PM Final Flashcards
Type of data needed for PERT analysis
Optimistic, pessimistic, average time for a task, Ts, critical paths?
PV
planned value of time anticipated
On gantt will have 0% until started and 100% when finished
EV
Earned value
0/100 rule–gives credit when work is completed (used for short duration projects)
50/50 rule–give 50% of value when started and 50% when finished (popular for short projects)
monitoring gates–gives points during stage process
AC
actual cost of work performed
BAC
total planned value of a project
CV
cost variance
CPI
cost performance index which is a measure of cost efficiency
most commonly accepted index
TCPI
To complete performance index
How much each dollar must create in value to stay in budget
SV
scheduled variance. negative number means work that was supposed to be finished has not been
but only true measure of variance is to compare project network to network schedule
SPI
scheduled performance index which is used to measure schedule efficiency
CP
critical path.
PCIB
what percentage of completed work has been on budget. shows how much of the project has been completed more or less
PCIC
what percentage has been completed based on revised estimates of total project costs
uses more accurate and up to date information
EACf
Forecasted estimate cost at completion
VAC
forecasted cost variance at completion. Positive means project will be completed under budget, negative over budget
VACe
revised estimate cost variance. positive means under, negative over budget
Types of resource issues
People
Materials
Equipment
Two types of scheduling problems
Time-constrained projects–must be done by a certain date
Resource constrained project–level of resource cannot go over a certain level
Leveling
delay noncritical activities by using up positive slack
Used for time constrained projects
Heuristics
Not always gives optimal result but is good for complex networks
Parallel method is widely used
Alternative to heuristics
Using linear programming to solve resource scheduling–hard to do due to large amount of data needed
Heuristic priorities
- minimum slack
- smallest duration
- lowest activity ID
Splitting
splits continuous work by interrupting work and sending resource to another task.
Bad when tasks have large start up or shutdown costs, interrupts people’s mental state
Time-phased budget baseline
A budget that breaks tasks into time and cost
CCPM
Critical chain project management
Use 50/50 estimate to discourage parkinsons law, student syndrome and self protection
Need to include buffers like (project, feeder and resource)
Tracking gantt chart
shows progress
Project baseline
Shows what deviations from the plan are