PMBOK Flashcards

1
Q

A set of conditions that is required to be met before deliverables are accepted

A

Acceptance criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Products, results, or capabilities produced by a project and validated by the project customer or sponsors as meeting their specified acceptance criteria

A

Accepted deliverables

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Within the quality management system, accuracy is an assessment of correctness

A

Accuracy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The process of obtaining team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work

A

Acquire resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Obtaining human and material resources necessary to perform project activities. acquisition implies a cost of resources, and is not necessarily financial

A

Acquisition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A distinct, scheduled portion of work performed during the course of a project

A

Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Multiple attributes associated with each schedule activity that can be included within the activity list. Activity attributes include activity codes, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints and assumptions

A

Activity attributes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The time in calendar units between the start and finish of a schedule activity.

A

Activity duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The quantitative assessments of the likely number of time periods that are required to complete an activity

A

Activity duration estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A document tabulation of schedule activities that shows the activity description, activity identifier, and a sufficiently detailed scope of work description so project team members understand what work is to be performed

A

Activity List

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The realized cost incurred for the work performed on an activity during a specific time period

A

Actual Cost (AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The time in calendar units between the actual start date of the schedule activity and either the data date of the project schedule if the schedule activity is in progress or the actual finish date if the schedule activity is complete

A

Actual Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A project life cycle that is iterative or incremental

A

Adaptive Life Cycle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

A technique that allows large numbers of ideas to be classified into groups for review and analysis.

A

Affinity Diagrams

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Any document or communication that defines the initial intentions of a project. this can take the form of a contract, memorandum of understanding (MOU), letters of agreement, verbal agreements, email, etc

A

Agreements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A technique used to evaluate identified options in order to select the options or approaches to use to execute and perform the work of the project

A

Alternative Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project

A

Analogous Estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Various Techniques used to evaluate, analyze, or forecast potential outcomes based on possible variations of project or environmental variables and their relationships with other variable.

A

Analytical Techniques

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

A factor in the planning process that is considered to be true, real, or certain, without proof or demonstration

A

Assumption

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

A project document used to record all assumptions and constraint throughout the project life cycle

A

Assumption Log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Method of measuring quality that consists of noting the presence (or absence) of some characteristic (attribute) in each of the units under consideration

A

Attribute Sampling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

The right to apply project resources, expend funds, make decisions, or give approvals

A

Authority

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

A critical path method technique or calculating the late start and late finish dates by working backward through the schedule model from the project end date.

A

Backward Pass

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

A graphic display of schedule-related information. In the Typical bar chart, schedule activities or work breakdown structure components are listed down the left side of the chart, dates are shown across the top, and activity durations are shown as date-placed horizontal bars. See also Gantt chart.

A

Bar Chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.

A

Baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Supporting documentation outlining the details used in establishing project estimates such as assumptions, constraints, level o detail, ranges, and confidence levels.

A

Basis of Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

The comparison of actual or planned products, processes, and practices to those of comparable organizations to identify best practices, generate ideas for improvements, and provide a basis for measuring performance.

A

Benchmarking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

The documented explanation defining the processes for creating, maximizing, and sustaining the benefits provided by a project or program.

A

Benefits Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

All documents used to solicit information, quotations, or proposals from prospective sellers.

A

Bid Documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

The meetings with prospective sellers prior to the preparation of a bid or proposal to ensure al prospective vendors have a clear and common understanding of the procurement. Also known as contractor conferences, vendor conferences, or pre-bid conference .

A

Bidder Conference

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure(WBS).

A

Bottom-Up Estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

The approved estimate for the project or any work breakdown structure component or any schedule activity.

A

Budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

The sum of all budgets established for the work to be performed.

A

Buget at Completion (BAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

A documented economic feasibility study used to establish validity of the benefits of a selected component lacking sufficient definition and that is used as a basis for the authorization of further project management activities.

A

Business Case

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

The net quantifiable benefit derived from a business endeavor. The Benefit may be tangible, intangible, or both.

A

Business Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

A decomposition technique that helps trace an undesirable effect back to its root cause.

A

Cause and Effect Diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

A modification to any formally controlled deliverable, project management plan component, or project document.

A

Change

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

A process whereby modifications to documents, deliverables, or baselines associated with the project are identified, documented, approved, or rejected.

A

Change Control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

A formally chartered group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project, and for recoding and communicating such decisions.

A

Change Control Board (CCB)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.

A

Change Control System

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

Manual or automated tools to assist with change and/or configuration management. At a minimum, the tools should support the activities of the CCB.

A

Change Control Tools

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

A comprehensive list of changes submitted during the project and their current status.

A

Change Log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

A component of the project management plan that establishes the change control board, documents the extent of its authority, and describes how the change control system will be implemented.

A

Change Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

A formal proposal to modify a document, deliverable, or baseline.

A

Change Request

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

A technique for systematically reviewing materials using a list for accuracy and completeness.

A

Checlist Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

A tally Sheet that can be used as a checklist when gathering data.

A

Checksheets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

A request, demand, or assertion of rights by a seller against a buyer, or vice versa, for consideration, compensation, or payment under the terms of a legally binding contract, such as for a disputed change.

A

Claim

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

The process of processing, adjudicating, a communicating contract claims.

A

Claims Administration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

The process of finalizing all activities for the project, phase, or contract.

A

Close Project or Phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

The process(es) performed to formally complete or close a project, phase, or contract.

A

Closing Process Group

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

A numbering system used to uniquely identify each component of the work breakdown structure(WBS).

A

Code of Accounts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

The process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives.

A

Collect Requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

An organizational Placement strategy where the project team members are physically located close to one another in order to improve communication, working relationships, and productivity.

A

Colocaiton

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

A systematic procedure, technique, or process used to transfer information among project stakeholders.

A

Communication Methods

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

A description, analogy, or schematic used to represent how the communication process will be performed for the project.

A

Communication Models

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

An analytical technique to determine the information needs of the project stakeholders through interviews, workshops, study of lessons learned from previous projects, etc.

A

Communication Requirements Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

A component of the project, program, or portfolio management plan that describes how, when, and by whom information about the project will be administered and disseminated.

A

COmmunications Mangement Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

A technique to identify the preferred communication method, format, and content for stake holders for planned communication activities.

A

Communication Styles Assesment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

Specific tools, systems, computer programs, etc., used to transfer information among project stakeholders.

A

Communication Technology

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

The process of obtaining seller responses, selecting a seller, and awarding a contract.

A

Conduct Procurements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

A component of the project management plan that describes how to identify and account for project artifacts under configuration control, and how to record and report changes to them.

A

Confirguration Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

A collection of procedures used to track project artifacts and monitor and control changes to the artifacts.

A

Configuration Mangement System

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

Within the quality management system, conformance is a general concept of delivering results that fall within the limits that define acceptable variation for a quality requirement.

A

Conformance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

A limiting factor that affects the execution of a project, program, portfolio, or process.

A

Constraint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

A visual depiction of the product scope showing a business system (process, equipment, computer system, etc.), and how people and other systems (actors) interact with it.

