PMP 2021 Glossary Flashcards

1
Q

80/20 rule

A

A general guideline with many applications; in terms of
controlling processes, it contends that a relatively
large number of problems or defects, typically 80%,
are commonly due to a relatively small number of
causes, typically 20%.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

AB testing

A

A marketing approach used to determine user preferences
by showing different sets of users similar services
with one independent variable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

AC (Actual Cost)

A

The realized cost incurred for the work performed on an activity during a specific time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

accept

A

A strategy for managing negative risks or opportunities
that involves acknowledging a risk and not taking any
action until the risk occurs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

acceptance criteria

A

A set of conditions that is required to be met before

deliverables are accepted.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

active listening

A

A communication technique that involves acknowledging what you hear and clarifying the message to confirm that what you heard matches the message that the sender intended.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

activity attributes

A

Multiple attributes associated with each schedule
activity that can be included within the activity
list.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

activity dependency

A

A logical relationship that exists between two project
activities. The relationship indicates whether the
start of an activity is contingent upon an event or
input from outside the activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

activity duration estimates

A

The quantitative assessments of the likely number of

time periods that are required to complete an activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

activity list

A

A documented tabulation of schedule activities that
shows the activity description, activity identifier,
and a sufficiently detailed scope-of-work description
so project team members understand what work is to be performed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

activity

A

A distinct, scheduled portion of work performed during

the course of a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

administrative closure

A

Involves verifying and documenting project results to

formalize project or phase completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Affinity diagram

A

A technique that allows large numbers of ideas to be

classified into groups for review and analysis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

agile life cycles

A

A project life cycle that is iterative or incremental.
Also referred to as change- driven or adaptive, they
work well in environments with high levels of change
and ongoing stakeholder involvement in a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Agile project management

A

A project management methodology that uses an iterative and incremental approach that focuses on customer value and team empowerment. In agile project management, the product is developed in iterations by small and integrated teams.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Agile release planning

A

A process in which you determine the number of
iterations or Sprints that are needed to complete each
release, the features that each iteration will
contain, and the target dates of each release.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

agreements

A

Any documents or communication that defines the initial intentions of a project. Examples include contracts, memorandums of understanding (MOUs), service level agreements (SLAs), letters of agreement, letters of intent, verbal agreements, email, or other written agreements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

analogous estimating

A

A technique for estimating the duration or cost of an
activity on a project using historical data from a
similar activity or project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

approved change requests

A

Change requests that have been reviewed and approved by the change control board (CCB) and are ready to be scheduled for implementation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

assumption and constraint analysis

A

A process that explores the validity of the project
assumptions within the constraints and identifies risks from any incompleteness or inaccuracy of these project
assumptions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

attribute sampling data

A

Data that is counted such as the number of product

defects or customer complaints.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

auditing

A

An examination of a project’s goals and achievements, including adequacy, accuracy, efficiency,
effectiveness, and the project’s compliance with
applicable methodologies and regulations. It tends to
be a formal, one-sided process that can be extremely
demoralizing to team members.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

autocratic

A

Using this group decision-making method,
one member of the group makes the decision. In most
cases, this person will consider the larger group’s
ideas and decisions and will then make a decision
based on that input.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

avoid

A

A strategy for managing negative risks or threats that
involves changing the project management plan to
remove the risk entirely by extending the schedule,
changing the strategy, increasing the funding, or
reducing the scope.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

BAC

A

(Budget at Completion) The sum of all budgets established for the work to be performed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

bar chart

A

A graphic display of schedule-related information. In the typical bar chart, schedule activities or WBS components are listed down the left side of the chart, dates are shown across the top, and activity durations are shown as date-placed horizontal bars. See also “Gantt chart”.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

benchmarking

A

The comparison of actual or planned products,
processes, and practices to those of comparable
organizations to identify best practices, generate
ideas for improvement, and provide a basis for
measuring performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

benefit cost analysis

A

A financial analysis tool used to determine the

benefits provided by a project against its costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

benefits management plan

A

The documented explanation defining the processes for creating, maximizing, and sustaining the benefits
provided by a project or program.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

bidder conferences

A

The meetings with prospective sellers prior to the
preparation of a bid or proposal to ensure all
prospective vendors have a clear and common
understanding of the procurement. Also called vendor
conferences, pre-bid conferences, or contractor
conferences.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

bottom-up estimating

A

A method of estimating project duration or cost by
aggregating the estimates of the lower- level
components of the WBS.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

brainstorming

A

A technique that involves a facilitator to help a group
identify project risks in a free-form session where
ideas are generated, built on, and recorded.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

breach of contract

A

The failure to meet some or all the obligations of a

contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

burndown chart

A

A tool that is used to track the progress of the
project by plotting the number of days of Sprint
against the number of hours of work remaining.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

business case

A

A documented economic feasibility study used to
establish the validity of the benefits of a selected
component lacking sufficient definition and that is
used as a basis for the authorization of further
project management activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

business risk

A

The inherent risk in any business endeavor that carries
the potential for either profit or loss. Types of
business risks are competitive, legislative, monetary,
and operational.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

business value

A

The net quantifiable benefit derived from a business
endeavor. The benefit may be tangible, intangible, or
both.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

CCB

A

(Change Control Board) A formally chartered group
responsible for reviewing, evaluating, approving,
delaying, or rejecting changes to the project, and for
recording and communicating such decisions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

cease and desist letter

A

A document sent to an individual or a business to stop
(cease) allegedly illegal activities and to not
undertake them again (desist).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

change control form

A

A document used to request a project change. They can also be recommendations for taking corrective or
preventive actions. See also “change request”.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

change control system

A

A set of procedures that describes how modifications
to the project deliverables and documentation are
managed and controlled.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

change management

A

The process of managing project changes in a structured and standardized manner.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

change management plan

A

A component of the project management plan that
establishes the Change Control Board, documents that
extent of its authority, and describes how the change
control system will be implemented.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

change request

A

Request for change sent to the upper management or the Change Control Board (CCB) for its evaluation and
approval. See also “change control form”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

checklist analysis

A

A technique for systematically reviewing materials

using a list for accuracy and completeness.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

