PMP Exam Flashcards

Pass the Exam

1
Q

Product definition

A

is an artifact, is quantifiable, and can be either an end item in itself or a component item. Additional words for products are materials and goods.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Triangular & Beta distribution

A

Used to calculate activity duration, use three estimates. Expected Duration = (O + M + P)/3

1) Optimistic Estimate
2) Pessimistic Estimate
3) Most Likely Estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

PERT

A

Program Evaluation and Review Technique
Most likely estimate by giving weightage
Expected Duration = (O +4M + P)/6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Low standard deviation and High standard deviation

A

Low: data points are close to the mean of the data set (average)
High: data points are spread out across the board

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Standard deviation equation

A

SD= (Pessimistic Value - Optimistic value)/6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Variance equation

A

SD^2

standard deviation squared

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Critical Path

A

Longest path duration

Has zero float so activities on it will also have zero float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Total Float

A

The amount of time the tasks on the non-critical path can be delayed without affecting the project schedule ; also known as float or slack

Late finish - early finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Free Float

A

the amount of time that an activity is delayed by without affecting the early start of the next activity

Free Float of Activity X = Early start of next activity - early finish of activity x - 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Early Start

A

the earliest time when an activity can be started

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Early Finish

A

The earliest time when an activity can be completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Late Start

A

The latest time when an activity can be started

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Late Finish

A

The latest time when an activity can be completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Activity Duration & equation

A

the amount of time taken by an activity on a network diagram to complete itself

Duration = early finish - early start + 1
OR
Duration = late finish - late start + 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The precedence diagram activities have four types of dependencies, what are they?

A

Start to Finish - The second activity cannot be finished until the first activity starts (least common)
Finish to Start - The next activity cannot be started until the first completes (most common)
Start to Start - the second activity cannot start until the first activity starts, both start simultaneously
Finish to Finish - the second activity cannot finish until the first activity finishes, both finish simultaneous

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Schedule Variance

A

tells you whether you are ahead or behind of schedule.

SV = Earned Value - Planned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

If a schedule variance is positive you are…

A

ahead of schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

If a schedule variance is negative you are

A

behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

If a schedule variance is 1 you are _ When a project is completed the schedule variance becomes _

A

on schedule

zero

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Cost Variance

A

tells you whether you are under budget or over budget

CV = Earned Value - Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

If a cost variance is positive you are

A

over budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

If a cost variance is negative you are

A

under budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

If a cost variance is zero you are

A

on budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Schedule Performance Index

A

Tells you how efficiently you are progressing compared to planned progress

SPI = Earned Value/ Planned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

If Schedule Performance is greater than one

A

you are ahead of schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

If schedule performance is less than one

A

you are behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

If schedule performance is 1

A

all work is completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Cost Performance Index

A

Helps you analyze the cost performance of the project

CPI = Earned Value/ Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

If the cost performance index is one

A

you are on budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

If the cost performance index is greater than one

A

you are under budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

If cost performance index is less than one

A

you are over budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

In Cost Performance Index you have three project forecasting tools

A

Estimate at Completion
Estimate to Complete
To Complete Performance Index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Estimate at Completion (EAC)

A

The amount of money the project will cost you when all is said and done
EAC = BAC (budget at completion) /CPI (cost performance index)
OR
EAC =AC + (BAC - EV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Estimate to Complete (ETC)

A

The estimated money you’ll have to spend to complete the remaining work
ETC=EAC-Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

To complete performance Index (TCPI)

A

Gives you the future cost performance index that you must follow for the remaining work if you want to complete it within a given budget (TCPI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

TCPI equation (when under budget & over budget)

A

To complete performance index
TCPI =remaining work/remaining funds
TCPI under budget: (BAC - EV) / (BAC-AC)
TCPI over budget: (BAC - EV) / (EAC - AC)

BAC budget at completion
EV Earned Value
AC actual cost
EAC = estimate at completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

How to find remaining work equation - when over budget

A

RW =BAC ( budget at completion) - EV (earned value)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

How to find remaining work equation - when under budget

A

RW = BAC (budget at completion) - AC (actual cost)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

Budget at Completion (BAC)

A

Total budget allotted to the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

Actual Cost (AC)

A

Total cost spent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

Planned Value (PV)

A

BAC (budget at completion) * % planned completed work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

Earned Value (EV)

A

EV = BAC (budget at completion) *% actual work completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

Project budget equation

A

Project budget = project cost +contingency reserve +management reserve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

What is the definitive estimate of a project?

A

-5% to 10% of the estimated budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

Variance at Completion (VAC)

A

VAC = BAC - EAC

budget at completion - estimate at completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

Communication Channels Formula

A

Communication channels = n * (n-1)/2

n is the number of stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

Expected Monetary Value (EMV)

A

Probability * Impact

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

Procurement Contract has 3 categories

A
  1. ) Fixed Price
  2. ) Cost Reimbursable
  3. ) Time and Material
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

Fixed Price Contracts can be broken down into 3 more pieces

A
  1. ) Firm Fixed Price (FFP)
  2. ) Fixed Price Incentive Fee (FPIF).
  3. ) Fixed Price with Economic Price Adjustment ( FP -EPA)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

Point of Total Assumption

A

PTA = ((ceiling price - target price) / buyers share ratio) + target cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

Cost Reimbursable Contract has 4 parts

A
  1. ) Cost Plus Fixed Fee Contract (CPFF)
  2. ) Cost Plus Incentive Fee (CPIF)
  3. ) Cost Plus Award Fee (CPAF)
  4. ) Cost Plus Percentage of Cost (CPPC)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

Share Ratio

A

buyer ratio/seller ratio

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

Future Value formula

A
FV = Present Value (1+r)^n
r= interest rate
n = time period
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

At IRR, Net Present Value will be

A

zero, always

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

highest IRR is always

A

better

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

Payback period

A

PBP = total cash out / average per period cash in

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

Accuracy

A

within the quality management system, the assessment of correctness

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

Acquisition

A

obtaining human and material resources necessary to perform project activities. Implies cost of resources, not necessarily financial

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

Activity

A

a distinct, scheduled portion of work performance during the course of a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

Activity duration estimates

A

the quantitative assessments of the likely number of time periods that are required to complete an activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

Activity List

A

a documented tabulation of schedule activities that shows the activity description, activity identifier and a sufficiently detailed scope of work description so project team members understand what work is to be performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

Affinity Diagram

A

a technique that allows large numbers of ideas to be classified into groups for review and analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

Alternative Analysis

A

a technique used to evaluate identified options in order to select the options or approaches to use to execute and perform the work of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

Analogous Estimating

A

A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

Attribute Sampling

A

Method of measuring quality that consists of noting the presence (or absence) of some characteristic (attribute) in each of the units under consideration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

Backward Pass

A

a critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

Basis of Estimate

A

Supporting documentation outlining the details used in establishing project estimates such as assumptions, constraints, level of detail, ranges and confidence levels

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

Bid Documents

A

all documents used to solicit information, quotations or proposals from prospective sellers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

Bidder Conference

A

The meetings with prospective sellers prior to the preparation of a bid or proposal to ensure all prospective vendors have a clear and common understanding of the procurement. Also known as contractor conferences, vendor conferences or pre bid conferences

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
70
Q

Bottom-Up Estimating

A

a method of estimating project duration or cost by aggregating the estimates of the lower level components of the WBS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
71
Q

Business Case

A

a documented economic feasibility study used to establish validity of the benefits of a selected component lacking sufficient definition and that is used as a basis for the authorization of further project management activities. may be used before project initiation and may result in a go/no-go decision for the project.

most commonly used to create the project charter.