A

Context Diagrams

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

An event or occurrence that could affect the execution of the project that may be accounted for with a reserve.

A

Contingency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

Time or money allocated in the schedule or cost baseline for known risks with active response strategies.

A

Contingency Reserve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

Responses provided which may be used in the even that a specific trigger occurs.

A

Contingent Response Strategies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

Amutually binding agreement that obligates the seller to provide the specified product or service or result and obligates the buyer to pay for it.

A

Contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
70
Q

The system used to collect, track, adjudicate and communicate changes to a contract.

A

Contract Change Control System

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
71
Q

Comparing actual performance with planned performance, analyzing variances, assessing trends to effect process improvements, evaluating possible alternatives, and recommending appropriate corrective action as needed.

A

Control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
72
Q

A management control point where scope, budget, actual cost, and schedule are integrated and compared to earned value for performance measurement.

A

Control Account

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
73
Q

A graphic display of process data over time and against established control limits, which has a centerline that assists in detecting a trend of plotted values toward either control limit.

A

Control Chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
74
Q

The process of monitoring the status of the project to update the project costs and manage changes to the cost baseline.

A

Control Costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
75
Q

The area composed of three standard deviations on either side of the centerline or mean of a normal distribution of data plotted on a control chart, which reflects the expected variation in the data. See also specification limits.

A

Control Limits

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
76
Q

The process of managing procurement relationships, monitoring contract performance, making changes and corrections as appropriate, and closing out contracts.

A

Control Procurements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
77
Q

The process of monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations.

A

Control Quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
78
Q

The acquisition of ensuring that the physical resources assigned and allocated to the project are available as a planned, as well as monitoring the planned versus actual utilization of resources and performing corrective action as necessary.

A

Control Resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
79
Q

The process of monitoring the status of the project and product scope and managing changes to the scope baseline.

A

Control Scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
80
Q

An intentional activity that realigns the performance of the project work with the project management plan.

A

Corrective Action

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
81
Q

Summing the lower-level cost estimates associated with the various work packages for a given level within the project’s WBS or for a given cost control account.

A

Cost Aggregation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
82
Q

The approved version of the time-phased project budget, excluding any management reserves, which can be changed only through formal change control procedures and is used as a basis for comparison to actual results..

A

Cost Baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
83
Q

A financial analysis tool used to determine the benefits provided by a project against its cost.

A

Cost-Benefit Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
84
Q

A component of a project or program management plan that describes how costs will be planned, structured, and controlled.

A

Cost Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
85
Q

All costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraisal of the product or service for conformance to requirements, and failure to meet requirements.

A

Cost of Quality (CoQ)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
86
Q

A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.

A

Cost Performance Index (CPI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
87
Q

A category of contract that involves payments to the seller for all legitimate actual costs incurred for completed work, plus an award fee representing seller profit.

A

Cost Plus Award Fee Contract (CPAF)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
88
Q

A type of cost-reimbursable contract where the buyer reimburses the seller for the seller’s allowable costs (allowable costs are defined by the contract) plus a fixed amount of profit (fee).

A

Cost Plus Fixed Fee Contract (CPFF)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
89
Q

A type of cost-reimbursable contract where the buyer reimburses the seller for the seller’s allowable costs (allowable costs are defined by the contract), and the seller earns its profit if it meets defined performance criteria.

A

Cost Plus Incentive Fee Contract (CPIF)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
90
Q

A type of contract involving payment to the seller for the seller’s actual costs, plus a fee typically representing the seller’s profit.

A

Cost-Reimbursable Contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
91
Q

The amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual cost.

A

Cost Variance (CV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
92
Q

A technique used to shorten the schedule duration for the least incremental cost by adding resources.

A

Crashing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
93
Q

The process of subdividing project deliverables and project work into smaller, more manageable components.

A

Create WBS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
94
Q

Standards, rules, or tests on which a judgment or decision can be based or by which a product, service, result, or process can be evaluated.

A

Criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
95
Q

The sequence of activities that represents the longest path through a project, which determines the shortest possible duration.

A

Critical Path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
96
Q

Any activity on the critical path in a project schedule.

A

Critical path Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
97
Q

A method used to estimate the minimum project duration and determine the amount of schedule flexibility on the logical network paths within the schedule model.

A

Critical Path Method (CPM)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
98
Q

Discrete, unorganized, unprocessed measurements or raw observations.

A

Data

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
99
Q

Techniques used to organize, assess, and evaluate data and information.

A

Data Analysis Techniques

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
100
Q

A point in time when the status of the project is recorded

A

Data Date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
101
Q

Techniques used to collect data and information from a variety of sources.

A

Data Gathering Techniques

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
102
Q

Graphic representations or other methods used to convey data and information.

A

Data Representation Techniques

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
103
Q

Techniques used to select a course of action from different alternatives.

A

Decision-Making Techniques

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
104
Q

A Diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.

A

Decision Tree Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
105
Q

A technique used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts.

A

Decomposition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
106
Q

An imperfection of deficiency in a project component where that component does not meet its requirements or specifications and needs to be either repaired or replaced.

A

Defect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
107
Q

An intentional activity to modify a nonconforming product or product component.

A

Defect Repair

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
108
Q

The process of identifying and documenting the specific actions to be performed to produce the project deliverables.

A

Define Activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
109
Q

The process of developing a detailed description of the project and product.

A

Define Scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
110
Q

Any unique and verifiable product, result, or capability to perform a service that is required to be produced to complete a process, phase, or project.

A

Deliverable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
111
Q

The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.

A

Determine Budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
112
Q

The method used to create and evolve the product, service, or result during the project life cycle, such as predictive, iterative, incremental agile, or a hybrid method.

A

Development Approach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
113
Q

The process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.

A

Develop Project Charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
114
Q

The process of defining, preparing, and coordinating all plan components and consolidating them into an integrated project management plan.

A

Develop Project Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
115
Q

The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model for project execution and monitoring and controlling.

A

Develop Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
116
Q

The process of improving competences, team member interaction, and overall team environment to enhance project performance.

A

Develop Team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
117
Q

Approaches to presenting information with logical linkages that aid in understanding.

A

Diagramming Techniques

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
118
Q

The process of leading and performing the work defined in a project management plan and implementing approved changes to achieve the project’s objectives.

A

Direct and Manage Project Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
119
Q

An activity that can be planned and measured and that yields a specific output.

A

Discrete Effort

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
120
Q

A relationship that is established based on knowledge of best practices within a particular application area or an aspect of the project where a specific sequence is desired.

A

Discretionary Dependency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
121
Q

The process of gathering a corpus of information and reviewing it to determine accuracy and completeness.

A

Documentation Reviews

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
122
Q

The total number of work periods required to complete an activity or work breakdown structure component, expressed in hours, days, or weeks. Contrast with effort.

A

Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
123
Q

In the critical path method, the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, the data date, and any schedule constraints.

A

Early Finish Date (EF)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
124
Q

In the critical path method, the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic, the data date, and any schedule constraints.