CI

A

(Continuous Improvement) The ongoing effort to improve products, services, or processes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

Close Project or Phase process

A

The process of finalizing all activities for the

project, phase, or contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

close-out meetings

A

Sessions held at the end of a project or phase; they
involve discussing the work and capturing lessons
learned.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

co-location

A

An organizational placement strategy where the project
team members are physically located close to one
another in order to improve communication, working
relationships, and productivity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

coaching

A

The act of giving guidance and direction to another

person so that they can make better decisions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

code of accounts

A

A numbering system used to uniquely identify each

component of the WBS.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

Code of Ethics and Professional Conduct

A

A PMI® publication that describes the ethical and
professional behavior expectations of an individual
working as a project management professional.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

communication methods

A

A systematic procedure, technique, or process used to

transfer information among project stakeholders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

communication requirements analysis

A

An analytical technique to determine the information
needs of the project stakeholders through interviews, workshops, study of lessons learned from previous
projects, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

communication styles assessment

A

A technique to identify the preferred communication

method, format, and content for stakeholders for planned communication activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

communication technology

A

Specific tools, systems, computer programs, etc., used

to transfer information among project stakeholders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

communications management plan

A

A component of the project, program, or portfolio
management plan that describes how, when, and by whom information about the project will be administered and disseminated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

completion contract

A

A type of contract that is completed when the vendor
delivers the product to the buyer and the buyer
accepts the product.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

configuration management

A

A tool used to manage changes to a product or service
being produced as well as changes to any of the
project documents such as schedule updates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

configuration management plan

A

A component of the project management plan that
describes how to identify and account for project
artifacts under configuration control and how to record
and report changes to them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

configuration management system

A

A collection of procedures used to track project
artifacts and monitor and control changes to these
artifacts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

conflict management

A

The application of one or more strategies for dealing
with disagreements that may be detrimental to team
performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

context diagram

A
A visual depiction of the product scope showing a 
business system (process, equipment, computer system, etc.), and how people and other systems (actors) interact with it.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

contingency plan

A

A risk response strategy developed in advance, before
risks occur; it is meant to be used if and when
identified risks become reality.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

Project Resource Management

A

includes the processes to identify, acquire, and manage the human resources needed to successfully complete a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

contingency reserves

A

Time or money allocated in the schedule or cost baseline for known risks with active response strategies.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

contract change control system

A

The system used to collect, track, adjudicate, and communicate changes to a contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

contract

A

A mutually binding agreement that obligates the seller to provide the specified project or service or result
and obligates the buyer to pay for it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

control account

A

A management control point where scope, budget, actual cost, and schedule are integrated and compared to earned value for performance measurement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
70
Q

Control Procurements process

A

The process of managing procurement relationships, monitoring contract performance, making changes and
corrections as appropriate, and closing out contracts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
71
Q

controlling PMO

A

A type of PMO that provides support and requires compliance through various means. Compliance may involve adopting project management frameworks or
methodologies; using specific templates, forms, and tools; or conformance to governance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
72
Q

CoQ

A

(Cost of Quality) All costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraisal of the product or service for conformance to requirements, and failure to meet requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
73
Q

cost aggregation

A

Summing the lower-level cost estimates associated with the various work packages for a given level within the
project’s WBS or for a given cost control account.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
74
Q

cost baseline

A

The approved version of the time-phased project budget, excluding any management reserves, which can
be changed only through formal change control procedures and is used as a basis for comparison to actual results.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
75
Q

cost management plan

A

A component of a project or program management plan that describes how costs will be planned, structured, and controlled.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
76
Q

cost of conformance

A

The money spent during a project to avoid failures. This includes prevention costs that build a quality product and appraisal costs that assess the quality.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
77
Q

cost of non-conformance

A

The money spent after a project is complete because of failures. This includes internal and external failure
costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
78
Q

cost-reimbursable contract

A

A type of contract involving payment to the seller for the seller’s actual costs, plus a fee typically representing the seller’s profit.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
79
Q

CPAF contract

A

(Cost Plus Award Fee contract) A category of contract that involves payments to the seller for all legitimate actual costs incurred for completed work, plus an award fee representing seller profit.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
80
Q

CPFF contract

A

(Cost Plus Fixed Fee contract) A type of cost-reimbursable contract where the buyer reimburses the seller for the seller’s allowable costs (allowable costs are defined by the contract) plus a fixed amount of profit (fee).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
81
Q

CPI

A

(Cost Performance Index) A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
82
Q

CPIF contract

A

(Cost Plus Incentive Fee contract) A type of cost-reimbursable contract where the buyer reimburses the seller for the seller’s allowable costs (allowable costs are defined by the contract), and the seller
earns its profit if it meets defined performance
criteria.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
83
Q

critical path activity

A

Any activity on the critical path in a project

schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
84
Q

critical path

A

The sequence of activities that represents the longest path through a project, which determines the shortest possible duration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
85
Q

cultural awareness

A

Understanding the cultural differences of the individuals, groups, and organizations in the project stakeholder community so you can adapt communication strategies to avoid or reduce miscommunication and
misunderstandings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
86
Q

CV

A

(Cost Variance) The amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
87
Q

daily standup

A

A short, 15-minute meeting in which the complete team gets together for a quick status update while standing in a circle. Also referred to as a daily scrum.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
88
Q

de facto regulations

A

Regulations that are widely accepted and adopted through use.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
89
Q

de jure regulations

A

Regulations that are mandated by law or have been approved by a recognized body of experts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
90
Q

debriefing

A

A less formal, more cooperative means of discussing the positives and the negatives of the project, what worked, and what will be done differently next time.
This discussion includes technology issues, people issues, vendor relationships, and organizational
culture.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
91
Q

decision making

A

The process of selecting a course of action from among multiple options.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
92
Q

decision tree analysis

A

A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
93
Q

decomposition

A

A technique used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
94
Q

deliverable

A

Any unique and verifiable product, result, or capability to perform a service that is required to be produced to complete a process, phase, or projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
95
Q

directions of influence

A

A classification model that groups stakeholders based on how they influence the project: upwards (senior
management), downwards (team or specialists), outwards (external), sidewards (project manager’s peers), and
prioritization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
96
Q

directive PMO

A

A type of PMO that takes control of projects by directly managing the projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
97
Q

discretionary dependency

A

A relationship that is established based on knowledge of best practices within a particular application area or an aspect of the project where a specific sequence
is desired.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
98
Q

document analysis

A

A technique used to gain project requirements from current documentation evaluation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
99
Q

