PM2 Flashcards

1
Q

Project scheduling - a summary on the key steps

A

split work into separate tasks (minimize task dependencies)
estimate the calendar time needed to complete each task
estimate effort required
mostly needs PM intuition and experience

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Project scheduling process

A
software requirements and design information
identify activities
identify activity dependencies
estimate resources for activities
allocate people to activities
create charts
(revise and update three prev steps)
bar charts describing project schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What do gantt charts capture

A

task completion
simple dependencies
milestones and deliverables

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What cant a gantt chart handle (i.e. in situations would a gantt chart not convey the schedule properly)

A

when there are complex task dependencies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what are Kanban Boards

A

Visualize at a glance current project activities. Each task is represented as a single card

Stories - full list of tasks
To do - tasks planned for current cycle or phase
In progress - tasks that have been started
Testing - tasks that have been completed and are ready to undergo testing
Done - Tasks that are completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Network diagram critical path?

A

sequence of stages determining the minimum time needed for an operation
Minimum project duration depends on CP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Earliest start/finish

A

Earliest a task can begin/end if all preceeding tasks are completed in the shortest times

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Latest start/finish

A

Latest a task can begin/end without delaying the minimum project completion time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Critical path

A

chain that determines overall project duration

can be >= 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Slack/float

A

amount of surplis time or leeway allowed while still maintaining the critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Boehm’s top ten risk items

A
personnel shortfalls
unrealistic schedules/budgets
developing wrong functions
developing wrong UI
gold-plating
continuing stream of requirements changes
shortfalls in externally performed tasks
shortfalls in externally-furnished components
real time performance shortfalls
straining computer science capabilities
being blindsided by competition
outside interruptions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Name and explain the three M’s of risk management

A

Mitigation - reduce the risk (avoid, transfer, control)
Monitoring - what factors can we track
Management - contingency plan if risk becomes a reality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Planning vs management

A
planning = pre and post, network analysis, resourcing, risk, schedule
management = during, controlling resources and timescales
How well did you know this?
1
Not at all
2
3
4
5
Perfectly