Planning For Success Flashcards

1
Q

What is Earned Value?

A

An assessment method used to calculate project performance at a given time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What would a variance of >0 signify when considering

A. Schedule
B. Cost

A

A: ahead of schedule if >0
B. Underspent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When considering Scheduled Performance index (SPI), what does a value <1 signify?

A

Behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How do you calculate schedule variance?

A

SV = earned value - planned value (PV)
SV = EV - PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the benefits of Earned value management ?

A

Measures efficiency of work done
Provides trend analysis
Provides tighter control as you are measuring elements of project
Focuses on useful work done

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the disadvantages of EVM?

A

Heavy on admin
Doesn’t consider quality , only delivery
Can be misrepresented or skewed if you have one area under performing and another over performing (takes a high level overview)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Calculate cost variance

A

cV = EV - actual cost (AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is critical chain?

A

A resource based approach to scheduling, ensuring resource is constantly utilised.

Implements buffer on activities to prevent over run

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the 3 ways to analyse critical path?

A

Forward pass - overall duration of project (early finish = early start + duration)

Backward pass - latest time activities can start (late start = late finish - duration )

Float - where and when there is flexibility in time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the difference between resource levelling and smoothing ?

A

Use levelling when resource is limited and can result in a delay to project.

Smoothing used when time is constrained and ensures resources are used efficiently - no effect on duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Explain 2 stages of configuration management

A

Planning -
Identification -
Control -
Status Accounting -
Audit -

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Name 6 stages of information management

A

Collection
Storage
Curation
Analysis
Archiving
Destruction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What do you find in a project management plan?

A

Scope - work breakdown structure
Resource - organisation breakdown structure
Cost - cost breakdown structure
Communication - communication plan
Risk management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the Responsibility Assignment Matrix (RAM) made up of

A

Organisation breakdown structure
And
Work breakdown structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What would you find contained in a Business Case?

A

Justification for the project - why needed and why this approach over other option

Strategic Objectives
Options - what has been considered and chosen - rationale?
Benefits - expected from the project
Commercial elements - Cost, Investment Appraisal and funding
Risk evaluation high level - alternate options
Timescale - summary of delivery and realistic timeline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
A