DoD

A

(Definition of Done) A team’s checklist of all the criteria required to be met so that a deliverable can be considered ready for customer use.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
100
Q

DoR

A

(Definition of Ready) A team’s checklist for a user-centric requirement that has all the information the team needs to be able to begin working on it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
101
Q

EAC

A

(Estimate at Completion) The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
102
Q

EEF

A

(Enterprise Environmental Factors) Conditions that are not under the immediate control of the team, and that
influence, constrain, or direct the project, program, or portfolio.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
103
Q

effect-based risk classification

A

A way of analyzing the major risks inherent to a project that could have an impact on its success. These major risks include time, cost, quality, and
scope.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
104
Q

effort

A

The number of labor units required to complete a scheduled activity or WBS component, often expressed in hours, days, or weeks. Contrast with duration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
105
Q

EI

A

(emotional intelligence) The ability to identify, assess, and manage the personal emotions of oneself and other people, as well as the collective emotions of groups of people. EQ is also a commonly used
abbreviation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
106
Q

elapsed time

A

The actual calendar time required for an activity from start to finish.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
107
Q

EMV

A

(Expected Monetary Value) A method of calculating the average outcome when the future is uncertain.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
108
Q

enhance

A

A strategy for managing positive risks or
opportunities that involves increasing the probability that the opportunity will happen, or the impact it will have by identifying and maximizing enablers of
these opportunities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
109
Q

escalate

A

The strategy in which you determine that a threat is outside the scope of the project or beyond the project manager’s authority. You then forward the threat to a person or part of the organization at a higher level.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
110
Q

ETC

A

(Estimate to Complete) The expected cost of finishing all the remaining project work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
111
Q

EV

A

(Earned Value) A measure of work performed expressed in terms of the budget authorized for that work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
112
Q

EVM

A

(Earned Value Management) A methodology that combines
scope, schedule, and resource measurements to assess
project performance and progress.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
113
Q

expert judgment

A

Judgment provided based upon expertise in an application area, knowledge area, discipline, industry, etc., as appropriate for the activity being performed. Such expertise may be provided by any group
or person with specialized education, knowledge, skill, experience, or training.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
114
Q

explicit knowledge

A

Knowledge that can be codified using symbols such as words, numbers, and pictures. This type of knowledge can be documented and shared with others.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
115
Q

exploit

A

A strategy for managing positive risks or

opportunities that involves attempting to make sure that the opportunity happens.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
116
Q

external dependency

A

Types of activity dependencies that exist between project activities and non-project activities and can be out of the project’s control.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
117
Q

facilitated workshops

A

Organized working sessions held by project managers to determine a project’s requirements and to get all stakeholders together to agree on the project’s
outcomes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
118
Q

facilitation

A

A skill used to lead or guide an assembled group toward a successful conclusion such as making a decision or finding a solution.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
119
Q

FF

A

(Finish-to-Finish) A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
120
Q

FFP contract

A

(Firm Fixed Price contract) A type of fixed price contract where the buyer pays the seller a set amount (as defined by the contract), regardless of the seller’s costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
121
Q

fixed price contract

A

An agreement that sets the fee that will be paid for a defined scope of work regardless of the cost or effort to deliver it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
122
Q

float

A

Also called slack. See also “total float” and “free float”.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
123
Q

focus groups

A

An elicitation technique that brings together pre-qualified stakeholders and subject matter experts to learn about their expectations and attitudes about a
proposed product, service, or result.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
124
Q

FPEPA contract

A

(Fixed Price with Economic Price Adjustment contract) A fixed-price contract, but with a special provision
allowing for pre-defined final adjustments to the contract price due to changed conditions, such as inflation changes, or cost increases (or decreases) for specific commodities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
125
Q

FPIF contract

A

(Fixed Price Incentive Fee contract) A type of contract where the buyer pays the seller a set amount (as defined by the contract), and the seller can earn an additional amount if the seller meets defined
performance criteria.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
126
Q

free float

A

The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
127
Q

FS

A

(Finish-to-Start) A logical relationship in which a successor activity cannot start until a predecessor activity has finished.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
128
Q

functional organization

A

An organizational structure in which staff is grouped by areas of specialization and the project manager has limited authority to assign work and apply resources.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
129
Q

funding limit reconciliation

A

The process of comparing the planned expenditure of project funds against any limits on the commitment of
funds for the project to identify any variances between the funding limits and the planned expenditures.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
130
Q

Gantt chart

A

A bar chart of schedule information where activities are listed on the vertical axis, dates are shown on the horizontal axis, and the activity durations are shown
as horizontal bars placed according to start and finish dates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
131
Q

IFB

A

(Invitation for Bid) Generally, this term is equivalent to request for proposal. However, in some application areas,
it may be a narrower or more specific meaning. A type of procurement document that is most commonly used when
deliverables are commodities for which there are clear specifications and when the quantities are very large. The
invitation is usually advertised, and any seller may submit a bid. Negotiation is typically not anticipated. These are sometimes used interchangeably with RFPs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
132
Q

impediment

A

An obstacle that prevents the team from achieving its objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
133
Q

increment

A

A functional, tested, and accepted deliverable that is a subset of the overall project outcome.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
134
Q

incremental life cycle

A

An adaptive project life cycle in which the deliverable is produced through a series of iterations that successively add functionality within a predetermined
time frame. The deliverable contains the necessary and sufficient capability to be considered complete only after the final iteration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
135
Q

