PM Knowledge Areas Flashcards
1
Q
List the PM Knowledge Areas
A
There are 10, numbered according to PMBOK Table 1-4
4) Project Integration Management
5) Project Scope Management
6) Project Schedule Management
7) Project Cost Management
8) Project Quality Management
9) Project Resource Management
10) Project Communications Management
11) Project Risk Management
12) Project Procurement Management
13) Project Stakeholder Management
2
Q
Project Integration Management
A
Initiating Process Group * 4.1 Develop Project Charter Planning Process Group * 4.2 Develop Project Management Plan Executing Process Group * 4.3 Direct and Manage Project Work * 4.4 Manage Project Knowledge Monitoring and Controlling Process Group * 4.5 Monitor and Control Project Work * 4.6 Perform Integrated Change Control Closing Process Group * 4.7 Close Project or Phase
3
Q
Project Scope Management
A
Planning Process Group * 5.1 Plan Scope Management * 5.2 Collect Requirements * 5.3 Define Scope * 5.4 Create WBS Monitoring and Controlling Process Group * 5.5 Validate Scope * 5.6 Control Scope
4
Q
Project Schedule Management
A
Planning Process Group * 6.1 Plan Schedule Management * 6.2 Define Activities * 6.3 Sequence Activities * 6.4 Estimate Activity Durations * 6.5 Develop Schedule Monitoring & Controlling Process Group * 6.6 Control Schedule
5
Q
Project Cost Management
A
Planning Process Group * 7.1 Plan Cost Management * 7.2 Estimate Costs * 7.3 Determine Budget Monitoring and Controlling Process Group * 7.4 Control Costs
6
Q
Project Quality Management
A
Planning Process Group * 8.1 Plan Quality Management Executing Process Group * 8.2 Manage Quality Monitoring and Controlling Process Group * 8.3 Control Quality
7
Q
Project Resource Management
A
Planning Process Group * 9.1 Plan Resource Management * 9.2 Estimate Activity Resources Executing Process Group * 9.3 Acquire Resources * 9.4 Develop Team * 9.5 Manage Team Monitoring and Controlling Process Group * 9.6 Control Resources
8
Q
Project Communications Management
A
Planning Process Group * 10.1 Plan Communications Management Executing Process Group * 10.2 Manage Communications Monitoring and Controlling Process Group * 10.3 Monitor Communications
9
Q
Project Risk Management
A
Planning Process Group * 11.1 Plan Risk Management * 11.2 Identify Risks * 11.3 Perform Qualitative Risk Analysis * 11.4 Perform Quantitative Risk Analysis * 11.5 Plan Risk Responses Executing Process Group * 11.6 Implement Risk Responses Monitoring and Controlling Process Group * 11.7 Monitor Risks
10
Q
Project Procurement Management
A
Planning Process Group * 12.1 Plan Procurement Management Executing Process Group * 12.2 Conduct Procurements Monitoring and Controlling Process Group * 12.3 Control Procurements
11
Q
Project Stakeholder Management
A
Initiating Process Group * 13.1 Identify Stakeholders Planning Process Group * 13.2 Plan Stakeholder Engagement Executing Process Group * 13.3 Manage Stakeholder Engagement Monitoring and Controlling Process Group *13.4 Monitor Stakeholder Engagement
12
Q
PM Knowledge Areas Acronym
A
I - 5 S - 2 S - 2 C - 2 Q - 3 R - 3 C - 3 R - 3 P - 3 S - 4