Determines if expected outcomes of the project justify the required investment. Business need and cost benefit analysis are contained in this.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
72
Q

Cause and Effect Diagram

A

a decomposition technique that helps trace an undesirable effect back to its root cause

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
73
Q

Change Control Tools

A

Manual or automated tools to assist with change and/or configuration management. Tools should support the CCB activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
74
Q

Change Management Plan

A

a component of the project management plan that establishes the change control board, documents the extent of its authority, and describes how the change control system will be implemented

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
75
Q

Checklist Analysis

A

a technique for systematically reviewing materials using a list for accuracy & completeness

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
76
Q

Checksheets

A

a tally sheet that can be used as a checklist when gathering data

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
77
Q

Claim

A

A request, demand, or assertion of rights by the seller against a buyer or vice versa, for consideration, compensation, or payment under the terms of a legally binding contract, such as for a disputed change

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
78
Q

Code of Accounts

A

a numbering system used to uniquely identify each component of the work breakdown structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
79
Q

Communications Management Plan

A

a component of the project, program or portfolio management plan that describes how, when, and by whom information about the project will be administered and disseminated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
80
Q

Conduct Procurements

A

the process of obtaining seller responses, selecting a seller and awarding a contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
81
Q

Configuration Management Plan

A

A collection of procedures used to track project artifacts and monitor and control changes these artifacts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
82
Q

Context Diagram

A

a visual depiction of the product scope showing a business system (process, equipment, computer system) and how people and other systems interact with it

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
83
Q

Contract Change Control System

A

the system used to collect, track, adjudicate and communicate changes to a contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
84
Q

Control

A

comparing actual performance with planned performance, analyzing variances, assessing trends to effect process improvements, evaluating possible alternatives and recommending appropriate corrective action as needed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
85
Q

Control Account

A

A management control point where scope, budget, actual cost and schedule and integrated and compare to earned value for performance measurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
86
Q

Control Chart

A

the process of monitoring the status of the project to update the project costs and manage changes to the cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
87
Q

Control limits

A

the area composed of three standard deviations on either side of the centerline or mean of a normal distribution of data plotted on a control chart, which reflects the expected variation in the data

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
88
Q

Cost Baseline

A

the approved version of the time-phased project budget, excluding any management reserves, which can be changed only through formal change control procedures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
89
Q

Cost Management Plan

A

a component of a project or program management plan that describes how costs will be planned, structured & controlled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
90
Q

Cost Plus Award Fee Contract (CPAF)

A

A category of contract that involves payments to the seller for all legitimate actual costs incurred for completed work, plus an award fee representing seller profit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
91
Q

Cost Plus Fixed Fee Contract (CPFF)

A

a type of cost reimbursable contract where the buyer reimburses the seller for the sellers allowable costs plus a fixed amount of profit (fee)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
92
Q

Cost Plus Incentive Fee Contract (CPIF)

A

a type of cost reimbursable contract where the buyer reimburses the seller for the sellers allowable costs, and the seller earns its profit if it meets defined performance criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
93
Q

Crashing

A

a technique used to shorten the schedule for the least incremental cost by adding resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
94
Q

Create WBS

A

the process of subdividing project deliverables and project work into smaller, more manageable components

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
95
Q

Critical Path Method (CPM)

A

a method used to estimate the minimum project duration and determine the amount of schedule flexibility on the logical network paths within the schedule model

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
96
Q

Decision Tree Analysis

A

a diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
97
Q

Earned Value Management

A

a methodology that contains scope, schedule and resource measurements to asses project performance & progress

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
98
Q

Develop Project Charter

A

the process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
99
Q

Diagramming Techniques

A

approaches to presenting information with logical linkages that aide in understanding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
100
Q

Discrete Effort

A

An activity that can be planned and measured and that yields a specific output

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
101
Q

Discretionary Dependency

A

a relationship that is established based on knowledge of best practices within a particular application area or an aspect of the project where a specific sequence is desired

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
102
Q

Estimate Activity Durations

A

the process of estimating the number of work periods needed to complete individual activities with the estimated resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
103
Q

Explicit Knowledge

A

Knowledge that can be codified using symbols such as words, numbers and pictures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
104
Q

External Dependency

A

a relationship between project activities and non project activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
105
Q

Fallback plan

A

an alternative set of actions and tasks available in the even that the primary plan needs to be abandoned because of issues, risks or other causes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
106
Q

Fast Tracking

A

A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
107
Q

Firm Fixed Price Contract (FFP)

A

a type of fixed price contract where the buyer pays the seller a set amount regardless of the sellers costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
108
Q

Fixed Price Incentive Fee (FPIF) contract

A

a type of contract where the buyer pays the seller a set amount and the seller can earn an additional amount if the seller meets defined performance criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
109
Q

Fixed Price with Economic Price Adjustment (FPEPA) Contract

A

a fixed price contract but with a special provision allowing for predefined final adjustments to the contract price due to changed conditions, such as inflation changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
110
Q

Forecast

A

an estimate or prediction of conditions and events in the projects future based on information and knowledge available at the time of the forecast

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
111
Q

Forward Pass

A

a critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the projects start date or a given point in time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
112
Q

Free Float

A

the amount of time that a schedule activity can be delayed without delay the early start date of any successor or violating a schedule constraint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
113
Q

Functional Organization

A

an organizational structure in which staff is grouped by areas of specialization and the project manager has limited authority to assign work and apply resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
114
Q

Funding Limit Reconciliation

A

the process of comparing the planned expenditure of project funds against an limits on the commitment of funds for the project to identify any variances between the funding limits and the planned expenditures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
115
Q

Grade

A

a category or rank used to distinguish items that have the same functional use but do not share the same requirements for quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
116
Q

Histogram

A

a bar chart that shows the graphical representation of numerical data

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
117
Q

Imposed Date

A

a fixed date imposed on a schedule activity or schedule milestone, usually in the form of a start no earlier than…and finish no later than.. date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
118
Q

Independent Estimate

A

a process of using a third party to obtain and analyze information to support prediction of cost, schedule or other items

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
119
Q

Influence Diagram

A

a graphical representation of situations showing casual influences, time ordering of events and other relationships among variables and outcomes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
120
Q

Information Management System

A

facilities, processes, and procedures used to collect, store and distribute information between producers and consumers of information in physical or electronic format

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
121
Q

Inspection

A

Estimation of work product to determine whether it conforms to documented standards

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
122
Q

Invitation for Bid (IFB)

A

Generally, the term is equivalent to request for proposal. However in some application areas it may have a narrower or more specific meaning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
123
Q

Lag

A

the amount of time whereby a successor activity will be delayed with respect to a predecessor activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
124
Q

Lead

A

the amount of time whereby a successor activity can be advanced with respect to a predecessor activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
125
Q

Level of Effort (LOE)

A

an activity that does not produce definitive end products and is measured by the passing of time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
126
Q

Make or Buy Analysis

A

the process of gathering an organizing data about product requirements and analyzing them against available alternatives including the purchase or internal manufacture of the product

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
127
Q

Make of Buy Decisions

A

decisions made regarding the external purchase or internal manufacture of a product

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
128
Q

Management Reserve

A

an amount of the project budget or project schedule held outside of the performance management baseline for management control purposes, that is reserved for unforeseen work that is within scope of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
129
Q

Mandatory Dependency

A

a relationship that is contractually required or inherent in the nature of work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
130
Q

Master Schedule

A

a summary level project schedule that identifies the major deliverables and work breakdown structure components and key schedule milestones

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
131
Q

Matrix Diagrams

A

a quality management and control tool used to perform data analysis within the organizational structured created in the matrix. This seeks to show the strength of relationships between factors, causes, and objectives that exist between the rows and columns that form the matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
132
Q

Matrix Organization

A

Any organizational structure in which the project manager shares responsibility with the functional managers for assigning priorities and for directing work of person assigned to the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
133
Q

Mind Mapping

A

a technique used to consolidate ideas created through individual brainstorming sessions into a single map to reflect commonality and differences in understanding and to generate new ideas

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
134
Q

Monitoring &; Controlling Process Group

A

Those processes required to track, review, and regulate the progress and performance of the project, identify any areas in which changes to the plan are required and initiate the corresponding changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
135
Q

Monte Carlo Simulation

A

An analysis technique where a computer model is iterated many times, with the input values chosen at random for each iteration driven by the input data, including probability distributions and probabilistic branches. Outputs are generated to represent the range of possible outcomes for the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
136
Q

Multicriteria Decision Analysis

A

This technique utilizes a decision matrix to provide a systematic analytical approach for establishing criteria such as risk levels, uncertainty and valuation to evaluate and rank many ideas

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
137
Q

Network Logic

A

all activity dependencies in a project schedule network diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
138
Q

Network Path

A

a sequence of activities connected by logical relationships in a project schedule network diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
139
Q

Node

A

a point at which dependency lines connect on a schedule network diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
140
Q

Nominal Group Technique

A

a technique that enhances brainstorming with a voting process used to rank the most useful ideas for further brainstorming and prioritization

four steps

  1. ) question or problem is posed to the group, each person writes down their ides
  2. ) moderator writes down the ideas on a flip chart
  3. ) each recorded idea is discussed
  4. ) individuals vote privately to prioritize the ideas on a scale 1-5
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
141
Q

