PM Knowledge Areas Flashcards

1
Q

List the PM Knowledge Areas

A

There are 10, numbered according to PMBOK Table 1-4

4) Project Integration Management
5) Project Scope Management
6) Project Schedule Management
7) Project Cost Management
8) Project Quality Management
9) Project Resource Management
10) Project Communications Management
11) Project Risk Management
12) Project Procurement Management
13) Project Stakeholder Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Project Integration Management

A
Initiating Process Group
* 4.1 Develop Project Charter
Planning Process Group
* 4.2 Develop Project Management Plan
Executing Process Group
* 4.3 Direct and Manage Project Work
* 4.4 Manage Project Knowledge
Monitoring and Controlling Process Group
* 4.5 Monitor and Control Project Work
* 4.6 Perform Integrated Change Control
Closing Process Group
* 4.7 Close Project or Phase
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Project Scope Management

A
Planning Process Group
* 5.1 Plan Scope Management
* 5.2 Collect Requirements
* 5.3 Define Scope
* 5.4 Create WBS
Monitoring and Controlling Process Group
* 5.5 Validate Scope
* 5.6 Control Scope
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Project Schedule Management

A
Planning Process Group
* 6.1 Plan Schedule Management
* 6.2 Define Activities
* 6.3 Sequence Activities
* 6.4 Estimate Activity Durations
* 6.5 Develop Schedule
Monitoring & Controlling Process Group
* 6.6 Control Schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Project Cost Management

A
Planning Process Group
* 7.1 Plan Cost Management
* 7.2 Estimate Costs
* 7.3 Determine Budget
Monitoring and Controlling Process Group
* 7.4 Control Costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Project Quality Management

A
Planning Process Group
* 8.1 Plan Quality Management
Executing Process Group
* 8.2 Manage Quality
Monitoring and Controlling Process Group
* 8.3 Control Quality
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Project Resource Management

A
Planning Process Group
* 9.1 Plan Resource Management
* 9.2 Estimate Activity Resources 
Executing Process Group
* 9.3 Acquire Resources
* 9.4 Develop Team
* 9.5 Manage Team
Monitoring and Controlling Process Group
* 9.6 Control Resources
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Project Communications Management

A
Planning Process Group
* 10.1 Plan Communications Management
Executing Process Group
* 10.2 Manage Communications
Monitoring and Controlling Process Group
* 10.3 Monitor Communications
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Project Risk Management

A
Planning Process Group
* 11.1 Plan Risk Management
* 11.2 Identify Risks
* 11.3 Perform Qualitative Risk Analysis
* 11.4 Perform Quantitative Risk Analysis
* 11.5 Plan Risk Responses
Executing Process Group
* 11.6 Implement Risk Responses
Monitoring and Controlling Process Group
* 11.7 Monitor Risks
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Project Procurement Management

A
Planning Process Group
* 12.1 Plan Procurement Management
Executing Process Group
* 12.2 Conduct Procurements
Monitoring and Controlling Process Group
* 12.3 Control Procurements
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Project Stakeholder Management

A
Initiating Process Group
* 13.1 Identify Stakeholders
Planning Process Group
* 13.2 Plan Stakeholder Engagement
Executing Process Group
* 13.3 Manage Stakeholder Engagement
Monitoring and Controlling Process Group
*13.4 Monitor Stakeholder Engagement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

PM Knowledge Areas Acronym

A
I - 5
S - 2
S - 2
C - 2
Q - 3
R - 3
C - 3
R - 3
P - 3
S - 4