A

Early Start Date (ES)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
125
Q

The measure of work performed expressed in terms of the budget authorized for that work.

A

Earned Value (EV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
126
Q

A methodology that combines scope, schedule, and resource measurements to assess project performance and progress.

A

Earned Value Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
127
Q

The number of labor units required to complete a schedule activity or work breakdown structure component, often expressed in hours, days, or weeks. Contrast with duration.

A

Effort

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
128
Q

The ability to identify, assess, and manage the personal emotions of oneself and other people, as well as the collective emotions of groups of people.

A

Emotional Intelligence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
129
Q

Conditions, not under the immediate control of the team, that influence, constrain, or direct the project, program, or portfolio.

A

Enterprise Environmental Factors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
130
Q

A quantitative assessment of the likely amount or outcome of a variable, such as project costs, resources, effort, or durations.

A

Estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
131
Q

The process of estimating the number of work periods needed to complete individual activities with the estimated resources.

A

Estimated Activity Durations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
132
Q

The process of estimating team resources and the type and quantities of material, equipment, and supplies necessary to perform project work.

A

Estimate Activity Resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
133
Q

The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.

A

Estimate at Completion (EAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
134
Q

The process of developing an approximation of the monetary resources needed to complete project work.

A

Estimate Costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
135
Q

The expected cost to finish all the remaining project work.

A

Estimate to Complete (ETC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
136
Q

Directing, managing, performing, and accomplishing the project work; providing the deliverables; and providing work performance information.

A

Execute

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
137
Q

Those processes performed to complete the work defined in the project management plan to satisfy the project requirements.

A

Executing Process Group

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
138
Q

Judgement provided based upon expertise in an application area, knowledge area, discipline, industry, etc., as appropriate for the activity being performed. Such expertise may be provided by any group or person with specialized education, knowledge, skill, experience, or training.

A

Expert Judgment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
139
Q

Knowledge that can be codified using symbols such as words, numbers, and pictures.

A

Explicit Knowledge

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
140
Q

A relationship between project activities and non-project activities.

A

External Dependency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
141
Q

Include an alternative set of actions and tasks available in the event that the primary plan needs to be abandoned because of issues, risks, or other causes.

A

Fallback Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
142
Q

A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.

A

Fast Tracking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
143
Q

Represents profit as a component of compensation to a seller.

A

Fee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
144
Q

A point in time associated with a schedule activity’s completion. Usually qualified by one of the following: actual, planned, estimated, scheduled, early, late, baseline, target, or current.

A

Finish Date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
145
Q

A logical relationship which a successor activity cannot finish until a predecessor activity has finished.

A

Finish-to-Finish (FF)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
146
Q

A logical relationship which a successor activity cannot Start until a predecessor activity has finished.

A

Finish-to-Start (FS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
147
Q

A type of fixed price contract where the buyer pays the seller a set amount (as defined by the contract), regardless of the seller’s costs

A

Firm Fixed Price Contract (FFP)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
148
Q

An agreement that sets the fee that will be paid for a defined scope of work regardless of the cost or effort to deliver it.

A

Fixed- Price Contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
149
Q

A type of contract where the buyer pays the seller a set amount (as defined by the contract), and the seller can earn an additional amount if the seller meets defined performance criteria.

A

Fixed Price Incentive Fee Contract (FPIF)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
150
Q

A fixed-price contract, but with a special provision allowing for predefined final adjustments to the contract price due to changed conditions, such as inflation changes, or cost increases (or decreases) for specific commodities.

A

Fixed Price with Economic Price Adjustment Contract (FPEPA)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
151
Q

The depiction in a diagram format of the inputs, process actions, and outputs of one or more processes within a system

A

Flowchart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
152
Q

An elicitation technique that brings together prequalified stakeholders and subject matter experts to learn about their expectations and attitudes about a proposed product, service, or result.

A

Focus Groups

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
153
Q

An estimate or prediction of conditions and events in the project’s future based on information and knowledge available at the time of the forecast.

A

Forecast

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
154
Q

A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.

A

Forward Pass

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
155
Q

The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint

A

Free Float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
156
Q

An organizational structure in which staff is grouped by areas of specialization and the project manager has limited authority to assign work and apply resources.

A

Functional Organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
157
Q

The Process of comparing the planned expenditure of project funds against any limits on the commitment of funds for the project to identify any variances between the funding limits and the planned expenditures.

A

Funding Limit Reconciliation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
158
Q

A bar chart of schedule information where activities are listed on the vertical axis, dates are shown on the horizontal axis, and activity durations are shown as horizontal bars placed according to start and finish dates.

A

Gantt Chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
159
Q

A category or rank used to distinguish items that have the same functional use but do not share the same requirements for quality.

A

Grade

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
160
Q

Expectations regarding acceptable behavior by project team members

A

Ground Rules

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
161
Q

A bar chart that shows the graphical representation of numerical data

A

Histogram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
162
Q

Documents and data on prior projects including project files, records, correspondence, closed contracts, and closed projects.

A

Historical Information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
163
Q

The process of identifying individual risks as well as sources of overall risk and documenting their characteristics

A

Identify Risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
164
Q

The process of identifying project stakeholders regularly and analyzing and documenting relevant information regarding their interests, involvement, interdependencies, influence, and potential impact on project success.

A

Identify Stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
165
Q

The process of implementing agreed-upon risk response plans

A

Implement Risk Reponses

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
166
Q

A fixed date imposed on a schedule activity or schedule milestone, usually in the form of a “start no earlier than” and “finish no later than” date

A

Imposed Date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
167
Q

A set of financial incentives related to cost, schedule, or technical performance of the seller.

A

Incentive fee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
168
Q

An adaptive project life cycle in which the deliverable is produced through a series of iterations that successively add functionality within a predetermined time frame. The deliverable contains the necessary and sufficient capability to be considered complete only after the final iteration.

A

Incremental Life Cycle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
169
Q

A process of using a third party to obtain and analyze information to support prediction of cost, schedule, or other items.

A

Independent Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
170
Q

A graphical representation of situations showing causal influences, time ordering of events, and other relationships among variables and outcomes.

A

Influence Diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
171
Q

Organized or structured data, processed for a specific purpose to make it meaningful, valuable, and useful in specific contexts.

A

Information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
172
Q

Facilities, processes, and procedures used to collect, store, and distribute information between producers and consumers of information in physical or electronic format.

A

Information Management Systems

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
173
Q

Those processes performed to define a new project or a new phase of an existing project by obtaining authorization to start the project or phase.

A

Initiating Process Group

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
174
Q

Any item, whether internal or external to the project, which is required by a process before that process proceeds. May be an output from a predecessor process.

A

Input

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
175
Q

Examination of a work product to determine whether it conforms to documented standards.

A

Inspection

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
176
Q

Skills used to effectively lead and interact with team members and other stakeholders

A

Interpersonal and Team Skills

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
177
Q

Skills used to establish and maintain relationships with other people

A

Interpersonal Skills

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
178
Q

A formal or informal approach to elicit information from stakeholders by talking to them directly.

