PMI-ACP formulas Flashcards

Learn the PMI-ACP fromuals with this deck

1
Q

PV formula in earned value management

A

No Formula. It is sometimes expressed as a %age of BAC.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

EV formula in earned value management

A

No Formula. It is sometimes expressed as a %age of BAC or PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

AC formula in earned value management

A

No Formula.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

SV formula in earned value management

A

SV = EV – PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CV formula in earned value management

A

CV = EV – AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

SPI formula in earned value management

A

SPI = EV / PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

CPI formula in earned value management

A

CPI = EV / AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Present value or discounted cash flow equation formula in project selection methods

A

PV = FV * DF || PV = FV / (1+r)^n (future value * discount factor)(n is years, r is discount rate)(note that discount factor is the reverse of compounding interest to account for inflation over time)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

NPV formula in project selection methods

A

ΣPV (higher is better all other things being equal)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

ROI formula in project selection methods

A

Return / Formula investment (higher is better)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

BCR formula in project selection methods

A

Benefits / Costs (higher is better)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

CBR formula in project selection methods

A

Costs / Benefits (lower is better)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

IRR formula in project selection methods

A

No formula, it’s estimated. (Higher is better)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

PP formula in project selection methods

A

Price Point. (Market price, sale price, contract price) Lesser the better.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Opp Cost formula in project selection methods

A

No formula, it’s estimated. (Higher is better)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A project will be carried out using one-week sprints. The steering committeewants an estimate of how long the project will take. The project backlog hasbeen estimated at 500 story points. The team estimates the velocity per sprintin the worst-case scenario as 10 story points, the best-case scenario with 25story points, and the most likely scenario as 20 points.Using a triangular distribution, how long will the project take?

A

32 weeks. Correct. The worst-case duration can be calculated as 500 / 10 which is50 sprints. The most likely case can be calculated as 500 / 20 which is25 sprints. The best case can be calculated as 500 / 25 which is 20sprints. Taking the average number of sprints would be (50 + 25 + 20) / 3which is 31.67. Thus, the estimate would be 32. Since each sprint is oneweek in length, the duration estimate would be 32 weeks.

17
Q

A Kanban board is used to manage the workflow of a software developmentproject. The project team has established a cycle time of five business daysper user story. The lead time is 10 business days per story. There are 20 userstories remaining in the backlog.What should the team report as an estimate to complete the backlog?

A

100 days. take the backlog and multiply by the cycle time.

18
Q

SPI agile formula

A

story points completed / story points planned

19
Q

CPI agile formula

A

Story point earned cost completed / cost of actual sprint

20
Q

When referencing dollar value, which is the preferred performance calculation for agile? - CPI or SPI

A

CPI because dollars is mentioned. Even if the question states. “according to planed.”