Opportunity

A

Risk that would have a positive effect on the project’s outcome

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
142
Q

Organizational Breakdown Structure

A

a hierarchal representation of the project organization which illustrates the relationship between project activities and organizational units that will perform those activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
143
Q

Parametric Estimating

A

an estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
144
Q

Path Convergence

A

a relationship in which a schedule activity has more than one predecessor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
145
Q

Path Divergence

A

a relationship in which a schedule activity has more than on successor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
146
Q

Performance Measurement Baseline

A

Integrated scope, schedule and cost baselines used for comparison to mange, measure and control project execution

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
147
Q

Perform Qualitative Risk Analysis

A

The process of prioritizing individual project risks for further analysis or action by assessing their probability of occurrence and impact as well as other characteristics

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
148
Q

Perform Quantitative Risk Analysis

A

the process of numerically analyzing the contained effect of identified individual project risks and other sources of uncertainty

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
149
Q

Planning Package

A

a work breakdown structure component below the control account with known work content but without detailed scheduled activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
150
Q

Planning Process Group

A

the processes required to establish the scope of the project, refine the objectives and define the course of action required to attain the objectives that the project was undertaken to achieve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
151
Q

Plurality

A

Decisions made by the largest block in a group, even if a majority is not achieved

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
152
Q

Portfolio

A

Projects, programs, subsidiary portfolios and operations managed as a group to achieve strategic decisions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
153
Q

Portfolio Management

A

The centralized management of one or more portfolios to achieve strategic objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
154
Q

Precedence Diagramming Method (PDM)

A

a technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
155
Q

Probability and Impact Matrix

A

a grid for mapping the probability of occurrence of each risk and its impact on project objectives if that risk occurs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
156
Q

Procurement documents

A

The documents utilized in bid and proposal activities, which include the buyers invitation for bid, invitation for negotiations, request for information, request for proposal, and sellers responses

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
157
Q

Procurement Documentation

A

all documents used in signing, executing and closing an agreement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
158
Q

Procurement Management Plan

A

A component of the project or program management plan that describes how a project team will acquire goods and services from outside of the performing organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
159
Q

Procurement Statement of Work

A

Describes the procurement item in sufficient detail to allow prospective sellers to determine if they are capable of providing the products, services or results

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
160
Q

Procurement Strategy

A

the approach by the buyer to determine the project delivery method and the type of legally binding agreements that should be used to deliver the desired results

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
161
Q

Program

A

Related projects, subsidiary programs, and program activities that are managed in a coordinated manner to obtain benefits not available from managing them individually

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
162
Q

Program Management

A

the application of knowledge, skills and principles to a program to achieve the program objectives and obtain benefits and control not available by managing program components separately

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
163
Q

Project

A

a temporary endeavor undertaken to create a unique product, service or result

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
164
Q

Project Charter

A

a document issues by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager authority to apply organizational resources to project activities

if external project, a contract is usually preferred, project charter may still be used to establish internal agreements within the org

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
165
Q

Project Funding Requirements

A

Forecast project costs to be paid that are derived from the cost baseline for total or periodic requirements, including projected expenditures plus anticipated liabilities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
166
Q

Project Governance

A

The framework, functions, and processes that guide project management activities in order to create a unique product, service or result to meet organizational, strategic and operational goals

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
167
Q

Project Initiation

A

Launching a process that can result in the authorization of a new project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
168
Q

Project Management

A

the application of knowledge, skills, tools and techniques to project activities to meet the project requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
169
Q

Project Manager Body of Knowledge

A

A term that describes the knowledge within the profession of project management. Includes proven traditional practices that are widely applied as well as innovative practices that are emerging

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
170
Q

PMO

A

A management structure that standardizes the project related governance processes and facilitates the sharing of resources, methodologies, tools and techniques

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
171
Q

Project Procurement Management

A

includes the processes necessary to purchase or acquire products, services or results needed from outside the project team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
172
Q

Project Schedule Network Diagram

A

a graphical representation of the logical relationships among the project schedule activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
173
Q

Project Team Directory

A

a documented list of project team members, their project roles and communication information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
174
Q

Proposal Evaluation Techniques

A

the process of reviewing proposals provided by suppliers to support contract award decisions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
175
Q

Quality

A

the degree to which a set of inherent characteristics fulfills requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
176
Q

RACI Chart

A

a common type of responsibility assignment matrix that uses responsible, accountable, consult and inform statuses to define the involvement of stakeholders to project activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
177
Q

Regression Analysis

A

an analytical technique where a series of input variables are examined in relation to their corresponding output results in order to develop a mathematical or statistical relationship

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
178
Q

Request for Information (RFI)

A

buyer requests a potential seller to provide various pieces of information related to a product or service or seller capability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
179
Q

Request for Proposal (RFP)

A

used to request proposals from prospective sellers of products or services. In some application areas, it may have a narrower or more specific meaning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
180
Q

Request for Quotation (RFQ)

A

request price quotations from prospective sellers of common or standard products or services. Sometimes used in place of request for proposal and in some application areas it may have a narrower or more specific meaning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
181
Q

Requirements Traceability Matrix

A

a grid that links product requirements from the origin to the deliverables that satisfy them

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
182
Q

Reserve Analysis

A

an analytical technique to determine the essential features and relationships of components in the project management plan to establish a reserve for the schedule duration, budget, estimated cost, or funds for a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
183
Q

Residual Risk

A

the risk that remains after risk responses have been implemented

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
184
Q

Resource Breakdown Structure

A

a hierarchical representation of resources by category and type

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
185
Q

Resource Calendar

A

a calendar that identifies the working days and shifts upon which each specific resource is available

186
Q

Resource Histogram

A

a bar chart showing the amount of time that a resource is scheduled to work over a series of time periods

187
Q

Resource Leveling

A

Resource optimization technique in which adjustments are made to the project schedule to optimize the allocation of resources and which may affect critical path

188
Q

Resource Optimization Technique

A

activity start and finish dates are adjusted to balance demand for resources with the available supply

189
Q

Resource Smoothing

A

free and total float are used without affecting the critical path.

190
Q

Rework

A

action taken to bring a defective component into compliance with requirements or specifications

191
Q

Risk Acceptance

A

project team decides to acknowledge the risk and not take any action unless the risk occurs

192
Q

Risk audit

A

audit to consider the effectiveness of the risk management process

193
Q

Risk Avoidance

A

project team acts to eliminate the threat or project the project from its impact

194
Q

Risk Categorization

A

organization by sources of risk, the area of the project affected, or other useful category to determine the areas of the project most exposed to the effects of uncertainty

195
Q

Risk Data Quality Assessment

A

technique to evaluate the degree to which the data about risks is useful for risk management

196
Q

Risk Enhancement

A

A risk response strategy whereby the project team acts to increase the probability of occurrence or impact an opportunity

197
Q

Risk Escalation

A

a risk response strategy whereby the team acknowledges that a risk is outside of its sphere of influence and shifts the ownership of that risk to a higher level of the organization where it is more effectively managed

198
Q

Risk Exploiting

A

a risk response strategy whereby the project team acts to ensure that an opportunity occurs

199
Q

Risk Exposure

A

an aggregate measure of the potential impact of all risks at any given point in time in a project, program or portfolio

200
Q

Risk Sharing

A

a risk response strategy whereby the project team allocates ownership of an opportunity to a third party who is best to capture the benefit of that opportunity

201
Q

Risk Transference

A

Project team gives risk to third party

202
Q

Schedule Forecasts

A

estimates or predictions of conditions and events in the projects future based on information and knowledge available at the time the schedule is calculated

203
Q

Schedule Network Analysis

A

identify early and late start dates, as well as early and late finish dates for the uncompleted portions of project activities

204
Q

Schedule Performance Index

A

measurement of schedule efficiency expressed as a ratio

205
Q

Scope Baseline

A

approved version of a scope statement, WBS and WBS dictionary

206
Q

Secondary Risk

A

a risk that arises as a direct result of implementing a risk response

207
Q

Seller Proposals

A

formal responses from sellers to a request for proposal or other procurement document specifying the price, commercial terms of sale, and technical specifications or capabilities the seller will do for the requesting organization that, if accepted, would bind the seller to perform the resulting agreement

208
Q

Sensitivity Analysis

A

An analysis technique to determine which individual project risk or other sources of uncertainty have the most potential impact on project outcomes, by correlating variations in project outcomes with variations in elements of a quantitative risk analysis model

209
Q

Source Selection Criteria

A

a set of attributes desired by the buyer which a seller is required to meet or exceed to be selected for a contract

