PMBOK Glossary A Flashcards

1
Q

A set of conditions that is required to be met before deliverables are accepted

A

Acceptance Criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Products, results, or capabilities produced by a project and validated by the project customer or sponsor as meeting their specified acceptance criteria

A

Accepted Deliverables

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Within the quality management system, ______ is an assessment of correctness

A

Accuracy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The process of obtaining team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work

A

Acquire Resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Obtaining human and material resources necessary to perform project activities. ______ implies a cost of resources, and is not necessarily financial

A

Acquisition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A distinct, scheduled portion of work performed during the course of a project

A

Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Multiple attributes associated with each schedule activity that can be included within the activity list. ____________ include activity codes, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, and assumptions

A

Activity Attributes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The time in calendar units between the start and finish of a schedule activity

A

Activity Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The quantitative assessments of the likely number of time periods that are required to complete an activity

A

Activity Duration Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A documented tabulation of schedule activities that shows the activity description, activity identifier, and a sufficiently detailed scope of work description so project team members understand what work is to be performed

A

Activity List

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

AON

A

Activity-on-Node

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

AC

A

Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The realized cost incurred for the work performed on an activity during a specific time period

A

Actual Cost (AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The time in calendar units between the actual start date of the schedule activity and either the data date of the project schedule if the schedule activity is in progress or the actual finish date if the schedule activity is complete

A

Actual Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A project life cycle that is iterative or incremental

A

Adaptive Life Cycle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A technique that allows large numbers of ideas to be classified into groups for review and analysis

A

Affinity Diagrams

17
Q

Any document or communication that defines the initial intentions of a project. This can take the form of a contract, memorandum of understanding (MOU), letters of agreement, verbal agreements, email, etc.

A

Agreements

18
Q

A technique used to evaluate identified options in order to select the options or approaches to use to execute and perform the work of the project

A

Alternative Analysis

19
Q

A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project

A

Analogous Estimating

20
Q

Various techniques used to evaluate, analyze, or forecast potential outcomes based on possible variations of project or environmental variables and their relationships with other variables

A

Analytical Techniques

21
Q

A factor in the planning process that is considered to be true, real, or certain, without proof or demonstration

A

Assumption

22
Q

A project document used to record all assumptions and constraints throughout the project life cycle

A

Assumption Log

23
Q

Method of measuring quality that consists of noting the presence (or absence) of some characteristic (attribute) in each of the units under consideration

A

Attribute Sampling

24
Q

The right to apply project resources, expend funds, make decisions, or give approvals

A

Authority