A

Interviews

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
179
Q

Generally, this term is equivalent to request for proposal. However, in some application areas, it may have a narrower or more specific meaning.

A

Invitation for Bid (IFB)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
180
Q

A current condition or situation that may have an impact on the project objectives.

A

Issue

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
181
Q

A project document where information about issues is recorded and monitored.

A

Issue Log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
182
Q

A project life cycle where the project scope is generally determined early in the project life cycle, but time and cost estimates are routinely modified as the project team’s understanding of the product increases. develops the product through a series of repeated cycles, while increments successively add to the functionality of the product.

A

Iterative Life Cycle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
183
Q

A mixture of experience, values and beliefs, contextual information, intuition, and insight that people use to make sense of new experiences and information.

A

Knowledge

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
184
Q

The amount of time whereby a successor activity will be delayed with respect to a predecessor activity

A

Lag

185
Q

In the critical path method, the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, the project completion date, and any schedule constraints.

A

Late Finish Date (LF)

186
Q

In the critical path method, the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic, the project completion date, and any schedule constraints.

A

Late Start Date (LS)

187
Q

The amount of time whereby a successor activity can be advanced with respect to a predecessor activity

A

Lead

188
Q

The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance.

A

Lessons Learned

189
Q

A project document used to record knowledge gained during a project so that it can be used in the current project and entered into the lessons learned repository.

A

Lessons Learned Register

190
Q

A store of historical information about lessons learned in projects.

A

Lessons Learned Repository

191
Q

An activity that does not produce definitive end products and is measured by the passage of time.

A

Level of Effort (LOE)

192
Q

A document used to record and describe or denote selected items identified during execution of the process or activity. Usually used with a modifier, such as issue, change, issue, or assumption.

A

Log

193
Q

A dependency between two activities, or between an activity and a milestone.

A

Logical Relationship

194
Q

The process of gathering and organizing data about product requirements and analyzing them against available alternatives including the purchase or internal manufacture of the product.

A

Make-or-Buy Analysis

195
Q

Decisions made regarding the external purchase or internal manufacture of a product.

A

Make-or-Buy Decisions

196
Q

The process of ensuring timely and appropriate collection, creation, distribution, storage, retrieval , management, monitoring, and the ultimate disposition of project information.

A

Manage Communications

197
Q

An amount of the project budget or project schedule held outside of the performance measurement baseline (PMB) for management control, that is reserved for unforeseen work that is within scope of the project.

A

Management Reserve

198
Q

The ability to plan, organize, direct, and control individuals or groups of people to achieve specific goals.

A

Management Skills

199
Q

The process of using existing knowledge and creating new knowledge to achieve the project’s objectives and contribute to organizational learning.

A

Management Project Knowledge

200
Q

The process of translating the quality management plan into executable quality activities that incorporate the organization’s quality policies into the project.

A

Manage Quality

201
Q

The process of communicating and working with stakeholders to meet their needs and expectations, address issues, and foster appropriate stakeholder involvement.

A

Manage Stakeholder Engagement

202
Q

The process of tracking team member performance, providing feedback, resolving issues, and managing team changes to optimize project performance.

A

Manage Team

203
Q

A relationship that is contractually required or inherent in the nature of the work.

A

Mandatory Dependency

204
Q

A summary-level project schedule that identifies the major deliverables and work breakdown structure components and key schedule milestones.

A

Master Schedule

205
Q

A quality management and control tool used to perform data analysis within the organizational structure created in the matrix. Seeks to show the strength of relationships between factors, causes, and objectives that exist between the rows and columns that form the matrix.

A

Matrix Diagrams

206
Q

Any Organizational Structure in which the project manager shares responsibility with the functional managers for assigning priorities and for directing the work of persons assigned to the project.

A

Matrix Organization

207
Q

A system of practices, techniques, procedures, and rules used by those who work in a discipline

A

Methodology

208
Q

A significant point or even t in a project, program, or portfolio

A

Milestone

209
Q

A type of schedule that presents milestones with planned dates. See also master schedule

A

Milestone Schedule

210
Q

A technique used to consolidate ideas created through individual brainstorming sessions into a single map to reflect commonality and differences in understanding and to generate new ideas

A

Mind-Mapping

211
Q

Collect project performance data, produce performance measures, and report and disseminate performance information

A

Monitor

212
Q

The process of tracking, reviewing and reporting overall progress to meet the performance objectives defined in the project management plan.

A

Monitor and Control Project Work

213
Q

The process of ensuring that the information needs of the project and its stakeholders are met

A

Monitor Communications

214
Q

Those processes required to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes.

A

Monitoring and Controlling Process Group

215
Q

The process of monitoring the implementation of agreed-upon risk response plans, tracking identified risks, identifying and analyzing new risks, and evaluating risk process effectiveness throughout the project.

A

Monitor Risks

216
Q

The process of monitoring project stakeholder relationships, and tailoring strategies for engaging stakeholders through the modification of engagement strategies and plans.

A

Monitor Stakeholder Engagement

217
Q

An analysis technique where a computer model is iterated many times, with the input values chosen at random for each iteration driven by the input data including probability distributions and probabilistic branches. Outputs are generated to represent the range of possible outcomes for teh project.

A

Monte Carlo Simulation

218
Q

This technique utilizes a decision matrix to provide a systematic analytical approach for establishing criteria, such as risk levels, uncertainty, and valuation, to evaluate and rank many ideas.

A

Multicriteria Decision Analysis

219
Q

All activity dependencies in a project schedule network diagram

A

Network Logic

220
Q

A sequence of activities connected by logical relationships in a project schedule network diagram

A

Network Path

221
Q

Establishing connections and relationships with other people from the same or other organizations

A

Networking

222
Q

A point at which dependency lines connect on a schedule network diagram

A

Node

223
Q

A technique that enhance brainstorming with a voting process used to rank the most useful ideas for further brainstorming or for prioritization.

A

Nominal Group Technique

224
Q

Something toward which work is to be directed, a strategic position to be attained, a purpose to be achieved, a result to be obtained, a product to be produced, or a service to be performed.

A

Objective

225
Q

A risk that would have a positive effect on one or more project objectives

A

Opportunity

226
Q

A hierarchical representation of the project organization, which illustrates the relationship between project activities and the organizational units that will perform those activities.

A

Organizational Breakdown Structure (OBS)

227
Q

A discipline concerned with the way individuals, groups, and organizations develop knowledge.

A

Organizational Learning

228
Q

Plans, processes, policies, procedures, and knowledge bases that are specific to and used by the performing organization.

A

Organizational Process Assets

229
Q

A product, result, or service generated by the process. May be an input to a successor process.

A

Output

230
Q

The effect of uncertainty on the project as a whole, arising from all sources of uncertainty including individual risks, representing the exposure of stakeholders to the implications of variations in project outcome, both positive and negative.

A

Overall Project Risk

231
Q

An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.