210
Q

Specification Limits

A

the area, on either side of the centerline, or mean, of data plotted on a control chart that meets the customers requirements for a product or service. This area may be greater than or less than the area defined by the control limits

211
Q

Statistical sampling

A

Choosing a part of a population of interest for inspection

212
Q

Tacit Knowledge

A

Personal knowledge that can be difficult to articulate and share such as beliefs, experience and insights

213
Q

Team Management Plan

A

component of the resource management plan that describes when and how team members will be acquired and how long they will be needed

214
Q

Test and Evaluation Documents

A

project documents that describe the activities used to determine if the product meets the quality objectives stated in the quality management plan

215
Q

Three Point Estimating

A

estimate cost or duration by applying an average or weighted average of optimistic, pessimistic and most likely estimates when there is uncertainty with the individual activity estimates

216
Q

Threshold

A

a predetermined value of a measurable project variable that represents a limit that requires action to be taken if it is reached

217
Q

Time and Material Contract (T&M)

A

hybrid contractual arrangement containing aspects of both cost reimbursable and fixed price contracts

218
Q

To Complete Performance Index (TCPI)

A

measure of the cost performance that is required to be achieved with the remaining resources in order to meet specified management goal, expressed as the ratio of the cost to finish the outstanding work to the remaining budget

219
Q

Tool

A

something tangible like a template or software program

220
Q

Tornado Diagram

A

special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables

221
Q

Total Float

A

amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating the schedule constraint

222
Q

Trend Analysis

A

uses mathematical models to forecast future outcomes based on historical records

223
Q

Variance Analysis

A

determining the cause and degree of difference between the baseline and actual performance

224
Q

Variance at Completion (VAC)

A

projection of the amount of budget deficit or surplus expressed as the difference between the budget at completion and the estimate at completion

225
Q

WBS Dictionary

A

document that provides detailed deliverable, activity and scheduling information about each component in the work breakdown structure

(code of account identifier, description of work, assumptions and constraints, responsible organization, schedule milestones, associated schedule activities, resources required, cost estimates, quality requirements, acceptance criteria, technical references, agreement information)

226
Q

WBS

A

hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish project objectives and create the required deliverables

227
Q

Work Performance Data

A

raw observations and measurements identified during activities being performed to carry out project work

228
Q

Work Performance Information

A

performance data collected from controlling processes, analyzed in comparison with project management plan components, project documents, and other work performance information

229
Q

Deliverable

A

any unique and verifiable product, result, or capability to perform a service that is required to be produced to complete a process, phase or project

230
Q

Examples of Deliverables

A

a unique product that can be either a component of another item, an enhancement or correction to an item or a new end item in itself.

a unique service or a capability to perform a service

a unique result such as an outcome or document

a unique combination of one or more products, services or results

231
Q

The end of a project is reached when

A

the project objectives have been achieved, the objectives cannot be met, funding is exhausted or no longer available for allocation to the project, the need for the project no longer exists, physical resources are no longer available, project is terminated

232
Q

Projects drive

A

change, move organization to a future state

233
Q

Business benefits may be tangible or intangible (examples of both are)

A

tangible: monetary, fixtures, tools, market shares, utility
intangible: goodwill, trademarks, public benefit, reputation, strategic alignment

234
Q

4 reasons for Project Initiation and examples

A
  1. ) meet regulatory, legal or social requirements
  2. ) satisfy stakeholder requests or needs
  3. ) implement or change business or technological strategies
  4. ) create, improve, or fix products, processes or services
235
Q

A project may be managed in three separate scenarios…

A
  1. ) stand alone project
  2. ) within a program
  3. ) within a portfolio
236
Q

Project

-Define scope, change, planning, management, monitoring & success

A

Scope: projects have defined objectives. Scope is progressively elaborated throughout the project lifecycle
Change: Project managers expect change and implement processes to keep change managed and controlled
Planning: project managers progressively elaborate high level information into detailed plans throughout the project life cycle
Management: PMs manage the project team and objectives
Monitoring: PMs monitor and control the work of producing the products, services or results that the project was undertaken to produce
Success: measured by the product and project quality, timelines, budget, compliance and degree of customer satisfaction

237
Q

Program

-Define scope, change, planning, management, monitoring & success

A

Scope: programs have a scope that encompasses the scope of its program components. Product benefits to an organization by ensuring that the outputs and outcomes of program components are delivered in a coordinated and complimentary manner
Change: Accepts and adapts to change as necessary
Planning: managed using high level plans that track the interdependencies and progress of program components
Management: Managed by Program Managers who ensure program benefits are delivered as expected by coordinating the activities of the program components
Monitoring: Program managers monitor the progress of program components to ensure the overall goals, schedules, budget and benefits of the program will be met
Success: measured by the programs ability to deliver its intended benefits to the organization, and by the programs efficiency and effectiveness in delivering those benefits

238
Q

Portfolio

-Define scope, change, planning, management, monitoring, success

A

Scope: organizational scope that changes with the strategic objectives of the organization
Change: Portfolio managers continuously monitor change in the broader internal and external environments
Planning: Portfolio Managers create and maintain necessary processes and communication relative to the aggregate portfolio
Management: Portfolio Managers may manage or coordinate portfolio management staff, or program ad project staff that may have reporting responsibilities into the aggregate portfolio
Monitoring: Portfolio Managers monitor strate3gic changes and aggregate resource allocation, performance results and risk of the portfolio
Success: measured in terms of aggregate investment performance and benefit realization of the portfolio

239
Q

The aim at portfolio management is to

A

guide organizational investment decisions, select the optimal mix of programs and projects to meet strategic objectives, provide decision making transparency, prioritize team and physical resource allocation, increase the likelihood of realizing the desired return on investment, centralize the management of the aggregate risk profile of all components

240
Q

Operations Management

A

ongoing production of goods/services . Ensures business operations continue efficiently by using optimal resources needed to meet customer demands

241
Q

Projects can intersect with operations at various points during the product life cycle such as

A

when developing a new product, upgrading a product or expanding outputs.
While improving operations or the product development process
At the end of the product life cycle
At each closeout phase

242
Q

Operational Project Management (OPM)

A

A framework in which portfolio, program and project management are integrated with organizational enablers in order to achieve strategic objectives - purpose is to ensure that the organization undertakes the right projects and allocates critical resources appropriately. .Also helps all levels in the organization understand the strategic vision, the initiatives that support the vision, the objectives & deliverables.

243
Q

Project life cycle

A

the series of phases that a project passes through from its start to completion

244
Q

Project Phase

A

a collection of logically related project activities that culminates in the completion of one or more deliverable. Can be described by a variety of attributes (name, number, duration, resource requirements, entrance and exit criteria)

245
Q

Project Management Process Group

A

a logical grouping of project management inputs, tools and techniques, and outputs. Includes initiating, planning, executing, monitoring and controlling, and closing. This is not project phases

246
Q

Development life cycles can be (___, ___, ___ , _____or ___)

A
predictive
iterative
incremental
adaptive
hybrid
247
Q

Predictive life cycle

A

Waterfall

248
Q

Iterative Life Cycle

A

project scope is identified early on, but time and cost estimates are routinely modified as the project teams understanding of the product increases. Iterations develop the product through a series of repeated cycles, while increments successively add to the functionality of the product

249
Q

Incremental Life Cycle

A

deliverable is produced through a series of iterations that successively add functionality within a predetermined time frame

250
Q

Adaptive Life Cycle

A

agile

251
Q

Project life cycles are independent of product life cycles, which may be produced by a project. a product life cycle is…

A

the series of phases that represent the evolution of a product, from concept through delivery, growth , maturity and to retirement.

252
Q

Project Phases may be established based on various factors including

A

management needs, nature of the project, unique characteristics of the organization, industry or technology, project elements including technology, engineering, business, process or legal and decision points.