Influence/impact grid

A

A classification model that groups stakeholders on the basis of their involvement in and impact on the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
136
Q

influencing

A

The act of presenting a good case to explain why an idea, decision, or problem should be handled a certain way, without resistance from other individuals.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
137
Q

information radiator

A

The generic term for visual displays placed in a visible location so everyone can quickly see the latest information. In agile practice, also known as “Big Visible Chart”.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
138
Q

insurable risk

A

A risk that has only the potential for loss and no potential for profit or gain. An insurable risk is one for which insurance may be purchased to reduce or offset the possible loss. Types of insurable risks are
direct property, indirect property, liability, and personnel- related.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
139
Q

interactive communication

A

An exchange of information between two or more people that ensures common understanding for everyone participating in that exchange.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
140
Q

internal dependency

A

A type of activity dependency that exists between project activities and is usually under the project’s control.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
141
Q

interpersonal skills

A

Skills used to establish and maintain relationships with other people.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
142
Q

interview

A

A formal or informal approach to elicit information from stakeholders by talking with them directly.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
143
Q

IRR

A

(Internal Rate of Return) The interest rate that makes the net present value of all cash flow equal to zero.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
144
Q

issue

A

A current condition or situation that may have an impact on the project objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
145
Q

issue log

A

A document where information about issues is recorded and monitored.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
146
Q

iteration

A

A timeboxed cycle of development on a product or deliverable in which all of the work that is needed to deliver value is performed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
147
Q

iterative life cycle

A

A project life cycle where the project scope is generally determined early in the project life cycle, but time and cost estimates are routinely modified as
the project team’s understanding of the product increases. Iterations develop the product through a series of repeated cycles, while increments successively add to the functionality of the product.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
148
Q

JAD

A

(Joint Application Design) Specialized workshops that include both SMEs and the development team together to discuss and improve on the software development
process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
149
Q

job shadowing

A

See “observations”.

150
Q

Kanban board

A

A visualization tool that enables improvements to the flow of work by making bottlenecks and work quantities
visible.

151
Q

knowledge management

A

Connecting individuals, in person or virtually, to share knowledge and collaborate together.

152
Q

KPI

A

(Key Performance Indicator) A set metric used to evaluate a team’s performance against the project vision and objectives.

153
Q

lag

A

The amount of time whereby a successor activity will be delayed with respect to a preceding activity.

154
Q

lead

A

The amount of time whereby a successor activity can be advanced with respect to predecessor activity.

155
Q

leadership

A

The ability to step up and guide others to achieve results. Leadership abilities are gained through experience, building relationships, and taking on initiatives.

156
Q

lean

A

An agile method used primarily in manufacturing that focuses on achieving outcomes with little or no waste.

157
Q

lessons-learned register

A

A project document used to record knowledge gained during a project so that it can be used in the current project and entered into the lessons-learned repository.

158
Q

lessons-learned repository

A

A store of historical information about lessons learned in projects.

159
Q

majority

A

A group decision-making method in which a majority of group members agree on the course of action to take.

160
Q

make-or-buy analysis

A

The process of gathering and organizing data about product requirements and analyzing them against available alternatives including the purchase or
internal manufacture of the project.

161
Q

make-or-buy decisions

A

Decisions made regarding the external purchase or internal manufacture of a product.

162
Q

management reserves

A

An amount of the project budget or project schedule held outside of the performance measurement baseline
(PMB) for management control purposes, that is reserved for unforeseen work that is within the scope of the project.

163
Q

mandatory dependency

A

A relationship that is contractually required or inherent in the nature of the work.

164
Q

matrix organization

A

An organizational structure in which the project manager shares responsibility with the functional managers for assigning priorities and for directing the work of persons assigned to the project.

165
Q

MBI

A

(Minimum Business Increment) The smallest amount of value that can be added to a product or service that
benefits the business.

166
Q

milestone

A

A significant point or event in a project, program, or portfolio.

167
Q

milestone charts

A

A type of project schedule bar chart that only includes milestone or major deliverables as points in time.

168
Q

milestone list

A

A document that contains the significant points or events in a project.

169
Q

mind mapping

A

A technique used to consolidate ideas created through individual brainstorming sessions into a single map to reflect commonality and differences in understanding and to generate new ideas.

170
Q

mitigate

A

A strategy for managing negative risks or threats that involves taking action to reduce the probability of occurrence or the impact of a risk.

171
Q

Monte Carlo simulation

A

An analysis technique where a computer model is iterated many times, with the input values chosen at
random for each iteration driven by the input data, including probability distributions and probabilistic
branches. Outputs are generated to represent the range of possible outcomes for the project.

172
Q

motivation

A

The inner drive that keeps people involved and wanting to complete work of high quality in a timely fashion.

173
Q

multi-criteria decision analysis

A

This technique utilizes a decision matrix to provide a systematic analytical approach for establishing criteria, such as risk levels, uncertainty, and valuation, to evaluate and rank many ideas.

174
Q

MVP

A

(Minimum Viable Product) The smallest collection of features that can be included in a product for customers to consider it functional. In Lean methodologies, it can be referred to as “bare bones” or “no frills” functionality.

175
Q

negotiated settlements

A

Are undertaken to arrive at a final equitable settlement of all outstanding issues, claims, and disputes by negotiation.

176
Q

negotiation

A

An approach used by more than one individual to come to an agreement or resolution.

177
Q

nominal group technique

A

A technique that enhances brainstorming with a voting process used to rank the most useful ideas for further brainstorming or for prioritization.

178
Q

NPS

A

(Net Promoter Score) Measures a customer’s willingness to recommend a provider’s products or services to
another on a scale of -100 to 100.

179
Q

Kano Model

A

Used as a prioritization technique identifying certain features or
capabilities as Basic, Performance, or Excitement helps in the prioritization of which capabilities are truly must-have, what features may create meaningful
competitive differentiators, etc.

180
Q

MoSCoW (MSCW) analysis

A

Used as a prioritization technique categorize features as Must Have, Should Have, Could Have, and Won’t Have (for now). This helps customers organize their thinking about what are truly must- have capabilities and enables identification of a Minimum Viable Product (MVP).