A

Parametric Estimating

232
Q

A relationship in which a schedule activity has more than one predecessor.

A

Path Convergence

233
Q

A relationship in which a schedule activity has more than one successor

A

Path Divergence

234
Q

An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.

A

Percent Complete

235
Q

Integrated scope, schedule, and cost baselines used for comparison to manage, measure, and control project execution.

A

Performance Mesaurement Baseline (PMB)

236
Q

A technique that is used to measure, compare, and analyze actual performance of work in progress on the project against the baseline.

A

Performance Reviews

237
Q

The process of reviewing all change requests; approving changes and managing changes to deliverables, organizational process assets, project documents, and the project management plan; and communicating the decisions.

A

Perform Integrated Change Control

238
Q

The process of prioritizing individual project risks for further analysis or action by assessing their probability of occurrence and impact as well as other characteristics.

A

Perform Qualitative Risk Analysis

239
Q

A review at the end of a phase in which a decision is made to continue to the next phase, to continue with modification, or to end a project or program.

A

Phase Gate

240
Q

The process of developing an appropriate approach and plan for project communication activities based on the information needs of each stakeholder or group, available organizational assets, and the needs of the project.

A

Plan Communications Management

241
Q

The process of defining how the project costs will be estimated, budgeted, managed, monitored, and controlled.

A

Plan Cost Management

242
Q

The authorized budget assigned to scheduled work.

A

Planned Value (PV)

243
Q

A work breakdown structure component below the control account with known work content but without detailed schedule activities. See also control account.

A

Planning Package

244
Q

Those processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project was undertaken to achieve.

A

Planning Process Group

245
Q

The process of documenting project procurement decisions, specifying the approach, and identifying potential sellers.

A

Plan Procurement Management

246
Q

The process of identifying quality requirements and/or standards for the project and its deliverables, and documenting how the project will demonstrate compliance with quality requirements and/or standards.

A

Plan Quality Management

247
Q

The process of defining how to estimate, acquire, manage, and utilize physical and team resources.

A

Plan Resource Management

248
Q

The process of defining how to conduct risk management activities for a project.

A

Plan Risk Management

249
Q

The process of developing options, selecting strategies, and agreeing on actions to address overall project risk exposure, as well as to treat individual project risks.

A

Plan Risk Reponses

250
Q

The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.

A

Plan Schedule Management

251
Q

The process of creating a scope management plan that documents how the project and product scope will be defined, validated, and controlled.

A

Plan Scope Management

252
Q

The process of developing approaches to involve project stakeholders, based on their needs, expectations, interests, and potential impact on the project

A

Plan Stakeholder Engagement

253
Q

Decisions made by the largest block in a group, even if a majority is not achieved.

A

Plurality

254
Q

A structured pattern of actions adopted by an organization such that the organization’s policy can be explained as a set of basic principles that govern the organization’s conduct.

A

Policy

255
Q

Projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives.

A

Portfolio

256
Q

The centralized management of one or more portfolios to achieve strategic objectives.

A

Portfolio Management

257
Q

A specific type of professional or management activity that contributes to the execution of a process and that may employ one or more techniques and tools.

A

Practice

258
Q

A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.

A

Precedence Diagramming Method (PDM)

259
Q

A logical dependency used in the precedence diagramming method.

A

Precedence Relationship

260
Q

An Activity that logically comes before a dependent activity in a schedule.

A

Predecessor Activity

261
Q

A form of project life cycle in which the project scope, time, and cost are determined in the early phases of the life cycle.

A

Predicitve Life Cycle

262
Q

An intentional activity that ensures the future performance of the project work is aligned with the project management plan.

A

Preventive Action

263
Q

A grid for mapping the probability of occurrence of each risk and its impact on project objectives if that risk occurs.

A

Probability and Impact Matrix

264
Q

An established method of accomplishing a consistent performance or result. Typically can be described as the sequence of steps that will be used to execute a process.

A

Procedure

265
Q

A systematic series of activities directed towards causing an end result such that one or more inputs will be acted upon to create one or more outputs.

A

Process

266
Q

The review of contracts and contracting processes for completeness, accuracy, and effectiveness

A

Procurement Audits

267
Q

The documents utilized in bid and proposal activites, which include the buyer’s invitation for bid, invitation for negotiations, request for information, request for quotation, request for proposal, and seller’s responses.

A

Procurement Documents

268
Q

All documents used in signing, executing, and closing an agreement. May include documents predating the project.

A

Procurement Documentation

269
Q

A component of the project or program management plan that describes how a project team will acquire goods and services from outside of the performing organization.

A

Procurement Management Plan

270
Q

Describes the procurement item in sufficient detail to allow prospective sellers to determine if they are capable of providing the products, services, or results.

A

Procurement Statement of Work

271
Q

The approach by the buyer to determine the project delivery method and the type of legally binding agreement(s) that should be used to deliver the desired results.

A

Procurement Strategy

272
Q

An artifact that is produced, is quantifiable, and can be either an end item in itself or a component item. Additional words for products are material and goods. See also deliverable.

A

Product

273
Q

For projects that have a product as a deliverable, it is a tool to define scope that generally means asking questions about a product and forming answers to describe the use, characteristics, and other relevant aspects of what is going to be manufactured.

A

Product analysis

274
Q

The series of phases that represent the evolution of a product, from concept through delivery, growth, maturity, and to retirement.

A

Product Life Cycle

275
Q

The features and functions that characterize a product, service, or result

A

Product Scope

276
Q

The documented narrative description of the product scope.

A

Product Scope Description

277
Q

Related projects, subsidiary programs, and program activities that are managed in a coordinated manner to obtain benefits not available from managing them individually.

A

Program

278
Q

The application of knowledge, skills, and principles to a program to achieve the program objectives and obtain benefits and control not available by managing program components individually.

A

Program Management

279
Q

The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.

A

Progressive Elaboration

280
Q

A temporary endeavor undertaken to create a unique product, service, or result.

A

Project

281
Q

A calendar that identifies working days and shifts that are available for scheduled activities.

A

Project Calendar

282
Q

A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.

A

Project Charter

283
Q

Includes the processes required to ensure timely and appropriate planning, collection, creation, distribution, storage, retrieval, management, control, monitoring, and ultimate disposition of project information.

A

Project Communications Management

284
Q

Includes the processes involved in planning, estimating, budgeting, financing, funding, managing, and controlling costs so the project can be completed within the approved budget.

A

Project Cost Management

285
Q

Forecast project costs to be paid that are derived from the cost baseline for total or periodic requirements, including projected expenditures plus anticipated liabilities.

A

Project Funding Requirements

286
Q

The framework, functions, and processes that guide project management activities in order to create a unique product, service, or result to meet organizational, strategic, and operational goals.

A

Project Governance

287
Q

Launching a process that can result in the authorization of a new project

A

Project Initiation

288
Q

Includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.

A

Project Integration Mangement

289
Q

The series of phases that a project passes through from its start to its completion.

A

Project Life Cycle

290
Q

The application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.