253
Q

Processes generally fall into one of three categories

A

1) Processes used once or at predefined points in the project (develop project charter, close project)
2. ) Processes that are performed periodically as needed (acquire resources)
3. ) Processes that are performed continuously throughout the project (define activities)

254
Q

Initiating Process Group

A

define a new project or a new phase

255
Q

Executing Process Group

A

performed to complete the work to satisfy project requirements

256
Q

Knowledge Area

A

identified area of project management defined by its knowledge requirements and described in terms of its component processes, practices, inputs, outputs, tools and techniques

257
Q

Ten Knowledge Areas

A
Project Integration Management
Project Scope Management
Project Schedule Management
Project Cost Management
Project Quality Management
Project Resource Management
Project Communications Management
Project Risk Management
Project Procurement Management
Project Stakeholder Management
258
Q

Project Integration Management Knowledge Area

A

includes the processes and activities to identify, define, combine, unify and coordinate the various processes and project management activities within the PM Process groups

259
Q

Project Scope Management Knowledge Area

A

includes the processes required to ensure the project includes all the work required, and only the work required to complete the project successfully

260
Q

Project Cost Management Knowledge Area

A

planning, estimating, budgeting, financing, funding, managing and controlling costs so the project can be completed within the approved budget

261
Q

Project Quality Management Knowledge Area

A

Incorporating the organizations quality policy regarding, planning, managing, and controlling project and product quality requirements. in order to meet stakeholder expectations

262
Q

Project Resource Management Knowledge Area

A

processes to identify acquire and manage the resources needed for the successful completion of the project

263
Q

Project Communications Management Knowledge Area

A

timely and appropriate planning, collection, creation, distribution, storage, retrieval, management, control, monitoring and ultimate disposition of project information

264
Q

Project Risk Management Knowledge Area

A

conducting risk management planning, identification, analysis, response planning, response implementation and monitoring risk on project

265
Q

Project Procurement Management Knowledge Area

A

purchase or acquire products, services or results needed from outside the project team

266
Q

Project Stakeholder Management Knowledge Area

A

identify the people, groups or organizations that could impact or be impacted by the project, to analyze stakeholder expectations and their impact on the project and to develop appropriate management strategies for effectively engaging stakeholders in project decisions and execution

267
Q

Project benefits management plan

A

the documented explanation defining the processes for creating, maximizing, and sustaining the benefits provided by a project

268
Q

In some cases the business case & project benefits management plan are

A

maintained at the program level so project managers need to work with program mangers to ensure the project management documents are aligned with the program documents

269
Q

What precedes the business case

A

Needs assessment. The needs assessment involves understanding business goals and objectives, issues and opportunities and recommending proposals to address them. Results of needs assessment may be summarized in the business case document.

270
Q

Business Case documents…

A

Business Needs (need for action, identification of scope, identification of stakeholders)

Analysis of the situation (identification of organizational strategies, goals, objectives, root causes of the problem, gap analysis, risks, success factors, decision criteria)

Identification of options to consider (do nothing, minimum work, more than min work)

Recommendation

Evaluation (plan for measuring benefits the project will deliver)

271
Q

A business case can present the following three options

A
  1. ) do nothing - business as usual
  2. ) do the minimum work possible to address the problem or opportunity - identifying the set of documented criteria that are key in addressing the problem/opportunity
  3. ) do more than the minimum work possible to address the problem/opportunity
272
Q

Project Benefits Plan includes

A
target benefits
strategic alignment 
timeframe for realizing benefits (benefits by phase, short term, long term)
metrics
assumptions
risks
273
Q

It is possible for a project to be successful from a scope/schedule/budget viewpoint and to be unsuccessful from a

A

business viewpoint. This can occur when there is a change in the business needs or the market environment before the project is completed

274
Q

Enterprise Environmental Factors (EEF)

A
Inputs to many PM processes
organizational culture, structure & governance
geographic distribution of resources & facilities
infrastructure
IT software
Resource availability 
Employee capability 
Marketplace conditions
social & cultural influences
legal restrictions
commercial databases
academic research
government or industry standards
financial considerations
physical environment elements
275
Q

Organizational Process Assets (OPA)

A

lessons from previous projects and historical information (processes, policies, procedures, organizational knowledge bases)

276
Q

Organizational Knowledge Repositories

A

Configuration management knowledge repositories (versions of software and hardware components and baselines of all performing organization standards, policies, procedures and project documents)
Financial data repositories (labor hours, incurred costs, budgets)
Historical information and lessons learned knowledge repositories
Issue and defect management data repositories
Data repositories for metrics used to collect and make available measurement data on processes and products
Project files from previous projects

277
Q

Organizational System

A

collection of various components that together can produce results not obtainable by the individual components alone. The interaction of various system components create the organizational culture & capabilities.

278
Q

Organizational System principals

A

Systems are dynamic, can be optimized, components can be optimized.
systems and their components cannot be optimized at the same time.
Systems are nonlinear in responsiveness

279
Q

Systems are typically the responsibility of

A

an organizations management. Organizations management examines the optimization trade offs between components and the system in order to take the appropriate action to achieve the best outcomes for the organization. PM should look at these results

280
Q

Concept of organizational governance is multidimensional and

A

includes consideration of people, roles, structures and policies.
requires providing direction and oversight through data and feedback

281
Q

Governance is the framework within which authority is exercised in organizations. This framework includes but is not limited to

A

rules, policies, norms, systems, processes, relationships. It influences how objectives of the organization are set and achieved, risk is monitored and assessed, performance is optimized

282
Q

Four governance domains & their functions

A

Alignment, Risk, Performance, Communications

Functions: oversight, control, integration, decision making

283
Q

Management Elements

A

the components that comprise the key functions or principles of general management in the organization. Key functions include division of work, authority given to perform work, responsibility to perform work, discipline of action, unity of command, unity of direction, general goals of the organization take precedence over individual goals, paid fairly for work performed, optimal use of resources, clear communication channels, right materials to the right person for the right job at the right time, fair and equal treatment, clear security of work positions, safety of people in the workplace, open contribution to planning and execution by each person and optimal moral

284
Q

Factors in organization structure selection

A

cost, physical location, delegation capabilities, adaptability of design, simplicity of design, degree of alignment with organizational objectives, span of control, clear path of decisions

285
Q

PMO types

A

Supportive - consultative role to projects by supplying templates, best practices, training, access to information, lessons learned. Serves as a project repository, PMO control is low.
Controlling - provides support and require compliance through various means. The degree of control provided by the PMO is moderative, compliance may involve adoption of project management frameworks or methodologies, use of specific templates, forms and tools and conformance to governance frameworks
Directive - take control of the projects by directly managing the projects. PMs are assigned by and report to the PMO. Control is high

286
Q

PMO is

A

the natural liaison between the organizations portfolios, programs, projects and the organizational measurement systems

287
Q

The primary function of a PMO is to support PM’s in a variety ways which may include

A

managing shared resources across all projects administered by the PMO, identifying and developing PM methodology, best practices and standards, coaching, mentoring, training, developing and managing project policies, procedures, templates and other shared documentation, coordinating communication across projects

288
Q

Consensus

A

relevant stakeholders support the project decisions and actions even when there is not 100% agreement

289
Q

Independent projects or projects that are part of the same program may impact a project due to

A

demands on the same resources
priorities of funding
receipt or distribution of deliverables
alignment of project goals and objectives with those of the organization

290
Q

in some situations the PM may be an external consultant place…

A

in a temporary management role

291
Q

PM must be aware of the industry, trends include

A

technology development
new and changing market niches
standards
technical support tools
economic forces that impact the immediate project
influences affecting the project management discipline
process improvement and sustainability strategies

292
Q

PM Talent Triangle

A

Technical Project Management
Leadership
Strategic & Business Management

293
Q

Politics involves

A

influence, negotiation, autonomy and power

294
Q

Positional Power

A

(formal, authoritative, legitimate)

formal position granted in the organization or team

295
Q

Informational Power

A

control of gathering or distribution

296
Q

Referent Power

A

respect or admiration others hold for the individual, credibility gained

297
Q

Situational Power

A

gained due to unique situation such as a specific crisis

298
Q

Personal or charismatic power

A

charm

299
Q

Relational Power

A

participates in networking, connections and alliances

300
Q

Expert Power

A

skill, information, possessed, experience, training, education, certification

301
Q

Reward-oriented Power

A

ability to give praise, monetary or other desired items

302
Q

Punitive or coercive power

A

ability to invoke discipline or negative consequences

303
Q

Ingratiating Power

A

application of flattery or other common ground to win favor or cooperation

304
Q

Pressure based power

A

limit freedom of choice or movement for the purpose of gaining compliance to desired action

305
Q

Guilt based power

A

imposition of obligation or sense of duty

306
Q

Persuasive power

A

ability to provide arguments that move people to a desired course of action

307
Q

Avoiding power

A

refusing to participate

308
Q

Top PMs are xxx and xxx when it comes to power

A

proactive and intentional

309
Q

Laissez faire leadership style

A

allowing the team to make their own decisions and establish their own goals, als referred to as taking a hands off style

310
Q

transactional leadership style

A

focus on goals, feedback, and accomplishment to determine rewards; management by exception