181
Q

Product backlog

A

Used as a prioritization technique In agile approaches, you maintain and manage a product backlog. The product backlog
is owned by the customer—or the product owner in Scrum—and reflects a list of desired capabilities, written as User Stories, and a prioritized list, with the
items that have the highest business value and highest business risk listed first.

182
Q

100 Points Method

A

Used as a prioritization technique where each stakeholder is given 100
points and can multi-vote their points across all the stories, which then give a weighted priority when combined.

183
Q

Paired Comparison Analysis

A

Used as a prioritization technique Looking at each pair of stories and prioritizing one over the others.

184
Q

NPV

A

(Net Present Value) The present value of all cash outflows minus the present value of all cash inflows.

185
Q

observations

A

The techniques used to gain knowledge of a specific job role, task, or function in order to understand and determine project requirements. This is also known as job shadowing.

186
Q

OPA

A

(organizational process assets) Plans, processes, policies, procedures, and knowledge bases that are specific to and used by the performing organization.

187
Q

opportunity

A

A risk that would have a positive effect on one or more project objectives.

188
Q

organizational theory

A

The study of how people, teams, and organizations behave to look for common themes for the purpose of maximizing efficiency and productivity, problem
solving, and meeting the stakeholder requirements of a project.

189
Q

outsourcing

A

Moving beyond the organization to secure services and expertise from an outside source on a contract or short-term basis.

190
Q

overlapping relationships

A

A type of phase-to-phase relationship that contains phases that start prior to the previous phase ending.

191
Q

parametric estimating

A

An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and
project parameters.

192
Q

Pareto chart

A

A histogram that is used to rank causes of problems in a hierarchical format.

193
Q

PDM

A

(Precedence Diagramming Method) A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.

194
Q

phase gate

A

A point review at the end of a phase in which a decision is made to continue to the next phase, to continue with modification, or to end a project or
program.

195
Q

planning package

A

A WBS component below the control account with known work content but without detailed schedule activities.

196
Q

plurality

A

Decisions made by the largest block in a group, even if a majority is not achieved.

197
Q

PMIS

A

(Project Management Information System) An information system consisting of the tools and techniques used to gather, integrate, and disseminate the outputs of
project management processes.

198
Q

PMO

A

(Project Management Office) A management structure that standardizes the project-related governance processes
and facilitates the sharing of resources,
methodologies, tools, and techniques. PMOs are more common in larger organizations because of the number
of projects that can be in process all at the same time.

199
Q

political awareness

A

The ability to recognize the power structure internal to the organization, and the ability to navigate the relationships.

200
Q

portfolio management

A

The centralized management of one or more portfolios to achieve strategic objectives.

201
Q

portfolio

A

Projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives.

202
Q

Power/influence grid

A

A classification model that groups stakeholders on the basis of their levels of authority and involvement in the project.

203
Q

Power/interest grid

A

A classification model that groups stakeholders on the basis of their levels of authority and interest in the project.

204
Q

precedence relationship

A

A logical dependency used in the precedence diagramming methods.

205
Q

predictive life cycle

A

A form of project life cycle in which the project scope, time, and cost are determined in the early phases of the life cycle.

206
Q

probability and impact matrix

A

A grid for mapping the probability of occurrence of each risk and its impact on project objectives if that risk occurs.

207
Q

probability distribution

A

The scattering of values assigned to likelihood in a sample population. It can be visually depicted in the form of a probability density function (PDF).

208
Q

procurement

A

The acquisition of goods and services from an external organization, vendor, or supplier to enable the deliverables of the project.

209
Q

procurement audit

A

The review of contracts and contracting processes for completeness, accuracy, and effectiveness.

210
Q

procurement documents

A

The documents utilized in bid and proposal activities, which include the buyer’s invitation for bid, invitation
for negotiations, request for information, request for quotation, request for proposal, and settler’s responses.

211
Q

procurement management plan

A

A component of the project or program management plan that describes how a project team will acquire goods and
services from outside of the performing organization.

212
Q

procurement SOW

A

Describes the procurement item in sufficient detail to allow prospective sellers to determine if they are
capable of providing the products, services, or results.

213
Q

product analysis

A

For projects that have a product as the deliverable, it
is a tool to define scope that generally means asking
questions about a product and forming answers to describe the use, characteristics, and other relevant aspects of
what is going to be manufactured.

214
Q

product backlog

A

A prioritized list of customer requirements and the first step of Scrum in which priority is based on the riskiness and business value of the user story.

215
Q

product box exercise

A

A technique used to explain an overarching solution wherein stakeholders try to describe aspects of a solution in the same way a marketer might describe
product features and benefits on a box.

216
Q

product owner

A

An individual or an organization who is responsible for gathering inputs about a product from the customer and
translating the requirements into the product vision for the team and stakeholders.

217
Q

product roadmap

A

A high-level visual summary of the product or products of the project that includes goals, milestones, and potential deliverables.

218
Q

program management

A

The application of knowledge, skills, and principles to a program to achieve the program objectives and obtain
benefits and control not available by managing program components individually.

219
Q

program

A

Related projects, subsidiary programs, and program activities that are managed in a coordinated manner to obtain benefits not available from managing them individually. A project may or may not be part of a program, but a program will always have projects.

220
Q

progressive elaboration

A

The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become
available.

221
Q

project artifact

A

Any document related to the management of a project.

222
Q

project charter

A

A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply
organizational resources to project activities.

223
Q

project governance

A

The framework, functions, and processes that guide project management activities to create a unique product, service, or result to meet organizational, strategic, and operational goals.

224
Q

ELMO

A

(enough, let’s move on) continue with what the team is doing and move forward. Topic can be moved to the parking lot.

225
Q

project life cycle

A

A series of phases that a project passes through from its start to its completion.

226
Q

project management plan

A

The document that describes how the project will be executed, monitored and controlled, and closed.

227
Q

project management software

A

A computer application that helps plan, organize, and manage project resources and develop resource estimates for activities.

228
Q

project management

A

The application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.

229
Q

project manager

A

The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.

230
Q

project phase

A

A collection of logically related project activities that culminates in the completion of one or more deliverables.