A

Project Management

291
Q

A term that describes the knowledge within the profession of project management. The project management body of knowledge includes proven traditional practices that are widely applied as well as innovative practices that are emerging in the profession.

A

Project Management Body of Knowledge

292
Q

An information system consisting of the tools and techniques used to gather, integrate, and disseminate the outputs of project management processes.

A

Project Management Information System

293
Q

An identified area of project management defined by its knowledge requirements and described in terms of its component processes, practices, inputs, outputs, tools, and techniques.

A

Project Mangement Knowledge Area

294
Q

A management structure that standardizes the project-related governance processes and facilitates the sharing of resources, methodologies, tools and techniques.

A

Project Management Office (PMO)

295
Q

The document that describes how the project will be executed, monitored and controlled, and closed.

A

Project Management Plan

296
Q

A logical grouping of project management inputs, tools and techniques, and outputs. Include initiating processes, planning processes, executing processes, monitoring and controlling processes, and closing processes.

A

Project Management Process Group

297
Q

The aggregation of the processes, tools, techniques, methodologies, resources, and procedures to manage a project.

A

Project Mangement System

298
Q

The members of the project team who are directly involved in project management activities. .See also Project team.

A

Project Mangement Team

299
Q

The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.

A

Project Manager (PM)

300
Q

A document that graphically depicts the project team members and their interrelationships for a specific project.

A

Project Organization Chart

301
Q

A collection of logically related project activities that culminates in the completion of one or more deliverables.

A

Project Phase

302
Q

Includes the processes necessary to purchase or acquire products, services, or results needed from outside the project team.

A

Project Procurement Management

303
Q

Includes the process for incorporating the organization’s quality policy regarding planning managing, and controlling project and product quality requirements, in order to meet stakeholders’ expectations.

A

Project Quality Management

304
Q

Includes the processes to identify, acquire, and manage the resources needed for the successful completion of the project.

A

Project Resource Management

305
Q

Includes the processes of conducting risk management planning, identification, analysis, response planning, response implementation, and monitoring risk on a project.

A

Project Risk Management

306
Q

An output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources.

A

Project Schedule

307
Q

Includes the processes required to manage the timely completion of the project

A

Project Schedule Management

308
Q

A graphical representation of the logical relationship among the project schedule activities.

A

Project Schedule Network Diagram

309
Q

The work performed to deliver a product, service, or result with the specified features and functions.

A

Project Scope

310
Q

Includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

A

Project Scope Management

311
Q

The description of the project scope, major deliverables, assumptions, and constraints.

A

Project Scope Statement

312
Q

Includes the processes required to identify the people, groups, or organizations that could impact or be impacted by the project, to analyze stakeholder expectations and their impact on the project, and to develop appropriate management strategies for effectively engaging stakeholders in project decisions and execution.

A

Project Stakeholder Mangement

313
Q

A set of individuals who support the project manager in performing the work of the project to achieve its objectives. See all Project Management Team

A

Project Team

314
Q

A documented list of project team members, their project roles, and communication information

A

Project Team Directory

315
Q

The process of reviewing proposals provided by suppliers to support contract award decisions.

A

Proposal Evaluation Techniques

316
Q

A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building it.

A

Prototypes

317
Q

The degree to which a set of inherent characteristics fulfills requirements

A

Quality

318
Q

A structured, independent process to determine if project activities comply with organizational and project policies, processes, and procedures.

A

Quality Audits

319
Q

A structured tool used to verify that a set of required steps has been performed.

A

Quality Checklists

320
Q

The documented results of control quality activities

A

Quality Control Measurements

321
Q

A component of the project or program management plan that describes how applicable policies, procedures, and guidelines will be implemented to achieve the quality objectives.

A

Quality Management Plan

322
Q

The organizational framework whose structure provides the policies, processes, procedures, and resources required to implement the quality management plan. The typical project quality management plan should be compatible to the organizations quality management system.

A

Quality Management System

323
Q

A description of a project or product attribute and how two measure it.

A

Quality Metrics

324
Q

A policy specific to the Project Quality Management Knowledge Area, it establishes the basic principles that should govern the organizations actions as it implements its system for quality management.

A

Quality Policy

325
Q

A project document that includes quality management issues, recommendations for corrective actions, and a summary of findings from quality control actives and may include recommendations for process, project, and product improvements.

A

Quality Report

326
Q

A condition or capability that will be used to assess conformance by validating the acceptability of an attribute for the quality of a result

A

Quality Requirement

327
Q

Written sets of questions designed to quickly accumulate information from large number of respondents

A

Questionnaires

328
Q

A common type of responsibility assignment matrix that uses responsible, accountable, consult, and inform states to define the involvement of stakeholders in project activities.

A

RACI Chart

329
Q

An analytical technique where a series of input variables are examined in relation to their corresponding output results in order to develop mathematical or statistical relationship.

A

Regression Analysis

330
Q

Requirements imposed by a governmental body. These requirements can establish product, process, or service characteristics, including applicable administrative provisions that have government-mandated compliance.

A

Regulations

331
Q

A type of procurement document whereby the buyer requests a potential seller to provide various pieces of information related to a product or service or seller capability.

A

Request for Information (RFI)

332
Q

A type of procurement document used to request proposals from prospective sellers of products or services. In some application areas, it may have a narrower or more specific meaning.

A

Request for Proposal (RFP)

333
Q

A type of procurement document used to request price quotations from prospective sellers of common or standard products or services. Sometimes used in place of request for proposal and, in some application areas, it may have a narrower or more specific meaning.

A

Request for Quotation (RFQ)

334
Q

A condition or capability that is necessary to be present in a product, service, or result to satisfy a business need.

A

Requirement

335
Q

A description of how individual requirements meet the business need for the project.

A

Requirements Documentation

336
Q

A component of the project or program management plan that describes how requirements will be analyzed, documented, and managed.

A

Requirements Management Plan

337
Q

A grid that links product requirements from their origin to the deliverables that satisfy them.

A

Requirements Traceability Matrix

338
Q

A provision in the project management plan to mitigate cost and/or schedule risk. Often used with a modifier (e.g., management reserve, contingency reserve) to provide further detail on what types of risk are meant to be mitigated.

A

Reserve

339
Q

An analytical technique to determine the essential features and relationships of components in the project management plan to establish a reserve for the schedule duration, budget, estimated cost, or funds for a project.

A

Reserve Analysis

340
Q

The risk that remains after risk responses have been implemented.

A

Residual Risk

341
Q

A team member or any physical item needed to complete the project

A

Resource

342
Q

A hierarchical representation of resources by category and type.

A

Resource Breakdown Structure

343
Q

A calendar that identifies the working days and shifts upon which each specific resource is available.

A

Resource Calendar

344
Q

A bar chart showing the amount of time that a resource is scheduled to work over a series of time periods.

A

Resource Histogram

345
Q

A resource optimization technique in which adjustments are made to the project schedule to optimize the allocation of resources and which may affect critical path. See also resource optimization technique and resource smoothing.