311
Q

Servant Leader Leadership Style

A

demonstrates commitment to serve and put other people first, focuses on other people’s growth, learning, development, autonomy and well-being; concentrates on relationships, community and collaboration; leadership is secondary and emerges after service

312
Q

Transformational Leadership Style

A

empowering followers through idealized attributes and behaviors, inspirational motivation, encouragement for innovation and creativity, and individual consideration

313
Q

Charismatic Leadership Style

A

able to inspire, high energy, self confident, holds strong convictions

314
Q

Interactional Leadership Style

A

combination of transactional, transformational & charismatic

315
Q

Three dimensions of complexity for projects

A

System behavior - interdependencies of components and systems
Human behavior - interplay between diverse individuals and groups
Ambiguity

316
Q

Project Integration Management includes making choices about

A

resource allocation, balancing competing demands, examining any alternative approaches, tailoring the processes to meet the project objectives, managing interdependencies among the PM knowledge areas

317
Q

Project Integration Management processes are

A

1.) develop project charter
2.) develop PM plan
3.) direct and manage project work
4.) manage Project knowledge
5.) monitor and control project work
6.) perform integrated change control
7.) close project or phase
PM must do the above, responsibility cannot be transferred

318
Q

Project Integration Management is about

A

ensuring that the deliverable due dates of the product and benefits management plan are aligned. Providing PM plan to achieve objectives. Ensuring the creation of the appropriate knowledge to and from the project as necessary. Managing the performance of changes of the activities in the PM plan. Making integrated decisions regarding key changes to the project. Measuring and monitoring projects progress. Collecting data on the results achieved, analyzing the data to obtain information and communicating this to stakeholders. Completing all work of the project and formally closing each phase, contract and the project. Managing phase transitions when necessary

319
Q

Integration trends

A

use of automated tools (PMIS to collect, analyze and use info)
use of visual management tools
project knowledge management (identifying knowledge throughout the project & transferring it to the target audience)
expanding PM’s responsibilities
Hybrid methodologies

320
Q

A project charter is not considered a

A

contract

321
Q

the business case is created as a result of one or more of the following

A

market demand, organizational need, customer request, technological advance, legal requirement, ecological impacts, social need

322
Q

PM does not update or modify

A

business documents

323
Q

Expert Judgement

A

judgement provided based upon expertise in an application area. Should be used in Organizational strategy, benefits management, technical knowledge, duration and budget estimation, risk identification

324
Q

Focus Group

A

bring together stakeholders and SME to learn about the perceived project risk, success criteria, and other topics in a more conversational way than a one-one interview

325
Q

Meeting Management

A

preparing the agenda, ensuring that a rep for each key stakeholder of the group is invited, preparing and sending meeting minutes

326
Q

Components of a project charter

A
project purpose
measurable project objectives/success criteria
high level requirements
high level project description, boundaries and key deliverables
overall project risk
summary milestone schedule
preapproved financial resources
key stakeholder list
project approval requirements
project exit criteria
assigned PM, responsibility and authority level
name and authority of sponsor
327
Q

Develop PM Plan

A

process of defining, preparing and coordinating all plan components and consolidating them into an integrated project management plan. Key benefit is the production of a comprehensive document that defines the basis of all project work and how the work will be performed.

328
Q

Develop Project Management Plan Inputs

A

Project charter
outputs from other processes
EEF
OPA

329
Q

Develop Project Management Plan Outputs

A

Project Management Plan

330
Q

Develop Project Management Plan tools & techniques

A

expert judgement
Data gathering (brainstorming, checklists, focus groups, interviews)
Interpersonal and team skills (conflict management, facilitation, meeting management)
Meetings (kick off)

331
Q

Project Management Plans include

A

subsidiary management plans (scope management, requirements management, schedule, cost, quality, resource, communications, risk, procurement, stakeholder engagement) and baselines (scope, schedule, cost) and change management plan, configuration management plan, performance measurement baseline, project life cycle, dev approach, management reviews.

332
Q

Develop Project Management Plan, examples of EEF

A

government or industry standards
legal and regulatory requirements/constraints
project management body of knowledge for vertical market and/or focus area (environmental, safety, risk, agile software development)
organizational structure, culture, management practices
organizational governance framework
infrastructure

333
Q

Develop Project Management Plan, examples of OPA

A

organizational standard policies, processes & procedures
PM plan template (guidelines and criteria for tailoring the organizations set of standard processes to satisfy the specific needs of the project and project closure guidelines, product validation, acceptance criteria)
change control procedures
monitoring and reporting methods
risk control procedures
communication requirements
project information from previous similar projects
historical information/lessons learned

334
Q

Develop Project Management Plan, examples of expert judgment

A

tailoring the project management process to meet the project needs, including the dependencies and interactions among those processes and the essential inputs/outputs
developing additional components of the PM plan
determining tools & techniques to be used
developing technical and management details to be included in the PM plan
determining resources and skill levels needed
defining the level of configuration management to apply
determining which project documents will be subject to formal change control process
prioritizing the work on the project to ensure the resources are allocated to the appropriate work at the appropriate time

335
Q

Direct and Manage Project Work Inputs

A
PM plan
Project documents (change log, lessons learned, milestone list, project communications, schedule, requirements traceability matrix, risk register, risk report)
approved change requests
EEF
OPA
336
Q

Direct and Manage Project Work Tools & Techniques

A

Expert Judgement
PMIS
Meetings

337
Q

Direct and Manage Project Work Outputs

A
Deliverables
work performance data
issue log
change requests 
PM plan updates
project document updates (activity list, assumption log, lessons learned, requirements documentation, risk register, stakeholder register)
OPA updates
338
Q

Direct and Manage Project Work

A

executing the planned project activities to complete project deliverables and accomplish establish objectives. Requires review of the impact of all project changes and the implementation of approved changes, corrective action, preventive action and/or defect repair.

339
Q

Direct and Manage Project Work EEF examples

A

organizational structure, culture, management practices
infrastructure
stakeholder risk thresholds

340
Q

Direct and Manage Project Work OPA examples

A

organizational standard policies, processes
issue and defect management defining issue and defect controls, issue and defect identification and resolution, action item tracking
issue and defect management databases containing historical issue and defect status, issue and defect resolution and action item results
performance measurement database used to collect and make available measurement data on processes and products
change control and risk control procedures
project information from previous projects

341
Q

Direct and Manage Project Work Expert Judgement

A
technical knowledge
cost and budget management
legal and procurement
legislation and regulations
organizational governance
342
Q

Change requests can be initiation from

A

inside or outside the project and they can be optional or legally mandated.

343
Q

Change request types

A

Corrective Action
Preventive Action
Defect Repair
Updates

344
Q

Corrective Action Change Request

A

an intentional activity that realigns the performance of the project work with the PM plan

345
Q

Preventive Action Change Request

A

an intentional activity that ensures the future performance of the project work is aligned with the PM plan

346
Q

Defect Repair

A

an intentional activity to modify a nonconforming product or product component

347
Q

Update Change Request

A

changes to formally controlled project documents, plans to reflect modified or additional ideas or content.

348
Q

Manage Project Knowledge

A

process of using existing knowledge and creating new knowledge to achieve the projects objectives and contribute to organizational learning

349
Q

Manage Project Knowledge Inputs

A
PM plan
project documents (lessons learned, project team assignments, resource breakdown structure, stakeholder register) 
deliverables
EEF
OPA
350
Q

Manage Project Knowledge Tools & Techniques

A

expert judgement
knowledge management
information management
interpersonal and team skills (active listening, facilitation, leadership, networking, political awareness)

351
Q

Manage Project Knowledge Outputs

A

Lessons learned
PM plan updates
OPA updates

352
Q

Explicit Knowledge

A

can be readily codified using words, pictures and numbers

353
Q

Tacit Knowledge

A

personal and difficult to express such as beliefs, insights, experiences and know-how

354
Q

Manage Project Knowledge EEF

A

organizational, stakeholder and customer culture
geographic distribution of facilities and resources
organizational knowledge experts
legal and regulatory requirements and/or constraints

355
Q

Manage Project Knowledge OPA

A

organizational standard policies, processes
personal admin (employee training)
organizational communication requirements
formal knowledge sharing and information sharing processes (learning reviews

356
Q

Manage Project Knowledge Expert Judgement

A
knowledge management
information management
organizational learning
knowledge and informational management tools
relevant information from other projects
357
Q

Lessons learned registry is transferred to

A

OPA asset called the lesson learned repository at the end of the manage project knowledge phase

