1
Q

Which knowledge areas are part of initiating process group?

A

Integration and Communications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which knowledge areas are part of planning process group?

A

Integration, Scope, Time, Cost, Quality, Human Resource, Communications, Risk, Procurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which knowledge areas are part of Executing process group?

A

Integration, Quality, Human Resource, Communications, Procurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Which knowledge areas are part of Monitoring and controlling process group?

A

Integration, Scope, Time, Cost, Quality, Communications, Risk, Procurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which knowledge areas are part of Closing Process Group?

A

Integration, Procurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What process is part of Initiating and integration?

A

Develop Project Charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What process is part of Initiating and Communications?

A

Identify StakeHolders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What process is part of Planning and Integration?

A

Develop Project Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What process is part of Planning and Scope?

A

Collect Requirements, Define Scope, Create WBS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What process is part of Planning and Time?

A

Devine Activities, Sequence Activities, Estimate Activity Resources, Estimate Activity Durations, Develop Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What process is part of Planning and Cost?

A

Estimate Costs, Determine Budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What process is part of Planning and Quality?

A

Plan Quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What process is part of Planning and Human Resource?

A

Develop human resource plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What process is part of Planning and Communications?

A

Plan Communications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What process is part of Planning and Risk Management?

A

Plan Risk Management, Identify Risks, Perform Qualitative Risk Analysis, Perform Quantitive Risk Analysis, Plan Risk Responses

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What process is part of Planning and Procurement?

A

Plan Procurements

17
Q

What process is part of Executing and Integration?

A

Direct and manage project execution

18
Q

What process is part of Executing and Quality?

A

Perform Quality Assurance

19
Q

What process is part of Executing and Human Resource?

A

Acquire Project Team, Develop project team, manage project team

20
Q

What process is part of Executing and Communications?

A

Distribute Information, Manage stakeholder expectations

21
Q

What process is part of Executing and Procurement?

A

Conduct procurements

22
Q

What process is part of Monitoring and Controlling and Integration?

A

Monitor and Control Project work, Perform integrated change control

23
Q

What process is part of Monitoring and Controlling and Scope?

A

Verify Scope, control scope

24
Q

What process is part of Monitoring and Controlling and Time?

A

Control Schedule

25
Q

What process is part of Monitoring and Controlling and Cost?

A

Control Costs

26
Q

What process is part of Monitoring and Controlling and Quality?

A

Perform Quality Control

27
Q

What process is part of Monitoring and Controlling and Communications?

A

Report Performance

28
Q

What process is part of Monitoring and Controlling and Risk?

A

Monitor and control risks

29
Q

What process is part of Monitoring and Controlling and Procurement?

A

Administer procurements

30
Q

What process is part of Closing and Integration?

A

Close project or phase

31
Q

What process is part of Closing and Procurement?

A

Close Procurements