231
Q

project requirements

A

For a project, these are the agreed-upon conditions or capabilities of a product, service, or outcome that a project is designed to satisfy.

232
Q

project schedule network diagram

A

A graphical representation of the logical relationships among the project schedule activities. project schedule. An output of a schedule model that presents linked
activities with planned dates, durations, milestones, and resources.

233
Q

project scope statement

A

The description of the project scope, major deliverables, assumptions, and constraints.

234
Q

project scope

A

The features and functions that characterize a product, service, or result.

235
Q

project team

A

A set of individuals who support the project manager in performing the work of the project to achieve its objectives.

236
Q

project

A

A temporary endeavor undertaken to create a unique product, service, or result.

237
Q

projectized organization

A

A structure where a project manager and a core project team operate as a separate organizational unit within the parent organization.

238
Q

prototypes

A

A method of obtaining early feedback on requirements by providing a working model of the expected product before
actually building it.

239
Q

pull communications

A

Messages that require the interested people to access the information based on their own initiative.

240
Q

push communications

A

Messages that are sent out to people who need to receive the information.

241
Q

PV

A

(Present Value) The current value of a future sum of money or stream of cash flows given a specific rate of return.

242
Q

PV

A

(Planned Value) The authorized budget assigned to scheduled work.

243
Q

QFD

A

(Quality function deployment) Workshops that are commonly used in the manufacturing field to determine
new product development requirements.

244
Q

qualified vendors

A

The vendors who are approved to deliver the products, services, or results based on the procurement requirements identified for a project.

245
Q

qualified vendors list

A

Contains details regarding vendors who meet the organization’s requirements and to whom requests can be sent.

246
Q

qualitative risk analysis

A

A technique used to determine the probability of occurrence and the impact of identified risk.

247
Q

quality audit

A

A structured, independent process to determine if project activities comply with organizational and project policies, processes, and procedures.

248
Q

quality gate

A

A special type of gate located before a phase that is strongly dependent upon the outcome of a previous phase. The quality gate process is a formal way of specifying and recording the transition between stages in the project life cycle.

249
Q

quality management plan

A

A component of the project or program management plan that describes how applicable policies, procedures, and
guidelines will be implemented to achieve the quality objectives.

250
Q

quality metric

A

A description of a project or product attribute and how to measure it.

251
Q

quality

A

The degree to which a set of inherent characteristics fulfills requirements.

252
Q

quantitative risk analysis

A

Technique used to assess the risk exposure events to overall project objectives and determine the confidence levels of achieving the project objectives.

253
Q

questionnaires

A

Written sets of questions designed to quickly accumulate information from a large number of respondents.

254
Q

RACI chart

A

(Responsible, Accountable, Consulted, and Informed) A common type of Responsibility Assignment Matrix (RAM) that uses responsible, accountable, consult, and inform statuses to define the involvement of stakeholders in project activities.

255
Q

RAM

A

(Responsibility Assignment Matrix) A grid that shows the project resources assigned to each work package.

256
Q

RBS

A

(risk breakdown structure) A hierarchical

representation of potential sources of risk.

257
Q

recognition

A

A more personalized, intangible, and experiential event that focuses on behavior rather than outcome.

258
Q

regulations

A

Requirements imposed by a governmental body. These requirements can establish product, process, or service
characteristics, including applicable administrative provisions that have government-mandated compliance.

259
Q

relative authority

A

The project manager’s authority relative to the functional manager’s authority over the project and the project team.

260
Q

requirements documentation

A

A description of how individual requirements meet the business need for the project.

261
Q

requirements management plan

A

A component of the project or program management plan that describes how requirements will be analyzed, documented, and managed.

262
Q

requirements traceability matrix

A

A grid that links product requirements from their origin to the deliverables that satisfy them.

263
Q

resource calendar

A

A calendar that identifies the working days and shifts upon which each specific resource is available.

264
Q

resource levelling

A

A resource optimization technique in which adjustments are made to the project schedule to optimize the allocation of resources and which may affect the
critical path.

265
Q

resource management plan

A

A component of the project management plan that describes how project resources are acquired, allocated, monitored, and controlled.

266
Q

resource requirements

A

The types and quantities of resources required for each activity in a work package.

267
Q

reward

A

A tangible, consumable item that is given to a person based on a specific outcome or an achievement.

268
Q

reward and recognition plan

A

A formalized way to reinforce performance or behavior.

269
Q

RFI

A

(Request for Information) A type of procurement document whereby the buyer requests a potential seller to provide
various pieces of information related to a product or service or seller capability.

270
Q

RFP

A

(Request for Proposal) A type of procurement document used to request proposals from prospective sellers of
products or services. In some application areas, it may have a narrower or more specific meaning.

271
Q

RFQ

A

(Request for Quotation) A type of procurement document used to request price quotations from prospective
sellers of common or standard products or services. Sometimes used in place of request for proposal and, in some application areas, it may have a narrower or more specific meaning.

272
Q

risk appetite

A

The degree of uncertainty an organization or individual is willing to accept in anticipation of a reward.

273
Q

risk categorization

A

Organization by sources of risk (e.g., using the RBS), the area of the project affected (e.g., using the WBS), or other useful category (e.g., project phase) to
determine the areas of the project most exposed to the effects of uncertainty.

274
Q

risk impact

A

The likely effect on project objectives if a risk event occurs.

275
Q

risk management plan

A

A component of the project, program, or portfolio management plan that describes how risk management activities will be structured and performed.

276
Q

resource requirements

A

The types and quantities of resources required for each activity in a work package.

277
Q

reward

A

A tangible, consumable item that is given to a person based on a specific outcome or an achievement.

278
Q

reward and recognition plan

A

A formalized way to reinforce performance or behavior.

279
Q

RFI

A

(Request for Information) A type of procurement document whereby the buyer requests a potential seller to provide
various pieces of information related to a product or service or seller capability.

280
Q

RFP

A

(Request for Proposal) A type of procurement document used to request proposals from prospective sellers of
products or services. In some application areas, it may have a narrower or more specific meaning.

