PM Exam Flashcards

1
Q

Teams have a vision statement before they begin a new project for what purpose

A

Lists the goal that team or company is ultimately trying to achieve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Team member says that he greatly appreciates leaders who support team s physical and mental health is a type of what leadership

A

Healing leadership

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Listening leadership

A

Ability to attend to other s opinions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Stewardship leadership

A

Means being responsible and working alongside the team to accomplish the work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Empathy leadership

A

Understanding other people s emotions and being sensitive to their feelings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

PM gathers a large group of potential stakeholders and evaluate their skills all at once. Method is called

A

Focus groups

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Focus groups

A

Way to assess skills that stakeholders possess and function like a group interview

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Skills matrix

A

Chart that displays various skills and whether team has them or not

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Survey

A

Series of questions that participants answer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Peer reviews

A

Teammates rating and analyzing each other’s performances

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Stakeholder explains one of her suggestions to team, and team later complains that the suggestion makes it more difficult for them to pursue their own interests for the project. What should team do?

A

Teams should work to meet the expectations of the stakeholder

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Stakeholders

A

Have influence over the project because they have Personal interest in seeing it succeed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Which of following is NOT an aspect of emotional intelligence

A

A. Motivation
B. Social skills
C. Empathy
D. Foresight

D foresight

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Cost variance (CV)

A

Actual costs subtracted from the earned value using equation
CV=EV-AC

Cost variance= earned value - actual costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Project budget = $150,000
30% of projected work has been completed
Earned value=$50,000
PM spent $55,000
What is cost variance

A

EV= $150,000 *.30=$50,000
CV= EV- AC
CV= $50000-55,000

Cost variance is $5000

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Schedule Variance (SV)

A

Difference between how much of work of project was planned to have been completed and how much work has actually been completed

17
Q

Schedule Variance (SV)

A

SV=EV-PV

Schedule variance=earned value minus how much work actually completed

SV= earned volume - planned volume

18
Q

Schedule variance (SV)

Project planned by 6 months =50%
Planned value after 6 months =$75000
30% of work completed after 6 months
Earned value is $50000
What is SV

A

SV ( schedule variance)

SV=EV-PV

$50000-$75000= -$25000

19
Q

Cost Performance Index (CPI)

A

Amount of work completed per dollars spent

CPI= EV/ AC

Cost performance index = earned value divided by actual costs spent

20
Q

CPI problem example

A

Earned value = $50000
Actual costs= $55000
CPI = 0.91
Means project loses $.09 for every dollar spent, which will result in total loss of $18,000 if project continues on same performance rate

21
Q

Schedule performance index (SPI)

A

Measurement of how closely the project is following the planned schedule

SPI= EV/ PV

22
Q

Schedule performance Index (SPI)

A

Earned value = $50000
Planned value = $75000

SPI= EV/PV

$50000/$75000= 0.67 SPI

23
Q

Estimate at Completion (EAC)

A

Projection of how much project will cost to complete based on current project performance

24
Q

EAC

A

Estimate at completion

EAC= AC ( BAC-EV/ CPI x SPI)

25
Q

Estimate at completion (EAC) example

A

Project budget=$150,000
Earned value=$50,000
Planned value after 6 months= $75,0000
SV= -$25,000
Actual cost=$55,000
CPI= 0.91
SPI= 0.67

EAC= $55,000 + ( $200,000 - $50,000/ 0.91 x 0.67)
EAC= $300, 901. 64

26
Q

To complete performance index (TCPI)

A

Predicts whether the project can be completed within the planned budget based on the current performance or whether it can be completed at the new EAC

27
Q

Determine if project can be completed within planned budget

TCPI= BAC - EV / BAC - AC

A

TCPI= 200,000-50,000/ 200,000-55,000

TCPI = ( 150,000/145,000)

TCPI=1.03

28
Q

Determine if project can be completed at new EAC

TCPI=BAC-EV/EAC-AC

A

TCPI = BAC- EV / EAC- AC

TCPI= 200,00-50,000/300,901.64 - 55,000

TCPI=150,000 /245, 901.64

TCPI= 0.61

29
Q

Estimate to Complete (ETC)

A

Estimate of how much money will be required to complete the project under the current conditions

ETC= EAC-AC

300, 901.64 - 55,000

ETC =245, 901.64