Planning and Monitoring Flashcards
1
Q
What is the purpose of release planning?
A
To plan/schedule work at a high level and feed into the iteration planning
2
Q
How many sprints ahead does a release plan have?
A
3-12
3
Q
Are dates included in a release plan?
A
YES – start and end dates for sprints and any hard deadlines
4
Q
What are the inputs for release planning?
A
Input is a prioritised and estimated Product backlog, the (estimated) velocity of the team
5
Q
What is a release plan?
A
- A release plan forecasts how a major release is developed.
- It’s a type ofAgile project plan and it usually covers the next three to six months.
6
Q
Product Roadmap
A
A high-level strategic plan of major stages of a road trip.
7
Q
Product Roadmap vs Release Plan
A
A product roadmap is a tactical plan with more detail on each stage of the road trip