PM Exam 2 Flashcards
Cost Plus Fixed Fee
the buyer reimburses the seller for the seller’s allowable costs plus a fixed amount of profit.
Gold Plating
done intentionally or knowingly for some strategic purpose. That by adding the extra features, future projects could be accepted
How to calculate stakeholder communication channels
((# of Stakeholders + PM) * (# of Stakeholders + PM – 1))/2
When are Project Deliverables Defined?
scope planning
Risk Exploitation
meant for positive situations.
Risk Mitigation
where you have a strategy to either reduce the risk impact or probability
Risk Acceptance
there is nothing you can do about situations not in your control
Balanced Matrix
Power resides equally distributed between the functional and project manager.
Weak Matrix
is more like a Functional Organization where the project manager has almost no authority.
In What type of management structure are the lines of authority clearly defined?
Functional
What are the parts of the management quality audit process?
Quality Audits
When does Define Activities take place?
Refinement Stage
What does the project quality management process address?
management of the project and the product. It improves project management as well as the quality of the product
Schedule Network Diagram
visualizes the sequential and logical relationship between tasks in a project setting
Backward Pass
Used to calculate the Late Start and Late Finish of all the activities in the network diagram.
Forward Pass
Early Start and Early Finish,
Work Authorization System
It defines how work will be authorized and how work will be done at the right time and in the right sequence.
Calculating Estimate at Completion
EAC = Actual Cost + (Budgeted AC - Estimated Value)
Earned Value Analysis
used to measure performance based on Scope, Schedule, and Cost.
Who Came Up With Continuous improvement
Deming Cycle – PDCA(Plan Do Check Act)
WBS Dictionary
Provides detailed deliverable, activity and schedule information of each component in the WBS
Qualitative Risk Analysis
Identifying Risks, How likely they are to happen and potential impacts if they do.
Quantitative Risk Analysis
Assign numerical value to each risk based on data collected by the project team.
Resource Breakdown Structure
Shows various resources, both human and mechanical, needed for the project.
Fast Tracking
schedule compression technique of performing activities in parallel ( may result in increased risk and rework)
Statement of Work
An SOW is a description of products to be delivered to the project by the vendor
Develop Schedule
Analyzing-
Activity Sequences
Constraints
Durations
Requirements
Delphi Technique
anonymously information gathering technique
Achievement Theory of Motivation
States there are three types of motivational needs: need for achievement, need for authority, and power, and need for affiliation.