358
Q

Monitor and Control Project Work

A

process of tracking, reviewing and reporting the overall progress to meet the performance objective defined in the project management plan. Benefits are that it allows stakeholders to understand the current state of the project, to recognize the actions taken to address any performance issues and to have visibility into future project status with cost and schedule forecasts

359
Q

Monitor and Control Project Work Inputs

A
Project management plan
Project documents (assumption log, basis of estimates, cost forecasts, issue log, lessons learned register, milestone list, quality reports, risk register, risk report, schedule forecasts) 
work performance information
agreements
EEF
OPA
360
Q

Monitor and Control Project Work Tools & Techniques

A

expert judgement
data analysis (alternative analysis, cost benefit, earned value, root cause, trend, variance)
decision making (voting)
meetings

361
Q

Monitor and Control Project Work Outputs

A

work performance reports
change requests
project management plan updates
project document updates (cost forecasts, issue log, lessons learned register, risk register, schedule forecasts)

362
Q

Control

A

determining corrective or preventive actions or replanning and following up on action plans to determine whether the actions taken resolved the performance issue

363
Q

Monitor and Control Project Work is concerned with

A

Comparing actual project performance against the PM Plan
Assessing performance periodically to determine whether any corrective or preventive actions are indicated
checking the status of project risks
Maintaining an accurate, timely information base concerning the projects products and their associated documentation through project completion
Providing information to support status reporting, progress measurement and forecasting
Providing forecasts to update current cost and schedule information
Providing appropriate reporting on project progress and status to program management when the project is part of an overall program
ensuring that the project stays aligned with the business needs

364
Q

Basis of estimates

A

how the various estimates were derived and can be used to make decisions on how to respond to variances

365
Q

Cost Forecasts

A

if the project is within defined tolerance ranges for budget and to identify any necessary change requests

366
Q

Quality Reports

A

includes quality management issues recommendations for process, project and product improvements; corrective action recommendations and the summary of findings from the control quality process

367
Q

Schedule Forecasts

A

used to determine if the project is within defined tolerance ranges for schedule and to identify any necessary change requests

368
Q

Monitor and Control Project Work EEF

A

project management information systems such as scheduling, cost, resourcing tools, performance indicators, databases, project records & financials
infrastructure
stakeholders expectations and risk thresholds
government or industry standards

369
Q

Monitor and Control Project Work OPA

A

organizational standard policies, processes
financial control procedures (accounting codes, standard contract provisions)
monitoring and reporting methods
issue management procedures defining issue controls, issue identification and resolution and action item tracking
defect management procedures
organizational knowledge base

370
Q

Monitor and Control Project Work Expert Judgement

A

earned value analysis
interpretation and contextualization of data
techniques to estimate duration and costs
trend analysis
technical knowledge on the industry and focus area of the project
risk management
contract management

371
Q

Earned Value Analysis

A

provides an integrated perspective on scope, schedule and cost performance

372
Q

Perform Integrated Change Control

A

process of reviewing all the change requests, approving changes and managing changes to deliverables, project documents and project management plan; and communicating the decisions. The key benefit is that it allows for documented changes within the project to be considered in an integrated manner while addressing overall project risk, which often arises from changes made without consideration of the overall project objectives

373
Q

Perform Integrated Change Control Inputs

A

Project management plan (change management plan, configuration management, scope baseline, schedule baseline, cost baseline)
project documents (basis of estimates, requirements traceability matrix, risk report)
work performance reports
change requests
EEF
OPA

374
Q

Perform Integrated Change Control Tools & Techniques

A

expert judgement
change control tools
data analysis (alternative and cost benefit)
decision making (voting, autocratic decision making, multicriteria decision making analysis)
meetings

375
Q

Perform Integrated Change Control Outputs

A

Approved change requests
project management plan updates
project document updates (change log)

376
Q

before baselines are established, changes are

A

not required to be formally controlled

377
Q

Perform Integrated Change Control EEF

A

legal restrictions such as country or local regulations
government or industry standards
legal and regulatory requirements and/or constraints
organizational governance framework
contracting and purchasing constraints

378
Q

Perform Integrated Change Control OPA

A

change control procedures, including the steps by which organizational standards, policies, plans, procedures or any project documents will be modified and how changes will be approved and validated
procedures for approving and issuing change authorizations
configuration management knowledge base containing the versions and baselines of all official organizational standards, policies, procedures and project documents

379
Q

Perform Integrated Change Control Expert Judgement

A
Technical knowledge
legislation and regulation
legal and procurement
configuration management
risk management
380
Q

Configuration Control

A

focuses on the specification of both the deliverables and the processes, while change control is focuses on identifying, documenting and approving or rejecting changes to the project documents, deliverables or baselines

381
Q

Change Control Tools

A

Identify configuration item
Record and report configuration item status
perform configuration item verification and audit

382
Q

Autocratic decision making

A

one individual takes the responsibility for making decision for the entire group

383
Q

Close Project or Phase

A

finalizing all activities for the project, phase, or contract. The key benefits of this process are the project or phase information is archived, the planned work is completed, the organizational team resources are released to pursue new endeavors

384
Q

Close Project or Phase Inputs

A
project charter
project management plan
project documents (assumption log, basis of estimates, change log, issue log, lessons learned, milestone list, project communications, quality control measures, quality reports, requirements documentation, risk register, risk report)
accepted deliverables 
business documents (business case, business management plan)
agreements
procurement documentation
OPA
385
Q

Close Project or Phase Tools & Techniques

A

expert judgement
data analysis (document analysis, regression analysis, trend analysis, variance analysis)
meetings

386
Q

Close Project or Phase Outputs

A

project document updates (lessons learned)
final product, service or result transition
final report
OPA updates

387
Q

Activities necessary for the administrative closure of the project or phase include

A

actions and activities to satisfy completion or exit criteria for the phase
activities related to the completion of the contractual agreements
activities to collect project records, audit project success, knowledge share, archive project information, transfer projects products, measuring stakeholder satisfaction

388
Q

to close the contract all procurement documentation is collected, indexed and filed. Information on contract schedule, scope, quality and cost performance along with all contract change documentation, payment records, inspection results are catalogued.

A

Truth

389
Q

Close project or phase OPA

A

Project phase closure guidelines or requirements

Configuration management knowledge base containing the versions and baselines of all official organizational standards

390
Q

Close project or phase Expert judgement

A

Management control
Audit
Legal and procurement
Legislation and regulations

391
Q

Close project or phase data analysis

A

Trend analysis
Variance analysis
Regression analysis
Document analysis

392
Q

Close project or phase final report

A

Summary level description of project
Scope objectives, criteria used to evaluate the scope and evidence that the completion criteria were met
Quality objectives to ensure product quality, verification and actual milestone delivery dates and reasons for variances
Cost objectives, actual cost range, actual costs and reasons for any variances
Summary of the validation information for the final product
Schedule objectives
Summary of how the final product achieved business needs identified in the business plan, if not met identify to the degree they were met and when/if they’ll be realized in the future.
Summary of risks or issues encountered and how they were addressed

393
Q

Close project OPAs

A

Project documents
Operational and support documents
Project closure documents
Lessons learned

394
Q

Project scope management processes

A
Plan scope management
Collect requirements 
Define scope
Create WBS
Validate scope
Control scope
395
Q

Plan Scope Management

A

Creating a scope management plan that documents how the project and product scope will be defined, validated and controlled

396
Q

Control Scope

A

Monitoring the status of the project and product scope and managing changes to the scope baseline

397
Q

Product Scope

A

The features and functions that characterize a product

398
Q

Project Scope

A

The work performed to deliver a product with the specified features and functions. Sometimes viewers as including product scope

399
Q

The requirements management process starts with a ____ which may begin in ____,_____ or____

A

Needs assessment
Portfolio planning
Program planning
Within a discrete project

400
Q

Plan Scope Management

A

Process of creating a scope management plan that documents how the project and product scope will be definite, validated and controlled. The key benefit of this process is that is provides guidance and direction on how Scope will be managed

401
Q

Plan Scope Management Inputs

A

Project charter
Project management plan ( quality management plan, project life cycle description, development approach)
EEF
OPA

402
Q

Plan Scope Management Tools and Techniques

A

Expert judgement
Data analysis (alternative analysis)
Meetings

403
Q

Plan Scope Management Outputs

A

Scope management plan

Requirements management plan

404
Q

Quality management plan

A

The way the project and product scope will be managed can be influenced by how the organizations quality policy, methodologies and standards are implemented on the project

405
Q

Plan Scope Management EEF

A

Culture
Infrastructure
Personal admin
Marketplace conditions

406
Q

Scope Management Plan Components

A

Scope statement
Creation of the WBS
Establish scope baseline approval and how it will be maintained
Determine formal acceptance of completed project deliverables

