PMI-SP Acronyms Flashcards

1
Q

AC

A

Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

ACWP

A

Actual cost of work performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

AD

A

Activity Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

AF

A

Actual Finish Date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

AS

A

Actual Start Date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

BAC

A

Budget at completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

CAM

A

Control account manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

CPI

A

Cost performance index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

CPM

A

Critical path method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

CV

A

Cost variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

DD

A

Data date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

DoD

A

Definition of done

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

DU

A

Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

DUR

A

Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

EAC

A

Estimate at completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

ETC

A

Estimate to Completion

17
Q

Earned Value

A

EV

18
Q

EVT

A

Earned value technique

19
Q

FF

A

Free float

20
Q

PC

A

Percent Complete

21
Q

PCT

A

Percent Complete

22
Q

PDM

A

Precedence diagramming method

23
Q

PV

A

Planned value

24
Q

RD

A

Remaining duration

25
Q

SPI

A

Schedule Performance Index

26
Q

SV

A

Schedule Variance

27
Q

TF

A

Total Float

28
Q

WBS

A

Work Breakdown Structure