281
Q

RFQ

A

(Request for Quotation) A type of procurement document used to request price quotations from prospective
sellers of common or standard products or services. Sometimes used in place of request for proposal and, in some application areas, it may have a narrower or more specific meaning.

282
Q

risk appetite

A

The degree of uncertainty an organization or individual is willing to accept in anticipation of a reward.

283
Q

risk categorization

A

Organization by sources of risk (e.g., using the RBS), the area of the project affected (e.g., using the WBS), or other useful category (e.g., project phase) to
determine the areas of the project most exposed to the effects of uncertainty.

284
Q

risk impact

A

The likely effect on project objectives if a risk event occurs.

285
Q

risk management plan

A

A component of the project, program, or portfolio management plan that describes how risk management activities will be structured and performed.

286
Q

risk probability

A

The likelihood that a risk event will occur or prove true during the project.

287
Q

risk register

A

A repository in which outputs of risk management processes are recorded.

288
Q

risk threshold

A

The level of risk exposure above which risks are addressed and below which risks may be accepted.

289
Q

risk tolerance

A

The maximum amount of risk, and the potential impact of that risk occurring, that a project manager or key stakeholder is willing to accept.

290
Q

risk workshop

A

A technique that uses a special meeting conducted for the purpose of identifying project risks. In addition to the
project team members, this workshop might also include the project sponsor, SMEs, customer representatives, and
other stakeholders, depending on the size of the project.

291
Q

risk

A

An uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives.

292
Q

ROI

A

(Return on Investment) A financial metric of

profitability that measures the gain or loss from an investment relative to the amount of money invested.

293
Q

root cause analysis

A

An analytical technique used to determine the basic underlying reason that causes a variance or a defect or a risk. A root cause may underlie more than one variance or
defect or risk.

294
Q

SAFe

A

(Scaled Agile Framework) A knowledge base of integrated patterns for enterprise-scale lean- agile development.

295
Q

salience model

A

A classification model that groups stakeholders on the basis of their level of authority, their immediate needs, and how appropriate their involvement is in
terms of the project.

296
Q

schedule management plan

A

A component of the project or program management plan that establishes the criteria and the activities for developing, monitoring, and controlling the schedule.

297
Q

scope baseline

A

The approved version of a scope statement, WBS, and its associated WBS dictionary, that can be changed using formal change control procedures and is used as a basis for comparison to actual results.

298
Q

scope creep

A

The uncontrolled expansion to product or project scope without adjustments to time, cost, and resources.

299
Q

scope management plan

A

A component of the project management plan or program management plan that describes how the scope will be defined, developed, monitored, controlled, and validated.

300
Q

Scrum master

A

The coach of the development team and process owner in the Scrum framework. Removes obstacles, facilitates productive events, and defends the team from
disruptions.

301
Q

Scrum team

A

Dedicated, self-managing, cross-functional, fully empowered individuals who deliver the finished work required by the customer.

302
Q

Scrum

A

An agile framework for developing and sustaining complex products, with specific roles, events, and artifacts.

303
Q

sequential relationships

A

A type of phase-to-phase relationship that contains consecutive phases that only start when the previous phase is complete.

304
Q

servant leadership

A

A type of leadership style used in agile and other types of projects which encourages the self-definition, self-
discovery, and self-awareness of team members by listening, coaching, and providing an environment which
allows them to grow.

305
Q

SF

A

(Start-to-Finish) A logical relationship in which a predecessor activity cannot finish until a successor activity has started.

306
Q

share

A

A strategy for managing positive risks or opportunities that involves allocating some or all of the ownership of the opportunity to a third party.

307
Q

simulation

A

An analytical technique that models the combined effect of uncertainties to evaluate their potential impact on
objectives.

308
Q

SLA

A

(Service Level Agreement) A contract between a service provider (either internal or external) and the end user that defines the level of service expected from the service provider.

309
Q

SoS

A

(Scrum of Scrums) A technique to operate Scrum at scale for multiple teams working on the same product, coordinating discussions of progress on their
interdependencies, and focusing on how to integrate the delivery of software, especially in areas of overlap.

310
Q

source selection criteria

A

A set of attributes desired by the buyer which a seller is required to meet or exceed to be selected for a contract.

311
Q

source-based risk classification

A

A method of analyzing risk in terms of its origins.

312
Q

SPI

A

(Schedule Performance Index) A measure of schedule efficiency expressed as the ratio of earned value to planned value.

313
Q

Sprint backlog

A

A list of work items identified by the Scrum team to be completed during the Scrum sprint.

314
Q

Sprint planning

A

A collaborative event in Scrum in which the Scrum team plans the work for the current sprint.

315
Q

Sprint retrospective

A

This critical part of the Scrum process is attended by the Product Owner, Scrum Master, and the Scrum team to analyze
from a process perspective what is working well and what is not and to agree upon changes to implement.

316
Q

Sprint review

A

A review at the end of each iteration with the Product Owner and other customer stakeholders to review the progress of the product, get early feedback, and review an
acceptance from Product Owner of the stories delivered in the iteration. Also referred to as a Demo.

317
Q

Sprint

A

A timeboxed iteration in Scrum.

318
Q

SS

A

(Start-to-Start) A logical relationship in which a successor activity cannot start until a predecessor activity has started.

319
Q

stakeholder analysis

A

A technique of systematically gathering and analyzing quantitative and qualitative information to determine whose interests should be taken into account throughout the project.

320
Q

stakeholder cube

A

A three-dimensional classification model that builds on the previous two-dimensional grids to group stakeholders.

321
Q

Stakeholder Engagement Assessment Matrix

A

A matrix that compares current and desired stakeholder engagement levels.

322
Q

stakeholder engagement plan

A

A component of the project management plan that identifies the strategies and actions required to promote productive involvement of stakeholders in project or program decision making and execution.

323
Q

stakeholder register

A

A project document including the identification, assessment, and classification of project stakeholders.

324
Q

stakeholder

A

An individual, group, or organization that may affect, be affected by, or perceive itself to be affected by a decision, activity, or outcome of a project, program,
or portfolio.

