-Faire: hands off, checked out
Transactional: focus on goals and feedback, manage when necessary
Servant Leader: serves the team primarily
Transformational: empowers followers by promoting ideas
Charismatic: inspires through personality
interactional: combination of other styles

86
Q

What visualisations can be used to show stakeholder power?

A

Power/interest grid (scatter plot)
Power/interest/attitude (3-D plot)
salience model (vin diagram with 3 circles: power, legitimacy, urgency)

87
Q

Explain colocation

A

entire team is physically in the same room

PMI likes this, allows passive communication through teammates that can be value and not otherwise realized

‘war room’, ‘situation room’, ‘tight matrix’

88
Q

What is the Tuckman ladder?

A

shows the 5 stages of team development

forming / storming / norming / performing / adjourning

89
Q

How do you calculate EAC? ETC?

A

You need EAC to calculate ETC.

Estimate at completion is your adjusted budget.

Estimate to complete is the adjusted budget less what has been spent so far.

EAC = estimate at completion = budget at completion / cost performance index

and cost performance index = earned value / actual cost

ETC = estimate to complete = estimate at completion - actual cost so far

90
Q

What is value stream mapping?

A

looks at time associated with individual processes and places to reduce time, improve flow of info or material needed to produce a product

91
Q

3 questions to answer at the daily stand up?

A

what has been done since last meeting
what needs to be done before the next meeting
what does anyone need help with

92
Q

What are the parts of active listening?

A

Reflecting: “so, what you’re saying is….”

Attending: eye contact, constant engagement

Following: respond verbally or nonverbally

93
Q

non-functional vs functional requirements

A

non-functional: requirements for the product to work (wind for a wind turbine)

functional: parts needed for the product to work (wind turbine blades)

94
Q

formula for present value

A

PV = 1/(1+i)^n x future value

95
Q

What is on the y-axis of a chart showing results from a monte carlo simulation?

A

cumulative probability

96
Q

Describe a PM’s power in different organizational structures

A

Functional structure: PM has least power

Matrix structure

Project-oriented structure: PM has most power

97
Q

Describe a PM’s power in different types of of PMOs

A

PMO = project management office

supportive: PM has least power

controlling

directive: PM has most power

98
Q

What are the 5 phases of Six Sigma?

A

Define
Measure
Analyze
Improve
Control

Figure out the problem, collect data, understand data, improve the situation, maintain the improvement