407
Q

Requirements management plan components

A

How requirement activities will be planned, tracked and reported
Configuration management activities (how changes will be initiated, impacts analyzed, taxes, tracked and reported)
Prioritization process
Metrics used
Traceability structure that reflects the requirement attributes captured on the traceability matrix

408
Q

Collect Requirements

A

Determining, documenting and managing stakeholder needs and requirements to meet objectives. The benefit is that it provides the basis for defining the product and project scope

409
Q

Collect Requirements Inputs

A

Project charter
Project management plan (scope management plan, requirements management plan, stakeholder engagement plan)
Project documents (assumption log, lessons learned, stakeholder register)
Business case
AgreementEEF
OPA

410
Q

Collect Requirements Tools and Techniques

A

Expert judgement
Data gathering (brainstorming, interviews, focus groups, questionnaires, benchmarking)
Document analysis
Decision making (voting, autocratic decision making,
Multicriteria decision making)
Data representation (affinity diagram, mind mapping)
Interpersonal and team skills (nominal group technique, observation, facilitation)
Context diagram
Prototypes

411
Q

Collect Requirements Outputs

A

Requirements documentation

Requirements traceability matrix

412
Q

Collect Requirements EEF

A

Culture
Infrastructure
Personnel admin
Marketplace conditions

413
Q

Collect Requirements OPA

A

Policies and procedures

Historical information and lessons learned repository

414
Q

Collect Requirements Expert Judgement

A
Business analysis
Requirements elicitation 
Requirements analysis
Requirements documentation
Project requirements in previous similar projects
Diagramming Techniques 
Facilitation
Conflict management
415
Q

Collect Requirements Data Analysis

A

agreements, business plans, business rules, current process flows marketing literature, problem logs, policies, requests for proposal, use cases

416
Q

Facilitation skills are used in the following situations

A

joint application design/development (JAD)
quality function deployment (QFD)
user stories

417
Q

Joint application Design/Development (JAD)

A

JAD sessions are used in the software development industry. Facilitated sessions focus on bringing business subject matter experts and the dev team together to gather requirements and improve the software development process

418
Q

Quality function deployment (QFD)

A

helps determine critical characteristics for new product development. Starts by collecting customer needs (VOC), these needs are then objectively sorted and prioritized and goals are set to achieve them.

419
Q

Storyboarding

A

is a prototyping technique showing sequence or navigation thorough a series of images or illustrations

420
Q

Functional Requirements

A

describe the behaviors of the product (actions, processes, data and interactions that the product should execute)

421
Q

Nonfunctional Requirements

A

These supplement functional requirements and describe the environmental conditions or qualities required for the product to be effective (security, performance, safety)

422
Q

Transition and readiness requirements

A

temporary capabilities such as data conversion and training requirements

423
Q

Project Requirement examples

A

milestone dates, contractual obligations, constraints

424
Q

Tracing requirements includes but is not limited to

A

business needs, opportunities, goals and objectives
project objectives
project scope and WBS deliverables
product design
product development
test strategy and test scenarios
high level requirements to more detailed requirements

425
Q

Requirements Traceability Matrix attributes

A
unique identifier
text description
rational for inclusion
owner
source
priority
version current status
status date
426
Q

Define Scope

A

process of developing description of the project and product. The key benefit is that it describes the product, service or result boundaries and acceptance criteria

427
Q

Define Scope Inputs

A
Project charter
Project management plan
project documents (assumption log, requirements documentation, risk register)
EEF
OPA
428
Q

Define Scope Tools & Techniques

A
Expert Judgement
Alternative Analysis
Multicriteria decision analysis
Interpersonal and team skills (facilitation)
product analysis
429
Q

Define Scope Outputs

A

project scope statement
project document updates (assumption log, requirements documentation, requirements traceability matrix, stakeholder register)

430
Q

Define Scope EEF

A

organizations culture
infrastructure
personnel admin
marketplace conditions

431
Q

Define Scope OPA

A

policies procedures and templates for a project scope statement
project files from pervious projects
lessons learned from previous projects

432
Q

Product Analysis

A

define products and services. asking questions about product or service and forming answers to describe the user, characteristics and other relevant aspects of what is going to be delivered. examples include (product breakdown, requirements analysis, systems analysis, systems engineering, value analysis and value engineering)

433
Q

Project Scope Statement includes

A

product scope description
deliverables
acceptance criteria
project exclusions

434
Q

Create WBS

A

the process of subdividing project deliverables into smaller and more manageable components. The key benefit of this process is that it provides framework of what has to be delivered

435
Q

Create WBS Inputs

A
project management plan (scope management plan)
project scope statement
requirements documentation
EEF
OPA
436
Q

Create WBS Tools & Techniques

A

expert judgement

decomposition

437
Q

Create WBS Outputs

A

scope baseline
assumption log
requirements documentation

438
Q

Create WBS OPA

A

policies, procedures and templates for the WBS
project files from previous projects
lessons learned from previous projects

439
Q

Decomposition

A

dividing and subdividing the project scope and project deliverables into smaller more manageable pieces. Generally involves identifying and analyzing the deliverables and related work, structuring and organization the WBS, decomposing the upper WBS levels into more detailed components, developing and assigning identification codes to the WBS components and verifying that the degree of decomposition of the deliverables is appropriate

440
Q

The WBS structure can be represented in a number of forms such as

A

using phrases of the project lifecycle as the second level of decomposition, with the product and project deliverables inserted at the third level
using major deliverables as the second level of decomposition
incorporating subcomponents that may be developed by the organizations outside the project team such as contracted work. The seller then develops the supporting contract WBS as part of the contracted work

441
Q

Decomposition of the upper-level WBS components requires

A

subdividing the work for each of the deliverables subcomponents into the most fundamental components, where the WBS components represent verifiable products

442
Q

Decomposition may not be possible for a deliverable or subcomponent that will be

A

accomplished far into the future.

443
Q

100% rule

A

the total of the work at the lowest levels should roll up to the higher levels so that nothing is left out and no extra work is performed

444
Q

Components of the Scope Baseline

A

project scope statement
WBS
Work Package
Planning Package

445
Q

Planning Package

A

work breakdown structure component below the control account and above the work package with known work content but without detailed schedule activities

446
Q

Validate Scope

A

process of formalizing acceptance of the completed project deliverables. The key benefit of this process is that it brings objectivity to the acceptance process and increases the probability of final product acceptance by validating each deliverable

447
Q

Validate Scope Inputs

A
scope management plan
requirements management plan
lessons learned register
quality reports
requirements documentation
requirements traceability matrix
verified deliverables
work performance data
448
Q

Validate Scope Tools & Techniques

A

inspection

voting

449
Q

Validate Scope Outputs

A
accepted deliverables
work performance information
change requests
lessons learned
requirements documentation
requirements traceability matrix
450
Q

Control Scope

A

process of monitoring the status of the project and product scope and managing changes to the scope baseline. the key benefit of this process is that the scope baseline is maintained throughout the project

451
Q

Control Scope Inputs

A
scope management plan
requirements management plan
change management plan
configuration management plan
scope baseline
performance measurement baseline
lessons learned
requirements documentation
requirements traceability matrix
work performance data
OPA
452
Q

Control Scope Tools & Techniques

A

variance analysis

trend analysis

453
Q

Control Scope Outputs

A
work performance information
change requests
scope management plan
scope baseline
schedule baseline
cost baseline
performance measurement baseline
lessons learned
requirements documentation
requirements traceability matrix
454
Q

Control Scope OPA

A

existing formal and informal scope, control related policies, procedures and guidelines
monitoring and reporting methods and templates to be used

455
Q

Control Scope - work performance information

A

includes correlated and contextualized information on how the project and product scope are performing compared to the scope baseline. it can include the categories of the changes received, the identified scope variances and their causes, how they impact schedule or cost and the forecast of the future scope performance

456
Q

Project Schedule Management processes are

A
plan schedule management 
define activities
sequence activities
estimate activity durations
develop schedule
control schedule
457
Q

Plan Schedule Management

A

process of establishing the policies, procedures and documentation for planning, developing, ,managing, executing and controlling the project schedule

458
Q

Define Activities

A

identifying and documenting specific actions to be performed to produce the project deliverables

459
Q

Sequence Activities

A

identifying and documenting relationships among the project activities

460
Q

Control Schedule

A

monitoring the status of the project to update the project schedule and manage changes to the schedule baseline