325
Q

standard

A

A document established by an authority, custom, or general consent as a model for example.

326
Q

statistical sampling process

A

A process that involves dividing sampling data into two categories—attribute and variable— each of which is gathered according to sampling plans. As corrective actions are taken in response to analysis of statistical sampling and other quality control activities, and as trend analysis is performed, defects and process
variability should be reduced.

327
Q

statistical sampling

A

Choosing part of a population of interest for inspection.

328
Q

storyboarding

A

The prototyping method that uses visuals or images to illustrate a process or represent a project outcome.
Storyboards are useful to illustrate how a product, service, or application will function or operate when it is complete.

329
Q

supportive PMO

A

The type of PMO that provides a consultative role to projects by supplying templates, best practices, training, access to information, and lessons learned
from other projects.

330
Q

SV

A

(Schedule Variance) A measure of schedule performance expressed as the difference between the earned value
and the planned value.

331
Q

SWOT analysis

A

An analysis of strengths, weaknesses, opportunities, and threats of an organization, project, or option.

332
Q

T&M contract

A

(Time and Material contract) A type of contract that is a hybrid contractual arrangement containing aspects of
both cost- reimbursable and fixed-price contracts.

333
Q

T-shaped

A

Refers to a person with one deep area of specialization and broad ability in the rest of the skills required by the team.

334
Q

tacit knowledge

A

Personal knowledge that can be difficult to articulate and share such as beliefs, experience, and insights.

335
Q

task board

A

Used to visualize the work and enable the team and stakeholders to track their progress as work is performed during an iteration. Examples of task boards
include Kanban boards, to-do lists, procedure
checklists, and Scrum boards.

336
Q

team building

A

The process of continually supporting and working collaboratively with team members in order to enable a team to work together to solve problems, diffuse
interpersonal issues, share information, and tackle project objectives as a unified force.

337
Q

team charter

A

A document that records the team values, agreements, and operating guidelines as well as establishing clear expectations regarding acceptable behavior by project
team members.

338
Q

team management plan

A

A component of the resource management plan that describes

when and how team members will be acquired and how long they will be needed.

339
Q

team resource management

A

The processes necessary to organize, manage, and lead the people on the project team as well as the
processes needed to procure and manage physical resources for a project.

340
Q

team-building activities

A

The specific functions or actions taken to help the team to develop into a mature, productive team. They can be formal or informal, brief or extended, and facilitated by the project manager or a group facilitator.

341
Q

teaming agreement

A

A legal contractual agreement between two or more parties to form a joint venture or any other arrangement as defined by the parties to meet the requirements of a business opportunity. The parties
can be internal or external to the organization executing the project.

342
Q

term contract

A

A type of contract that engages the vendor to deliver a set amount of service—measured in staff-hours or a similar unit—over a set period of time.

343
Q

threat

A

A risk that would have a negative effect on one or more project objectives.

344
Q

three-point estimating

A

A technique used to estimate cost or duration by applying an average or weighted average of optimistic,
pessimistic, and most likely estimates when there is uncertainty with the individual activity estimates.

345
Q

timebox

A

A fixed period of time; for example, 1 week, 2 weeks, 3 weeks, or 1 month.

346
Q

tolerance

A

The quantified description of acceptable variation for a quality requirement.

347
Q

total float

A

The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.

348
Q

TQM

A

(Total Quality Management) An approach to improve business results through an emphasis on customer satisfaction, employee development, and processes
rather than on functions.

349
Q

training

A

An activity in which team members acquire new or enhanced skills, knowledge, or attitudes.

350
Q

transfer

A

A strategy for managing negative risks or threats that involves shifting the impact and ownership of the risk to a third party and paying a risk premium to the party taking on the liability of the risk.

351
Q

trend analysis

A

An analytical technique that uses mathematical models to forecast future outcomes based on historical results.

352
Q

trigger condition

A

An event or situation that indicates that a risk is about to occur.

353
Q

unanimity

A

Agreement by everyone in the group on a single course of action.

354
Q

unique identification code

A

A specific configuration of a code of accounts that assigns a particular alphanumeric sequence of characters
to each element of a WBS.

355
Q

user story

A

A brief description of deliverable value for a specific user. It is a promise for a conversation to clarify details.

356
Q

Validate Scope

A

The process of formalizing acceptance of the completed project deliverables.

357
Q

value stream mapping

A

A lean enterprise technique used to document, analyze, and improve the flow of information or materials required to produce a product or service for a
customer.

358
Q

value stream

A

An organizational construct that focuses on the flow of value to customers through the delivery of specific products or services.

359
Q

variable sampling data

A

Data from a sample that is measured on a continuous scale such as time, temperature, or weight.

360
Q

variance

A

A quantifiable deviation, departure, or divergence away from a known baseline or expected value.

361
Q

variance analysis

A

A technique for determining the cause and degree of difference between the baseline and the actual performance.

362
Q

version control

A

A system that records changes to a file, in a way that allows you to retrieve previous changes made to it.

363
Q

virtual team

A

A group of people with a shared goal who fulfill their roles with little or no time spent meeting face-to-face.

364
Q

waiver

A

The giving up of a contract right, even inadvertently.

365
Q

warranty

A

A promise, explicit or implied, that goods or services will meet a predetermined standard.

366
Q

WBS dictionary

A

A document that provides detailed deliverable, activity, and scheduling information about each component in the work breakdown structure.

367
Q

WBS

A

(work breakdown structure) A hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables.

368
Q

work package

A

The work defined at the lowest level of the work breakdown structure for which cost, and duration are estimated and managed.

369
Q

work performance data

A

The raw observations and measurements identified during activities being performed to carry out the project
work. They can be recorded in the PMIS and project documents.

370
Q

work performance information

A

The performance data collected from controlling processes, analyzed in comparison with project management plan components, project documents, and
other work performance information.

371
Q

work performance report

A

The physical or electronic representation of work performance information compiled in project documents, intended to generate decisions, actions, or awareness

372
Q

work shadowing

A

An on-the-job technique that enables someone to learn about and perform a job while observing and working with another more experienced person, or mentor