A

Resource Leveling

346
Q

A component of the project management plan that describes how project resources are acquired, allocated, monitored, and controlled.

A

Resource Management Plan

347
Q

An individual with management authority over one or more resources

A

Resource Manager

348
Q

A technique in which activity start and finish dates are adjusted to balance demand for resources with the available supply. See also resource leveling and resource smoothing.

A

Resource Optimization Technique

349
Q

The types and quantities of resources required for each activity in a work package.

A

Resource Requirement

350
Q

A resource optimization technique in which free and total float are used without affecting the critical path. See also resource leveling and resource optimization technique.

A

Resource Smoothing

351
Q

An assignment that can be delegated within a project management plan such that the assigned resource incurs a duty to perform the requirements of the assignment.

A

Responsibility

352
Q

A grid that shows the project resources assigned to each work package.

A

Responsibility Assignment Matrix (RAM)

353
Q

An output from performing project management processes and activities. Results include outcomes (e.g., integrated systems, revised process, restructured organization, tests, trained personnel, etc.) and documents (e.g., policies, plans, studies, procedures, specifications, reports, etc.) See also deliverable.

A

Result

354
Q

Action taken to bring a defective or nonconforming component into compliance with requirements or specifications.

A

Rework

355
Q

An uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives.

A

Risk

356
Q

A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.

A

Risk Acceptance

357
Q

The degree of uncertainty an organization or individual is willing to accept in anticipation of a reward.

A

Risk Appetite

358
Q

A type of audit used to consider the effectiveness of the risk management process.

A

Risk Audit

359
Q

A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.

A

Risk Avoidance

360
Q

A hierarchical representation of potential sources of risks.

A

Risk Breakdown Structure (RBS)

361
Q

Organization by sources of risk (e.g., using the RBS), the area of the project affected (e.g., using the WBS), or other useful category (e.g., project phase) to determine the areas of the project most exposed to the effects of uncertainty.

A

Risk Categorization

362
Q

A group of potential causes of risk.

A

Risk Category

363
Q

Technique to evaluate the degree to which the data about risks is useful for risk management.

A

Risk Data Quality Assessment

364
Q

A risk response strategy whereby the project team acts to increase the probability of occurrence or impact of an opportunity.

A

Risk Enhancement

365
Q

A risk response strategy whereby the team acknowledges that a risk is outside of its sphere of influence and shifts the ownership of the risk to a higher level of the organization where it is more effectively managed.

A

Risk Escalation

366
Q

A risk response strategy whereby the project team acts to ensure that an opportunity occurs.

A

Risk Exploiting

367
Q

An aggregate measure of the potential impact of all risks at any given point in time in a project, program, or portfolio.

A

Risk Exposure

368
Q

A component of the project, program, or portfolio management plan that describes how risk management activities will be structured and performed.

A

Risk Management Plan

369
Q

A risk response strategy whereby the project team acts to decrease the probability of occurrence or impact of a threat.

A

Risk Mitigation

370
Q

The person responsible for monitoring the risks and for selecting and implementing an appropriate risk response strategy.

A

Risk Owner

371
Q

A repository in which outputs of risk management processes are recorded.

A

Risk Register

372
Q

A project document developed progressively throughout the Project Risk Management processes, which summarizes information on individual project risks and the level of overall project risk.

A

Risk Report

373
Q

A meeting to examine and document the effectiveness of risk responses in dealing with overall project risk and with identified individual project risks.

A

Risk Review

374
Q

A risk response strategy whereby the project team allocates ownership of an opportunity to a third party who is best able to capture the benefit of that opportunity.

A

Risk Sharing

375
Q

The level of risk exposure above which risks are addressed and below which risks may be accepted.

A

Risk Threshold

376
Q

A risk response strategy whereby the project team shifts the impact of a threat to a third party, together with ownership of the response.

A

Risk Transference

377
Q

A defined function to be performed by a project team member, such as testing, filing, inspecting, or coding,.

A

Role

378
Q

An iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level.

A

Rolling Wave Planning

379
Q

An analytical technique used to determine the basic underlying reason that causes a variance or a defect or a risk. A root cause may underlie more than one variance or defect or risk.

A

Root Cause Analysis

380
Q

The approved version of a schedule model that can be changed using formal change control procedures and is used as the basis for comparison to actual results.

A

Schedule Baseline

381
Q

A technique used to shorten the schedule duration without reducing the project scope.

A

Schedule Compression

382
Q

The collection of information for describing and controlling the schedule.

A

Schedule Data

383
Q

Estimates or predictions of conditions and events in the projects future based on information and knowledge available at the time the schedule is calculated.

A

Schedule FOrecasts

384
Q

A component of the project or program management plan that establishes the criteria and the activities for developing, monitoring, and controlling the schedule.

A

Schedule Management Plan

385
Q

A representation of the plan for executing the project’s activities including durations, dependencies, and other planning information, used to produce a project schedule along with other scheduling artifacts.

A

Schedule Model

386
Q

A technique to identify early and late start dates, as well as early and late finish dates, for the uncompleted portions of project activities.

A

Schedule Network Analysis

387
Q

A measure of schedule efficiency expressed as the ratio of earned value to planned value.

A

Schedule Performance Index (SPI)

388
Q

A measure of schedule performance expressed as the difference between the earned value and the planned value.

A

Schedule Variance (SV)

389
Q

A tool that provides schedule component names, definitions, structural relationships, and formats that support the application of a scheduling method.

A

Scheduling Tool

390
Q

The sum of the products, services, and results to be provided as a project. See also project scope and product scope.

A

Scope

391
Q

The approved version of a scope statement, work breakdown structure (WBS), and its associated WBS dictionary, that can be changed using formal change control procedures and is used as a basis for comparison to actual results.

A

Scope Baseline

392
Q

The uncontrolled expansion to product or project scope without adjustments to time, cost, and resources.

A

Scope Creep

393
Q

A component of the project or program management plan that describes how the scope will be defined, developed, monitored, controlled, and validated.

A

Scope Management Plan

394
Q

A risk that arises as a direct result of implementing a risk response

A

Secondary Risk

395
Q

A team formation where the team functions with an absence of centralized control.

A

Self-organizing Teams

396
Q

A provider or supplier of products, services, or results to an organization.

A

Seller

397
Q

Formal responses from sellers to a request for proposal or other procurement document specifying the price, commercial terms of sale, and technical specifications or capabilities the seller will do for the requesting organization that, if accepted, would bind the seller to perform the resulting agreement .

A

Seller Proposals

398
Q

An analysis technique to determine which individual project risks or other sources of uncertainty have the most potential impact on project outcomes, by correlating variations in project outcomes with variations in elements of a quantitative risk analysis model.

A

Sensitivity Analysis

399
Q

The process of identifying and documenting relationships among the project activities.

A

Sequence Activiteis

400
Q

A contract between a service provider (either internal or external) and the end user that defines the level of service expected from the service provider.

A

Service Level Agreement (SLA)

401
Q

An analytical technique that models the combined effect of uncertainties to evaluate their potential impact on objectives.

