PMP Flashcards
How to set up a project for EVM measurement? (prepare the baseline)
- Create WBS
- Develop a schedule
- Estimate cost for scheduled work
- Calculated the cumulative cost by time period
BAC
Budget at Completion. Cumulative total for all the work
PMB
Performance Measurement Baseline.
PV
Plan Value. Budget for the scheduled work.
Level of effort
No deliverable associated with the work. The work to support project to get done.
Schedule Variance
Scheduled variance = PV -EV. Desired to be negative.
SPI
Schedule Performance Index. SPI=EV/PV. Desired to be >1
EV
BAC X Percent complete
CV
Cost Variance = EV-AC. Desired to be positive.
EV
Earned Value
CPI
Cost Performance index. CPI=EV/AC. Desired to have >1
ETC
Estimate to Complete.
1. ETC math = BAC - EV assuming the cost variance is one time event
2. (BAC-EV)/CPI
BAC
Estimate at Completion
1. BAC-EV+AC (
2. EAC CPI, assuming the future performance rate will be the same rate as current performance. BAC/CPI
3. EAC CPI XSPI. Most realistic. (BAC-EV)/CPI X SPI +AC
TCPI
To-Complete Performance Index. TCPI = (BAC-EV)/(BAC-AC)