A

Simulation

402
Q

A set of attributes desired by the buyer which a seller is required to meet or exceed to be selected for a contract.

A

Source Selection Criteria

403
Q

A precise statement of the needs to satisfied and the essential characteristics that are required.

A

Specification

404
Q

The area, on either side of the centerline, or mean, of data plotted on a control chart that meets the customers requirements for a product or service. This area may be greater than or less than the area defined by the control limits. See also control limits.

A

Specification Limits

405
Q

A person or group who provides resources and support for the project, program, or portfolio and is accountable for enabling success.

A

Sponsor

406
Q

The entity responsible for providing the projects sponsor and a conduit for project funding or other project resources

A

Sponsoring Organization

407
Q

An individual, group, or organization that may affect, be affected b, or perceive itself to be affected by a decision, activity, or outcome of a project, program, or portfolio.

A

Stakeholder

408
Q

A technique of systematically gathering and analyzing quantitative and qualitative information to determine whose interests should be take into account throughout the project.

A

Stakeholder Analysis

409
Q

A matrix that compares current and desired stakeholder engagement levels.

A

Stakeholder Engagement Assessment Matrix

410
Q

A component of the project management plan that identifies the strategies and actions required to promote productive involvement of stakeholders in project or program decision making and execution.

A

Stakeholder Engagement Plan

411
Q

A project document including the identification, assessment, and classification of project stakeholders.

A

Stakeholder Register

412
Q

A document established by an authority, custom, or general consent as a model or example.

A

Standard

413
Q

A point in time associated with a schedule activities start, usually qualified by one of the following: actual, planned, estimated, scheduled, early, late, target, baseline, or current.

A

Start Date

414
Q

A logical relationship in which a successor activity cannot finish until a predecessor activity has started.

A

Start-to-Finish (SF)

415
Q

A logical relationship in which a successor activity cannot start until a predecessor activity has started.

A

Start-to-Start (SS)

416
Q

A narrative description of products, services, or results to be delivered by the project.

A

Statement of Work (SOW)

417
Q

Choosing part of a population of interest for inspection.

A

Statistical Sampling

418
Q

A dependent activity that logically comes after another activity in a schedule.

A

Successor Activity

419
Q

A group of related schedule activities aggregated and displayed as a single activity.

A

Summary Activity

420
Q

Analysis of strengths, weaknesses, opportunities, and threats of an organization, project, or potion.

A

SWOT Anaylsis

421
Q

Personal knowledge that can be difficult to articulate and share such as beliefs, experience, and insights.

A

Tacit Knowledge

422
Q

Determining the appropriate combination of processes, inputs, tools, techniques, outputs, and life cycle phases to manage a project.

A

Tailoring

423
Q

A document that records the team values, agreements, and operating guidelines, as well as establishing clear expectations regarding acceptable behavior by project team members.

A

Team Charter

424
Q

A component of the resource management plan that describes when and how team members will be acquired and how long they will be needed.

A

Team Management Plan

425
Q

A defined systematic procedure employed by a human resource to perform an activity to produce a product or result or deliver a service, and that may employ one or more tools.

A

Technique

426
Q

A partially complete document in a predefined format that provides a defined structure for collecting, organizing, and presenting information and data.

A

Templates

427
Q

Project documents that describe the activities used to determine if the product meets the quality objectives stated in the quality management plan.

A

Test and Evaluation Documents

428
Q

A risk that would have a negative effect on one or more project objectives.

A

Threat

429
Q

A technique used to estimate cost or duration by applying an average or weighted average of optimistic, pessimistic, and most likely estimates when there is uncertainty with the individual activity estimates.

A

Three-Point Estimating

430
Q

A predetermined value of a measurable project variable that represents a limit that requires action to be taken if it is reached.

A

Threshold

431
Q

A type of contract that is a hybrid contractual arrangement contains aspects of both cost-reimbursable and fixed-price contracts.

A

Time and Material Contract (T&M)

432
Q

A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal, expressed as a ratio of the cost to finish the outstanding work to the remaining budget.

A

To-Complete Performance Index (TCPI)

433
Q

The quantified description of acceptable variation for a quality requirement

A

Tolerance

434
Q

Something tangible, such as a template or software program, used in performing an activity to produce a product or result.

A

Tool

435
Q

A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables.

A

Tornado Diagram

436
Q

The amount of time that a schedule activity can be delayed or extended from it’s early start date without delaying the project finish date or violating a schedule constraint.

A

Total Float

437
Q

An analytical technique that uses mathematical models to forecast further outcomes based on historical results.

A

Trend Analysis

438
Q

An event or situation that indicates that a risk is about to occur.

A

Trigger Condition

439
Q

Agreement by everyone in the group on a single course of action

A

Unanimity

440
Q

A modification to any deliverable, project management plan component, or project document that is not under formal change control.

A

Update

441
Q

The process of formalizing acceptance of the completed project deliverables.

A

Validate Scope

442
Q

The assurance that a product, service, or result meets the needs of the customer and other identified stakeholders. Contrast with verification.

A

Validation

443
Q

A quantifiable deviation, departure, or divergence away from a known baseline or expected value.

A

Variance

444
Q

A technique for determining the cause and degree of difference between the baseline and actual performance

A

Variance Analysis

445
Q

A projection of the amount of budget deficit or surplus, expressed as the difference between the budget at completion and the estimate at completion.

A

Variance At Completion (VAC)

446
Q

An actual condition that is different from the expected condition that is contained in the baseline plan.

A

Variation

447
Q

The evaluation of whether or not a product, service, or result complies with a regulation, requirement, specification, or imposed condition. Contrast with Validation.

A

Verification

448
Q

Completed project deliverables that have been checked and confirmed for correctness through the Control Quality process.

A

Verified Deliverables

449
Q

Groups of people with a shared goal who fulfill their roles with little or no time spent meeting face to face.

A

Virtual Teams

450
Q

A planning technique used to provide products, services, and results that truly reflect customer requirements by translating those customer requirements into the appropriate technical requirements for each phase of project product development.

A

Voice of the Customer

451
Q

A document that provides detailed deliverable, activity, and scheduling information about each component in the work breakdown structure.

A

WBS Dictionary

452
Q

The process of evaluating scenarios in order to predict their effect on project objectives.

A

What-If Scenario Analysis

453
Q

A hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables.

A

Work Breakdown Structure (WBS)

454
Q

An entry in the work breakdown structure that can be at any level.

A

Work Breakdown Structure Component

455
Q

The work defined at the lowest level of the work breakdown structure for which cost and duration are estimated and managed.

A

Work Package

456
Q

The raw observations and measurements identified during activities being performed to carry out the project work.

A

Work Performance Data

457
Q

The performance data collected from controlling processes, analyzed in comparison with project management plan complines, project documents, and other work performance information.

A

Work Performance Information

458
Q

The physical or electronic representation of work performance information compiled in project document, intended to generate decisions, actions, or awareness.

A

Work Performance Reports